Freshwater lake project worth over VND1,300 billion in Tra Vinh is gradually taking shape

HOÀNG LỘC |

Tra Vinh - The project to build freshwater reservoir infrastructure has been completed by 23% since October 2024, promising to support agriculture and people's lives in the dry season.

The joy of farmers in Tra Vinh

According to the reporter's records, at the construction site of the Tra Vinh province freshwater reservoir infrastructure project, workers are urgently constructing to complete the project on schedule.

Not happy that the locality is about to have a freshwater reservoir, Ms. Tran Thi Nhat in Cang Long district, Tra Vinh province said that this project brings great hope to local people, having a source of fresh water will help farmers protect their crops and avoid damage caused by salinity intrusion.

According to Ms. Nhat, in the past, in the dry season, when the water was salty, the trees died, or the productivity was low, the quality of the fruit was not as good as the large quantity.

"I hope the Tra Vinh freshwater reservoir infrastructure project will be completed on schedule, so that local people can soon have stable freshwater use, ensuring both plant varieties and household activities," Ms. Nhat added.

Anh: Hoang Loc
The freshwater infrastructure construction project started in October 2024 and is expected to be completed in April 2026. Photo: Hoang Loc

Sharing the same joy, Ms. Le Thi Lung in Cang Long district, Tra Vinh province said that the Freshwater Infrastructure Project is about to be completed and she is very happy. She looks forward to having a source of fresh water every day in the dry season.

According to Ms. Lung, every time there is a shortage of fresh water, her family always has to save a little bit from watering the plants to using them in daily life, which is very difficult and greatly affects her family's life.

"I hope the project will be completed soon so that fresh water can be used stably, improving life because there is a source of fresh water throughout the year, bringing high productivity in agriculture," Ms. Lung added.

Expected to be completed in April 2026

Talking to Lao Dong, Mr. Lam Hoang Vu - Investor in the construction of freshwater reservoir infrastructure in Tra Vinh province said that the Tra Vinh freshwater reservoir infrastructure construction project, which has been implemented since October 2024, has now been completed 23%.

According to Mr. Vu, the project is being implemented on schedule and promises to be an important solution in providing stable fresh water for Tra Vinh people, contributing to solving urgent problems with clean water during the dry season.

Anh: Hoang Loc
Mr. Lam Hoang Vu - Investor in the construction of freshwater reservoir infrastructure in Tra Vinh province informed about the project construction progress. Photo: Hoang Loc

This project not only helps solve the problem of saline intrusion, protect domestic water resources, but also supports sustainable agricultural production, especially for areas specializing in rice and fruit growing.

Ensuring a stable source of fresh water will help people minimize damage caused by climate change and prolonged drought.

This is a key project to celebrate the Tra Vinh Provincial Party Congress, so the investor will continue to urge contractors to speed up the construction progress to ensure the project is completed on schedule.

"The project will also facilitate the socio-economic development of the province, improve the quality of life of the people and contribute to the sustainable development of Tra Vinh in the future," Mr. Vu added.

The total investment capital of the project is more than 1,300 billion VND, of which the provincial budget is over 1,189 billion VND, the rest is the central budget capital of more than 141 billion VND. The implementation period is 600 days (expected to be completed in April 2026).

HOÀNG LỘC
TIN LIÊN QUAN

Many trees fell and broke in the dry season in Tra Vinh

|

Tra Vinh - On February 24, many trees in Tra Vinh City suddenly fell due to strong winds, fortunately not causing any human casualties.

Tra Vinh freshwater lake infrastructure construction reaches 20% after 4 months

|

Tra Vinh - After 4 months of construction, the Tra Vinh freshwater reservoir infrastructure project has reached over 20%, bringing hope to people in preventing saline intrusion.

Water recedes for construction of the largest freshwater lake in the West in Ben Tre

|

Ben Tre - The Lac Dia freshwater reservoir construction project is in the final stage to be completed in August 2025.

Big fire at phone store in Quang Binh

|

Quang Binh - A major fire at a phone store in Dong Hoi City, authorities urgently put out the fire and protected property.

Union news: 2 pension levels in the new increase

|

The union newsletter includes: Pension levels 1 and 2 in the new increase; Proposal for financial support for disadvantaged people to participate in voluntary social insurance...

Every doctor and medical staff deserves to be honored

|

The "Shining White Blouse" Award in Da Nang is awarded annually to honor doctors and nurses, but more than an award is their silent efforts and sacrifices.

The Ministry of Education and Training reduces 5 units, changes from January 1

|

According to Decree No. 37/2025/ND-CP of the Government, the organizational structure of the Ministry of Education and Training will be reduced from 23 to 18 units.

Haaland shines to help Man City defeat Tottenham

|

Erling Haaland scored the only goal to help Man City beat Tottenham, maintaining their top 4 position.

Many trees fell and broke in the dry season in Tra Vinh

HOÀNG LỘC |

Tra Vinh - On February 24, many trees in Tra Vinh City suddenly fell due to strong winds, fortunately not causing any human casualties.

Tra Vinh freshwater lake infrastructure construction reaches 20% after 4 months

HOÀNG LỘC |

Tra Vinh - After 4 months of construction, the Tra Vinh freshwater reservoir infrastructure project has reached over 20%, bringing hope to people in preventing saline intrusion.

Water recedes for construction of the largest freshwater lake in the West in Ben Tre

Thành Nhân |

Ben Tre - The Lac Dia freshwater reservoir construction project is in the final stage to be completed in August 2025.