The project to open the road 575 billion dong in Ha Tinh is still entangled

TRẦN TUẤN |

Ha Tinh - Ham Nghi Street project extended with a total investment of 575 billion VND is still entangled in site clearance after the delayed progress has had to apply for an extension.

On April 16, the reporter of the Lao Dong Newspaper, the Ham Nghi road project that extends the section near the joint with Highway 1 (bypass) has not been cleared so it has not been constructed.

Meanwhile, more than 1.2 km of Km4+740 - Km5+959 section of the 09XL package of this project has been completed construction from 2024.

Ham Nghi street construction project has a length of 3.3km with the beginning point connecting Highway 1 bypass of Ha Tinh City through Thach Dai commune, the end point connects to the branch of National Highway 8C through Thach Xuan commune.

The project has a total investment of 575 billion VND by the Management Board of the Construction Investment Project of Ha Tinh Province as an investor.

The Center for Land Fund Development and Geopolitical Technology of Ha Tinh Department of Agriculture and Environment is the unit of site clearance. The project has been implemented in November 2022.

On April 16, Mr. Ho Nhat Le - Director of Ha Tinh Land Fund Development and Technical Development Center - said that the remaining obstacle of Ham Nghi Street project has not been liberated.

The reason, according to Mr. Le, must complete the construction of the resettlement area and then relocate people and hand over the ground.

"Currently, it is currently approving the policy of building a resettlement area. The current problem is a part of resettlement households, and for households who do not resettle, it is already done," Le shared.

Goi thau XL09 cua Du an duong Ham Nghi keo dai da thi cong xong trong nam 2024, trong khi goi thau con lai hien van dang vuong mac mat bang chua giai phong duoc. Anh: Tran Tuan.
The 09XL package of Ham Nghi Street project has been completed in 2024, while the remaining bidding package is still having an unexplained ground. Photo: Tran Tuan.

According to the scope of site clearance (GPMB) approved, Ham Nghi street projects extend affecting land, houses and architectural works of 314 households in Thach Dai commune with a total area of ​​over 21 hectares.

Of which, 137 households were affected by residential land, 177 households were affected by agricultural land.

If only the scope of the main route land clearance (excluding collection road items), the project affects 136 residential land plots, estimated to arrange about 100 resettlement land lots.

Up to now, the agricultural land has completed compensation for 171 households with a total amount of more than 18.7 billion dong corresponding to the recall area of ​​13.3ha and has handed over 100% of the ground to the project construction unit.

The Ham Nghi road project is long progress, which should have been completed in 2024 but due to the clearance problems, the project adjustment to the June 2026 will be completed.

 

TRẦN TUẤN
RELATED NEWS

Many key projects in Nghe An, Quang Tri have difficulty because of clearance

|

Many key projects in Nghe An and Quang Tri have large investment capital, facing the risk of delayed progress due to site clearance (GPMB) facing many difficulties and obstacles.

Binh Dinh issued the deadline for clearance of Quy Nhon port

|

Binh Dinh - On April 13, Vice Chairman Nguyen Tu Cong Hoang concluded that resolving problems in land clearance and resettlement to expand Quy Nhon port.

Information appears that France will send soldiers to Ukraine

|

There are reports that France has sent troops to Ukraine for training, in the context of Russia's continuous strong reaction to the military presence of the West.

Live futsal match between Vietnam and Indonesia at SEA Games 33

|

Live football match between Vietnam and Indonesia futsal team at SEA Games 33 taking place at 4:00 p.m. on December 17.

Trinh Thu Vinh won 4 gold medals, breaking 3 records at SEA Games 33

|

December 17 witnessed the impressive performance of shooter Trinh Thu Vinh, affirming his position as the number one star of Vietnamese shooting at the 33rd SEA Games.

Revealing equipment and machinery worth over VND1,000 billion at Bach Mai Hospital, Facility 2

|

Ninh Binh - The investor and the construction unit are rushing to complete the installation of equipment and machinery at Bach Mai Hospital, Facility 2, to be ready for operation.

Coach Kim Sang-sik: U22 Vietnam will win the championship at Rajamangala

|

Coach Kim Sang-sik is confident that U22 Vietnam will win the 33rd SEA Games gold medal against host Thailand U22.

Gold prices surge, people buy and sell enthusiastically

|

Gold prices recovered after a decline, people with a busy demand for buying. Number of sellers continue to receive coupons waiting for transactions.

Many key projects in Nghe An, Quang Tri have difficulty because of clearance

QUANG ĐẠI - HƯNG THƠ |

Many key projects in Nghe An and Quang Tri have large investment capital, facing the risk of delayed progress due to site clearance (GPMB) facing many difficulties and obstacles.

Binh Dinh issued the deadline for clearance of Quy Nhon port

Hoài Luân |

Binh Dinh - On April 13, Vice Chairman Nguyen Tu Cong Hoang concluded that resolving problems in land clearance and resettlement to expand Quy Nhon port.

Chậm giải phóng mặt bằng, Công viên Tuổi trẻ Thủ đô bị lãng phí

Minh Hạnh |

Hà Nội - Việc chậm giải phóng mặt bằng một phần Công viên Tuổi trẻ Thủ đô khiến khu vực này mất trật tự an toàn giao thông và lãng phí tài sản công.