Billion-dollar road used for more than a year has peeled off and degraded

Nguyễn Hoàn |

Bac Kan - The Nong Ha - Khe Thi route: DH.75 (Cho Moi) has been rapidly degraded, the road surface is peeling, and the rocks and gravel are unidespread.

According to the reporter's records at the end of March 2025, after more than 1 year of use, the Nong Ha - Khe Thi: DH.75 route through Nong Ha commune (Cho Moi, Bac Kan) has seriously degraded.

Many sections of the concrete road surface are peeling, revealing the layer of gravel and rocks lying around below. Notably, this situation has not happened recently but has appeared for a long time.

As a household with a house near the above road, Mr. Nguyen Van Thinh (character's name has been changed) in Ban Tet village, Nong Ha commune said that the road deterioration has been going on for a long time and has not been repaired yet.

Mr. Thinh shared that at first there were only a few small cracks, but over time, the road surface gradually peeled off, and many sections have now clearly revealed the rock and gravel layer below.

"I don't understand the quality of the project but it has been damaged after such a short time. If not repaired soon, this road will soon be more severely damaged," Mr. Thinh added.

gshs
The road is damaged and degraded despite not being in use for long. Photo: Nguyen Hoan

According to local people, this route has very few heavy trucks circulating, mainly cars, motorbikes and some small wood-carried vehicles.

With a not-so-large traffic volume, the road surface deterioration after a short time has made many people wonder about the quality of the project.

Informing reporters, a member of the project supervision team said that since the road was first poured, some sections have shown signs of deterioration and are not guaranteed.

Some people in the supervision team later gave their opinions on this issue but did not understand why the project was still accepted and put into use.

Nong Ha - Khe Thi road project: DH.75 through Nong Ha commune, Cho Moi district, Bac Kan province is invested by the Bac Kan Province Traffic Construction Investment Project Management Board, with a total investment of more than 13.2 billion VND.

The route is about 5km long, constructed by the Phu Thanh - Cao Ha joint venture, and started construction in November 2022, with a implementation period of 12 months.

Talking with Lao Dong Newspaper reporter, Mr. Vu Nhu Hoi - Chairman of Nong Ha Commune People's Committee - confirmed that the road was completed in 2023 and is now degraded. Some sections, routes, and concrete sections of the road surface are peeling, exposing the layer of gravel and rocks below.

The commune leader also said that the locality has reported to the People's Committee of Cho Moi district to have a plan to restore and repair the road to ensure urban aesthetics as well as make travel easier.

Some recorded images:

1
After more than 1 year of use, the Nong Ha - Khe Thi route: DH.75 has deteriorated. Photo: Nguyen Hoan
2
The road surface is printed with wheel spots, peeling concrete, revealing a layer of hazy gravel. Photo: Nguyen Hoan
3
Some sections and routes have long cracks on the concrete surface. Photo: Nguyen Hoan
4
The road deterioration after a short period of use has made people wonder about the quality of the project. Photo: Nguyen Hoan
5
A section through Ban Tet village, Nong Ha commune (Cho Moi, Bac Kan) has been degraded for a long time but has not been renovated or repaired yet. Photo: Nguyen Hoan
Nguyễn Hoàn
RELATED NEWS

By 2030, the degraded road will be completely repaired

|

Vinh Long - Due to limited transportation capital, the repair of the road connecting Long Ho town through Hoa Tinh commune, Mang Thit district is expected to be completed by 2030.

Danger lurks on the degraded suspension bridge in Bac Kan

|

Bac Kan - After many years of use, Na Deo suspension bridge (Cho Moi) has degraded, the solder, the bridge surface is cracked, posing a potential risk to the safety of people and vehicles.

The stadium used to have a capacity of 50,000 seats and is degraded

|

Without a professional team competing for a long time, Can Tho Stadium is in a state of disrepair.

A ward in Hanoi resolves land procedures overdue for 134 days, must apologize to citizens

|

Hanoi - Long Bien Ward is assessed as still having shortcomings and limitations when resolving administrative procedures on land, including dossiers that are overdue for 134 days.

Prenn Pass road closed in Da Lat for 6 days to repair landslide site

|

Lam Dong - Functional agencies decided to close Prenn Pass road for 6 days to repair and fix damaged points caused by previous landslides.

Forecast of the time to end widespread severe cold in the North

|

According to a representative of the meteorological agency, it is forecast that widespread severe cold and frost in the North will last until about January 10, to prevent frost and frost in mountainous areas.

Ho Chi Minh City launches campaign to handle sidewalk and roadway encroachment throughout the area

|

Ho Chi Minh City is deploying a peak period of inspection and handling of sidewalk and roadway encroachment throughout the area to restore urban order.

A restaurant yacht catches fire on the Saigon River

|

Ho Chi Minh City - Restaurant yacht on Saigon River suddenly catches fire, functional forces are controlling the fire.

By 2030, the degraded road will be completely repaired

HOÀNG LỘC |

Vinh Long - Due to limited transportation capital, the repair of the road connecting Long Ho town through Hoa Tinh commune, Mang Thit district is expected to be completed by 2030.

Danger lurks on the degraded suspension bridge in Bac Kan

Nguyễn Hoàn |

Bac Kan - After many years of use, Na Deo suspension bridge (Cho Moi) has degraded, the solder, the bridge surface is cracked, posing a potential risk to the safety of people and vehicles.

The stadium used to have a capacity of 50,000 seats and is degraded

Thanh Vũ |

Without a professional team competing for a long time, Can Tho Stadium is in a state of disrepair.