The 2,600 billion VND belt project connecting Ho Chi Minh City - Dong Nai is behind schedule

HÀ ANH CHIẾN |

Dong Nai - 3 main packages in the component project 3 of Ho Chi Minh City's Ring Road 3 passing through Nhon Trach district are behind schedule, with only 55% of the construction site completed.

On November 17, the People's Committee of Dong Nai province said it had requested the People's Committee of Nhon Trach district to speed up compensation and site clearance for the Ho Chi Minh City Ring Road 3 project.

According to the People's Committee of Dong Nai province, up to now, the locality has handed over 58.15/65 hectares of land compensation and clearance, reaching 89%. However, the construction area is only about 36.01 hectares, reaching 55% of the land.

Thi cong du an Vanh dai 3 - TPHCM, doan qua tinh Dong Nai. Anh: HAC
Construction of Ho Chi Minh City Ring Road 3 project, section through Dong Nai province. Photo: HAC

The Ho Chi Minh City Ring Road 3 project, through Dong Nai province, has 3 component projects including: component project 1A invested by My Thuan Project Management Board; component project 3 invested by Dong Nai Province Traffic Construction Investment Project Management Board.

As for component project 4 - compensation and resettlement support for Ho Chi Minh City Ring Road 3 through Dong Nai province, Nhon Trach District People's Committee is the investor in site clearance work.

For component project 3, invested by Dong Nai Province Traffic Construction Investment Project Management Board, over 11km long, there are 3 main construction packages.

Up to now, in package No. 26, construction has been carried out for 302/990 days (30% of implementation time), the completed volume has reached 7.5%, slower than the overall progress of the package.

In package No. 29, construction took 306/990 days (40% of implementation time), with the completed volume reaching 12%, slower than the overall progress of the package.

In package No. 32, construction took 41/835 days (5% of implementation time), with the completed volume reaching 2.5% of the contract value, behind the overall progress of the package.

The Component 3 project of Ho Chi Minh City Ring Road 3, the section passing through Dong Nai province, started construction on June 18, 2023 with a total investment of nearly VND 2,600 billion. It is expected to be completed in 2025 and put into operation from 2026.

The project starts at Km 0+000 in Vinh Thanh commune, Nhon Trach district, Dong Nai province. The end point is at Nhon Trach bridge in Long Tan commune, Nhon Trach district (continuing with component project 1A of Ho Chi Minh City Ring Road 3).

On the route, a 5km expressway will be built connecting component project 1A, Tan Van - Nhon Trach section at the intersection of provincial road 25B, with a scale of 4 lanes and a speed of 100 km/h.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Ho Chi Minh City builds 11 compact urban areas along Metro Lines 1, 2 and Ring Road 3

|

Ho Chi Minh City has just issued a plan to develop 11 compact urban areas along Metro lines 1, 2 and Ring Road 3 according to the TOD model.

Shape of Ring Road 3 through Cu Chi district after 14 months of construction

|

The atmosphere at the Ho Chi Minh City Ring Road 3 project passing through Cu Chi district is currently very bustling with the efforts of hundreds of workers working day and night to speed up the project's progress.

Ho Chi Minh City Ring Road 3 through Dong Nai clears 90% of land

|

Dong Nai - Component 3 project of Ho Chi Minh City Ring Road 3, section through Nhon Trach district, has cleared more than 90% of the land.

Tornado rips roofs off many households and factories in Phu Yen

|

Phu Yen - From yesterday afternoon (November 22) to this morning, in Dong Hoa town, there were 2 tornadoes, causing damage to many houses and factories.

EU suffers bitter consequences from new US sanctions on Russia

|

The latest US sanctions on Russia will affect the European Union (EU), according to experts.

Gold price today 11/23: Gold ring breaks the threshold of 86.5 million

|

Gold prices today, November 23, continued to increase sharply in both domestic and world markets.

Car overturned in the middle of the highway after colliding with a tractor-trailer

|

Binh Thuan - A pickup truck overturned in the middle of the Vinh Hao - Phan Thiet highway after colliding with a tractor-trailer. Traffic police closed one side of the road at the accident site to handle the situation.

Thanh Oai land auction: Few participants

|

On the morning of November 23, an auction of 23 land plots took place in Thanh Oai district, Hanoi.

Ho Chi Minh City builds 11 compact urban areas along Metro Lines 1, 2 and Ring Road 3

MINH QUÂN |

Ho Chi Minh City has just issued a plan to develop 11 compact urban areas along Metro lines 1, 2 and Ring Road 3 according to the TOD model.

Shape of Ring Road 3 through Cu Chi district after 14 months of construction

Anh Tú |

The atmosphere at the Ho Chi Minh City Ring Road 3 project passing through Cu Chi district is currently very bustling with the efforts of hundreds of workers working day and night to speed up the project's progress.

Ho Chi Minh City Ring Road 3 through Dong Nai clears 90% of land

HÀ ANH CHIẾN |

Dong Nai - Component 3 project of Ho Chi Minh City Ring Road 3, section through Nhon Trach district, has cleared more than 90% of the land.