The project to open the road 575 billion dong in Ha Tinh is still entangled

TRẦN TUẤN |

Ha Tinh - Ham Nghi Street project extended with a total investment of 575 billion VND is still entangled in site clearance after the delayed progress has had to apply for an extension.

On April 16, the reporter of the Lao Dong Newspaper, the Ham Nghi road project that extends the section near the joint with Highway 1 (bypass) has not been cleared so it has not been constructed.

Meanwhile, more than 1.2 km of Km4+740 - Km5+959 section of the 09XL package of this project has been completed construction from 2024.

Ham Nghi street construction project has a length of 3.3km with the beginning point connecting Highway 1 bypass of Ha Tinh City through Thach Dai commune, the end point connects to the branch of National Highway 8C through Thach Xuan commune.

The project has a total investment of 575 billion VND by the Management Board of the Construction Investment Project of Ha Tinh Province as an investor.

The Center for Land Fund Development and Geopolitical Technology of Ha Tinh Department of Agriculture and Environment is the unit of site clearance. The project has been implemented in November 2022.

On April 16, Mr. Ho Nhat Le - Director of Ha Tinh Land Fund Development and Technical Development Center - said that the remaining obstacle of Ham Nghi Street project has not been liberated.

The reason, according to Mr. Le, must complete the construction of the resettlement area and then relocate people and hand over the ground.

"Currently, it is currently approving the policy of building a resettlement area. The current problem is a part of resettlement households, and for households who do not resettle, it is already done," Le shared.

Goi thau XL09 cua Du an duong Ham Nghi keo dai da thi cong xong trong nam 2024, trong khi goi thau con lai hien van dang vuong mac mat bang chua giai phong duoc. Anh: Tran Tuan.
The 09XL package of Ham Nghi Street project has been completed in 2024, while the remaining bidding package is still having an unexplained ground. Photo: Tran Tuan.

According to the scope of site clearance (GPMB) approved, Ham Nghi street projects extend affecting land, houses and architectural works of 314 households in Thach Dai commune with a total area of ​​over 21 hectares.

Of which, 137 households were affected by residential land, 177 households were affected by agricultural land.

If only the scope of the main route land clearance (excluding collection road items), the project affects 136 residential land plots, estimated to arrange about 100 resettlement land lots.

Up to now, the agricultural land has completed compensation for 171 households with a total amount of more than 18.7 billion dong corresponding to the recall area of ​​13.3ha and has handed over 100% of the ground to the project construction unit.

The Ham Nghi road project is long progress, which should have been completed in 2024 but due to the clearance problems, the project adjustment to the June 2026 will be completed.

 

TRẦN TUẤN
RELATED NEWS

Many key projects in Nghe An, Quang Tri have difficulty because of clearance

|

Many key projects in Nghe An and Quang Tri have large investment capital, facing the risk of delayed progress due to site clearance (GPMB) facing many difficulties and obstacles.

Binh Dinh issued the deadline for clearance of Quy Nhon port

|

Binh Dinh - On April 13, Vice Chairman Nguyen Tu Cong Hoang concluded that resolving problems in land clearance and resettlement to expand Quy Nhon port.

Heavy rain during storm, many culverts in Gia Lai have risen

|

Gia Lai Storm No. 13 is making landfall, and many culverts along rivers and streams in mountainous areas have begun to rise.

Officials working abroad and integrating regularly internationally will be supported with 100% of their salary

|

The Government proposes that people working in foreign affairs and international integration who are regularly supported with 100% of their salary according to the current coefficient (excluding allowances).

Announcement of the 14th Conference of the 13th Party Central Committee

|

Implementing the full-term Working Program, from November 5, 2025 to November 6, 2025, in Hanoi, the 13th Party Central Committee held its 14th Conference to discuss and give opinions on the work of the 14th National Party Congress; Party building work and the political system; personnel work and a number of other important contents. General Secretary To Lam delivered the opening and closing speeches at the Conference.

Ho Chi Minh City Department of Construction speaks out about the proposal to convert gasoline motorbikes to electricity

|

HCMC - The renovation of gasoline motorbikes to electric vehicles to be officially implemented needs to continue to perfect the legal basis, technical regulations, safety standards...

Dak Lak bans people from going out in storm-affected areas from the afternoon of November 6

|

Dak Lak requires the ban on all people in areas affected by the storm until the storm passes, except for functional forces on duty.

Hundreds of officers and soldiers urgently reinforce Hoi An coast before storm No. 13

|

Da Nang - Hundreds of officers and soldiers of the Da Nang City Military Command urgently reinforced the Hoi An coast before Typhoon 13 made landfall.

Many key projects in Nghe An, Quang Tri have difficulty because of clearance

QUANG ĐẠI - HƯNG THƠ |

Many key projects in Nghe An and Quang Tri have large investment capital, facing the risk of delayed progress due to site clearance (GPMB) facing many difficulties and obstacles.

Binh Dinh issued the deadline for clearance of Quy Nhon port

Hoài Luân |

Binh Dinh - On April 13, Vice Chairman Nguyen Tu Cong Hoang concluded that resolving problems in land clearance and resettlement to expand Quy Nhon port.

Chậm giải phóng mặt bằng, Công viên Tuổi trẻ Thủ đô bị lãng phí

Minh Hạnh |

Hà Nội - Việc chậm giải phóng mặt bằng một phần Công viên Tuổi trẻ Thủ đô khiến khu vực này mất trật tự an toàn giao thông và lãng phí tài sản công.