On 7.2, the Standing Committee of the Steering Committee (Steering Committee) of the Ring Road Project 4 - Hanoi Capital Region held a conference to urge the progress of the implementation of the Ring Road 4 project, the section passing the territory of Bac Ninh province.
Currently, construction and installation packages No. 14, 15 and 16 of the 2.3 component project are speeding up the construction progress.
The total construction output reaches 24.1%, specifically: the construction output of package No. 14 reaches 33.4%; Bidding package No. 15 reaches 22.64%; Package No. 16 reaches 17.55%.
The investor directed and urged the contractor to speed up the construction of the sections that were present, ensuring the schedule as committed.
Regarding the compensation, support and site clearance (land clearance): 100% of the area of agricultural land, farm and land is difficult to cultivate; The remaining 10 hectares of residential land, land allocated illegally, irrigation land, intersection, claws ... localities are urgently planning compensation, support, solving problems, striving to hand over Done the ground in the first quarter.
The contractor is speeding up the relocation of technical infrastructure works of 110kV, 220kV and 500KV electrical infrastructure; Move the 0.4KV-35KV electrical system, telecommunications system, irrigation works.
Disbursement value in 2024 reached 68%; In 2025, disbursed 91.57/100 billion VND for component projects 1.3. The localities are urgently building 10 resettlement areas, soon handing over residential land to people with land with recovered and stable life.
Chairman of the People's Committee of Bac Ninh Province Vuong Kingdom requested, in terms of the point of view, he must continue to act fiercely, unify the will, just do it, do not go back, resolutely finish the entire project in 2025.
Regarding land clearance, Chairman of Bac Ninh People's Committee requires localities to create the best conditions for the people in compensation and support in the spirit of in accordance with the provisions stay, the lives of people with land are recovered.
In the process of propaganda, advocacy, it must be clearly and specifically for the people to grasp the provisions of law, mechanisms and support policies of the province, and at the same time strongly propagate the effects of the project, The cohesion with other projects, creating consensus and highly spread effects among the people.
At least 20.3, localities must complete the land clearance work, this is the last time to complete the project progress at the end of this year.
The Steering Committee of Bac Ninh province requires the heads of localities to be responsible to the province for the progress of land clearance for the project. In parallel with that, the enforcement plan must be developed for cases of intentional failure to comply with and associated with ensuring security and order.