The project to open the road 575 billion dong in Ha Tinh is still entangled

TRẦN TUẤN |

Ha Tinh - Ham Nghi Street project extended with a total investment of 575 billion VND is still entangled in site clearance after the delayed progress has had to apply for an extension.

On April 16, the reporter of the Lao Dong Newspaper, the Ham Nghi road project that extends the section near the joint with Highway 1 (bypass) has not been cleared so it has not been constructed.

Meanwhile, more than 1.2 km of Km4+740 - Km5+959 section of the 09XL package of this project has been completed construction from 2024.

Ham Nghi street construction project has a length of 3.3km with the beginning point connecting Highway 1 bypass of Ha Tinh City through Thach Dai commune, the end point connects to the branch of National Highway 8C through Thach Xuan commune.

The project has a total investment of 575 billion VND by the Management Board of the Construction Investment Project of Ha Tinh Province as an investor.

The Center for Land Fund Development and Geopolitical Technology of Ha Tinh Department of Agriculture and Environment is the unit of site clearance. The project has been implemented in November 2022.

On April 16, Mr. Ho Nhat Le - Director of Ha Tinh Land Fund Development and Technical Development Center - said that the remaining obstacle of Ham Nghi Street project has not been liberated.

The reason, according to Mr. Le, must complete the construction of the resettlement area and then relocate people and hand over the ground.

"Currently, it is currently approving the policy of building a resettlement area. The current problem is a part of resettlement households, and for households who do not resettle, it is already done," Le shared.

Goi thau XL09 cua Du an duong Ham Nghi keo dai da thi cong xong trong nam 2024, trong khi goi thau con lai hien van dang vuong mac mat bang chua giai phong duoc. Anh: Tran Tuan.
The 09XL package of Ham Nghi Street project has been completed in 2024, while the remaining bidding package is still having an unexplained ground. Photo: Tran Tuan.

According to the scope of site clearance (GPMB) approved, Ham Nghi street projects extend affecting land, houses and architectural works of 314 households in Thach Dai commune with a total area of ​​over 21 hectares.

Of which, 137 households were affected by residential land, 177 households were affected by agricultural land.

If only the scope of the main route land clearance (excluding collection road items), the project affects 136 residential land plots, estimated to arrange about 100 resettlement land lots.

Up to now, the agricultural land has completed compensation for 171 households with a total amount of more than 18.7 billion dong corresponding to the recall area of ​​13.3ha and has handed over 100% of the ground to the project construction unit.

The Ham Nghi road project is long progress, which should have been completed in 2024 but due to the clearance problems, the project adjustment to the June 2026 will be completed.

 

TRẦN TUẤN
RELATED NEWS

Many key projects in Nghe An, Quang Tri have difficulty because of clearance

|

Many key projects in Nghe An and Quang Tri have large investment capital, facing the risk of delayed progress due to site clearance (GPMB) facing many difficulties and obstacles.

Binh Dinh issued the deadline for clearance of Quy Nhon port

|

Binh Dinh - On April 13, Vice Chairman Nguyen Tu Cong Hoang concluded that resolving problems in land clearance and resettlement to expand Quy Nhon port.

"Call for help" case suspected of being abused by stepmother: Baby once suffered a psychological shock

|

Hanoi - Relatives said that in the past, H often showed signs of panic and psychological trauma suspected of being abused by her stepmother.

Hoang Anh Gia Lai eliminates Thanh Hoa in the National Cup

|

On the evening of September 13, Hoang Anh Gia Lai defeated Thanh Hoa 2-0 in the qualifying round of LPBank Securities National Cup 2025-2026.

Apartment fire in central apartment building of Ho Chi Minh City

|

HCMC - Fire at an apartment on Pasteur Street, Ben Nghe Ward, fortunately did not cause any casualties.

Suing a company that owes wages, many workers in Gia Lai have their petitions returned to court

|

Gia Lai - Many workers sued Phuc Thinh Binh Dinh Company Limited for unpaid wages and benefits and were court-issued because they had not yet passed the mandatory mediation step.

Associate Professor, Dr. Tran Dinh Thien: There may be attacks using fake news to destroy leading enterprises

|

Associate Professor, Dr. Tran Dinh Thien - Member of the Prime Minister's Policy Advisory Council, former Director of the Vietnam Economic Institute - said that fake news is no longer a simple "social networking story" but has become a danger to the entire economy.

Many key projects in Nghe An, Quang Tri have difficulty because of clearance

QUANG ĐẠI - HƯNG THƠ |

Many key projects in Nghe An and Quang Tri have large investment capital, facing the risk of delayed progress due to site clearance (GPMB) facing many difficulties and obstacles.

Binh Dinh issued the deadline for clearance of Quy Nhon port

Hoài Luân |

Binh Dinh - On April 13, Vice Chairman Nguyen Tu Cong Hoang concluded that resolving problems in land clearance and resettlement to expand Quy Nhon port.

Chậm giải phóng mặt bằng, Công viên Tuổi trẻ Thủ đô bị lãng phí

Minh Hạnh |

Hà Nội - Việc chậm giải phóng mặt bằng một phần Công viên Tuổi trẻ Thủ đô khiến khu vực này mất trật tự an toàn giao thông và lãng phí tài sản công.