Clearance of 100% of land in the bypass project has not been completed after 19 years

Tân Văn |

Cao Bang - The city bypass construction project has all the land for construction.

The investment project to build the Cao Bang city bypass (old name) was approved in principle in 2006 and re-approved by the Ministry of Transport (old) in 2022 with a total investment of more than 221.88 billion VND.

The investor is the Department of Transport (GTVT) of Cao Bang province (now the Department of Construction). The route is 7.036 km long, passing through Thuc Phan and Tan Giang wards.

For many years, the project has been behind schedule because about 100m of site in Tan Giang ward has not been handed over.

Lanh dao tinh Cao Bang trao Quyet dinh 1846/QD-UBND cho gia dinh ong Ha Hai Long, Ha Nguyen Thuy. Anh: Nguyet Ha
Cao Bang Provincial leaders presented Decision 1846/QD-UBND to the family of Mr. Ha Hai Long and Mr. Ha Nguyen Thuy. Photo: Nguyet Ha

The main reason is problems related to land management between State-owned enterprises and Mr. Ha Hai Long - Ha Nguyen Thuy's household, along with errors in original legal documents, causing the determination of public and private land to prolong.

The dispute originated from Decision No. 779/QD-UB dated April 25, 2003 of the People's Committee of Cao Bang province, accordingly, Mr. Ha Hai Long's complaint about land use rights in the area of Mineral Company I. Although Mr. Long has continuously petitioned and complained for many years, the case has not been completely resolved.

Mat bang thi cong tuyen duong tranh da duoc giai phong 100%. Anh: Tan Van
The construction site of the bypass has been 100% cleared. Photo: Tan Van

Then, in 2004, Mr. Long transferred this land to his son - Mr. Ha Nguyen Thuy - to cultivate, build a house and live stably since 2006.

The land has houses, ancillary works, crops, fish ponds, and is the only place for the family to live. However, due to the old decision, the authorities do not have a basis for compensation, support, and resettlement.

In that situation, the Standing Committee of the Cao Bang Provincial Party Committee has directed the Provincial People's Committee and relevant departments and branches to review, consider and handle. On November 5, 2025, the People's Committee of Cao Bang province issued Decision No. 1846/QD-UBND, abolishing Decision No. 779/QD-UB (2003) on the grounds of "not in accordance with legal regulations". This is considered a turning point to remove the bottleneck that has lasted for 19 years, and at the same time paving the way for the handover of the site and construction of the project.

Mr. Ha Hai Long shared: "For my father and I, this is an indescribable joy. After many years of petitioning, now our rights have been guaranteed, we are ready to hand over the site to serve the project".

On November 11, informing reporters, a representative of the People's Committee of Cao Bang province said that up to now, the entire bypass site has been cleared and handed over.

Cac nha thau huy dong may moc thi cong tai vi tri vua giai phong xong mat bang. Anh: Tan Van
Contractors mobilized construction machinery at the site that had just been cleared. Photo: Tan Van
Thong tin du an. Anh: Tan Van
Project information. Photo: Tan Van

Contractors are mobilizing machinery and construction equipment, digging and filling the roadbed and breaking the intersection with National Highway 3, ensuring completion progress in 2025.

Mr. Nguyen Van Hoang - a resident of Thuc Phan ward - said: "When the road is completed, travel will be closer and more convenient. Everyone hopes the project will be completed soon".

Tân Văn
RELATED NEWS

Directing the completion of the bypass road under construction for nearly 2 decades

|

Cao Bang - The Cao Bang City bypass was built in 2006 but has not been completed yet.

Two hundred-billion-dong bypass routes must be completed in 2025

|

Cao Bang - According to the plan, the two bypass routes in Quang Uyen and Xuan Hoa town must be completed in 2025.

The mystery of Chen Zhi's scams

|

scammer Chen Zhi - the mysterious ghost of Southeast Asian cybercrime - disappears while the world is hunting for him.

A large bridge collapsed in China after several months of opening to traffic

|

The 758m long bridge in Sichuan Province, China, showed cracks before collapsing into the river.

Different views on removing the regulation on "resolving consequences" when considering reducing sentences

|

National Assembly deputies have given two different opinions on whether to consider "resolving the consequences" when classifying prisoners.

Ukraine widely withdraws after a series of safe tanks were destroyed by Russia

|

Ukraine admitted to withdrawing from many positions in the Zaporizhzhia region as dense Russian fire destroyed a series of public works and shelters.

Gold price today 11/12: Neo high at 3-week peak

|

Gold price today 11/12: Continued struggle around the highest peak in the past 3 weeks.

Directing the completion of the bypass road under construction for nearly 2 decades

Tân Văn |

Cao Bang - The Cao Bang City bypass was built in 2006 but has not been completed yet.

On the construction site of a bypass worth 197 billion VND in Cao Bang

Tân Văn |

Cao Bang - The Hoa An bypass project is being accelerated.

Two hundred-billion-dong bypass routes must be completed in 2025

Tân Văn |

Cao Bang - According to the plan, the two bypass routes in Quang Uyen and Xuan Hoa town must be completed in 2025.