Recorded by a reporter from Lao Dong Newspaper on August 21, at column 8 at the top of Ngang Pass in Ky Nam commune, Ky Anh town (bordering Quang Binh province), a group of about 20 workers of the Communications Company Ha Tinh power transmission is constructing and erecting the top of the pole body.
In particular, about 7 workers are hanging on the top of the column to complete the final erection, while below more than a dozen workers are transporting iron bars for the crane to bring to the top of the column for the group on the column to proceed with the assembly. column.
This is the position of the 2-stem column. The rope next to the column has completed pulling the rope. A few workers are still climbing on the column body and have pulled the rope to check, review, and tighten the last screws to ensure stability. sure.
Mr. Nguyen Truong Sinh - technical officer of Ha Tinh Power Transmission Company - said that if the construction effort ends on August 21, we will be able to hand over the pole to the wire pulling unit to carry out pulling the wire on the pole from tomorrow. .
"We have made great efforts and determination to have the project completed soon before September 2 as directed by the Prime Minister" - Mr. Sinh shared.
At column number 40 in Ky Thinh ward, Ky Anh town, the road to the column is located halfway up a high mountain, making moving up very difficult and dangerous. Here, workers are pulling the rope.
The weather was hot so the workers were tired, but they all tried their best because these were the last days of a key national project that was about to be completed. They are about to go home after a long period of intense concentration on construction to reach the finish line.
Here are some pictures that Lao Dong Newspaper reporter recorded at the construction site: