Nearly 1,500 billion VND lake project in Dak Lak begins to store water

BẢO TRUNG |

Dak Lak - The contractor has begun blocking the construction flow and storing water at the Ea Tam irrigation lake project.

On March 14, the People's Committee of Buon Ma Thuot city (Dak Lak province) held a ceremony to block the construction and storage of water at the Ea Tam irrigation lake project.

Ea Tam Irrigation Reservoir is a key project of Dak Lak province as well as Buon Ma Thuot city. The project has a total investment of 1,468.5 billion VND.

Of which, 700 billion VND is invested from government bond capital and 768 billion VND from local capital and other legal sources.

Mot goc du an ho thuy loi Ea Tam dang trong qua trinh thi cong. Anh: Bao Trung
A corner of the Ea Tam irrigation lake project is under construction. Photo: Bao Trung

When completed, the Ea Tam Irrigation Reservoir Project will ensure the regulation of over 1 million m3 of water to serve domestic water for about 25,000 people in the city and neighboring areas.

Thereby, contributing to reducing the impact of climate change, creating environmental landscapes, contributing to increasing groundwater levels in the area. This also promises to be a place to exploit tourism potential, call for investment and expand urban space around the project area.

Du an da chinh thuc chan dong
The project has begun to block the construction flow and store water. Photo: Bao Trung

Mr. Tran Duc Nhat, Vice Chairman of Buon Ma Thuot City People's Committee, said: "Blocking the construction flow and storing water aims to complete the entire project before the main flood in the 2025 crop".

According to Mr. Nhat, the City Construction Investment Project Management Board (representing the investor) and related units focus on organizing appraisal and approving measures to organize flow control and construction to overcome floods. Thereby, ensuring absolute safety for the project and people in the area.

Cac mui thi cong bat dau cong viec duoc giao. Anh: Bao Trung
The construction teams have started the assigned work. Photo: Bao Trung

"Relevant units organize the preparation and submission of appraisal and approval of natural disaster response plans for the project and downstream areas of the dam during the construction process," Mr. Nhat added.

Mr. Do Duc Thong - General Director of Dak Lak Construction Joint Stock Company (representative of the construction contractor consortium) said: "We will organize construction and installation in accordance with the design and technical documents approved by competent authorities. The construction teams will take advantage of the sunny time to work overtime and increase teams to ensure the completion of the project progress as set out".

Previously, Lao Dong Newspaper reported that the Ea Tam irrigation lake project, with a total investment of nearly 1,500 billion VND in the center of Buon Ma Thuot city, is facing many difficulties, the site clearance and construction progress have not met expectations...

The project is divided into two phases: Phase 1 (2017 - 2020) focuses on site clearance for the lake bed, roads and main items.

Phase 2 (2021 - 2024) will deploy site clearance for connecting routes, install drainage and lighting systems. However, as we have entered 2025, many items are still unfinished, affecting people's lives.

BẢO TRUNG
RELATED NEWS

2 social housing projects are preparing to be implemented in Long Bien

|

Hanoi - In 2025, the city will implement 2 social housing projects in Long Bien.

HCMC - Binh Duong breaks through infrastructure with 5 projects worth tens of thousands of billions

|

Expanding National Highway 13, the road connecting Ho Chi Minh City - Chon Thanh Expressway, Ring Road 3, Ring Road 4, and extending Metro Line 1 to increase connectivity between Ho Chi Minh City and Binh Duong.

Bac Ninh names 5 projects causing great loss and waste

|

Bac Ninh - The Provincial People's Committee has just named 5 projects that are behind schedule, have long backlogs, and are ineffective, causing great loss and waste.

Ea Tam irrigation reservoir worth nearly 1,500 billion VND is behind schedule and has many problems

|

The Ea Tam irrigation reservoir project, with a total investment of nearly 1,500 billion VND in the center of Buon Ma Thuot city, is facing many difficulties, the progress of site clearance and construction has not met expectations...

U23 Vietnam vs U23 Korea Preview in the 3rd place match of the AFC U23 Championship

|

Football prediction U23 Vietnam vs U23 Korea in the 3rd place match of the 2026 AFC U23 Championship taking place at 10:00 PM tonight (January 23).

U23 Vietnam players and the opportunity to join the national team

|

Some U23 Vietnam players have enough capacity and desire to try their hand at the national team after the 2026 AFC U23 Championship.

Focus on implementing three strategic breakthroughs, bringing Vinh Long to rapid and sustainable development

|

The 14th National Party Congress is a major political event of the country, deciding strategic issues for the future and destiny of the nation, unleashing all resources and development motivation. To help readers have a comprehensive and objective view of the contributions of the Vinh Long Provincial Party Committee Delegation at the Congress, as well as the solutions of the Provincial Party Committee in thoroughly grasping and effectively implementing the Resolution of the 14th Party Congress, reporters of Vinh Long Newspaper and Radio, Television interviewed comrade Tran Tri Quang - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee about the above content.

Comrade Ha Quoc Tri: shifting from "passive to proactive" inspection and supervision, not allowing serious violations to occur

|

Ladies and gentlemen! In the term of the 13th Party Congress, the work of inspection, supervision, and Party discipline has achieved many important results; focusing on inspecting party members and Party organizations when there are signs of violations, thereby detecting, rectifying and handling them promptly. However, according to assessments, inspection and supervision work is still passive (i.e., inspection and supervision are only carried out when there are signs of violations).

2 social housing projects are preparing to be implemented in Long Bien

KHÁNH AN |

Hanoi - In 2025, the city will implement 2 social housing projects in Long Bien.

Chi tiết dự án đường nối KCN Nam Thăng Long - Vành đai 3,5

Hữu Vũ |

Dự án đầu tư xây dựng tuyến đường nối khu công nghiệp (KCN) Nam Thăng Long - Vành đai 3,5 nhằm kết nối KCN với các tuyến giao thông, thúc đẩy kinh tế xã hội.

HCMC - Binh Duong breaks through infrastructure with 5 projects worth tens of thousands of billions

MINH QUÂN |

Expanding National Highway 13, the road connecting Ho Chi Minh City - Chon Thanh Expressway, Ring Road 3, Ring Road 4, and extending Metro Line 1 to increase connectivity between Ho Chi Minh City and Binh Duong.

Bac Ninh names 5 projects causing great loss and waste

Trần Tuấn |

Bac Ninh - The Provincial People's Committee has just named 5 projects that are behind schedule, have long backlogs, and are ineffective, causing great loss and waste.

Ea Tam irrigation reservoir worth nearly 1,500 billion VND is behind schedule and has many problems

BẢO TRUNG |

The Ea Tam irrigation reservoir project, with a total investment of nearly 1,500 billion VND in the center of Buon Ma Thuot city, is facing many difficulties, the progress of site clearance and construction has not met expectations...