Resolving difficulties in material mines for Ninh Binh – Hai Phong expressway

NGUYỄN TRƯỜNG |

Ninh Binh - The implementation of the Ninh Binh - Hai Phong expressway construction project, the section passing through Ninh Binh province, is facing some difficulties regarding material quarries.

As planned, the Ninh Binh - Hai Phong Expressway Project, the section passing through Ninh Binh province, will start construction in December 2024.

To resolve difficulties and obstacles regarding construction material mines serving the implementation and construction of the project, the People's Committee of Ninh Binh province issued a document assigning the Department of Natural Resources and Environment to preside over and coordinate with relevant departments, branches, sectors, investors and agencies and units to urgently review and determine the specific location, boundaries and scale of Gay Trau mine, Nam Doi Duong mine, and Doi Lang mine.

At the same time, proactively guide investors to carry out procedures on land, forest land conversion, mineral exploitation licensing and other related procedures according to regulations.

Along with that, the People's Committees of Yen Khanh and Yen Mo districts are requested to focus on and urgently speed up the project's site clearance progress, ensuring the required commencement schedule; review and determine capital needs for site clearance in 2024.

It is known that currently in Ninh Binh province, there are 5 land mines included in the Ninh Binh Provincial Planning for the period 2021 - 2030, with a vision to 2050, approved by the Prime Minister in Decision No. 218/QD-TTg dated March 4, 2024.

However, after reviewing, Ninh Binh province has identified and selected 2 soil mines (soil mines south of Duong hill, Lang hill; soil mines in Gay Trau hill area) to exploit to provide soil materials for the Ninh Binh - Hai Phong expressway construction investment project through Ninh Binh province and apply special policies on mineral exploitation licensing according to Resolution No. 106/2023/QH15 dated November 28, 2023 of the National Assembly.

NGUYỄN TRƯỜNG
RELATED NEWS

Ninh Binh - Hai Phong Expressway will start construction in December 2024

|

Ninh Binh - As planned, the Ninh Binh - Hai Phong expressway project, the section passing through Ninh Binh province, will start construction in December 2024.

Timely rescue of 165 people in rising floodwaters in Ben Cat ward, Ho Chi Minh City

|

HCMC - Authorities in HCMC have rescued 165 people from a nearly 2m deep flooded area in Ben Cat Ward after heavy rain.

Many units join hands with people in the provinces to overcome the consequences of storms and floods

|

On October 22, the Central Relief Mobilization Committee received many supports from units sent to people affected by natural disasters and floods.

Clarifying the case of the Vice Principal in Gia Lai forcing students to stop studying and sweep the yard in the sun

|

Gia Lai is clarifying the fact that the Vice Principal of An Thanh Secondary School was accused of forcing students to stop teaching and sweep the schoolyard at noon, causing parents to be upset.

Gold and silver prices plummet, witnessing the strongest sell-off in many years

|

Gold and silver prices plummeted. However, experts say that this decline is just a technical adjustment, long-term supporting factors remain unchanged.

How to become a principal related to reviewing students in Quang Ninh

|

Quang Ninh - 9 cadres, civil servants and public employees involved in the case of changing scores for students in Ha Lam ward were disciplined, in which one principal was dismissed.

Inside the world's most honored tourist village in Tuyen Quang

|

Tuyen Quang - Lo Lo Chai community tourism village still retains its rustic features, rich in indigenous culture and is a favorite destination for tourists.

Culture of self-respecting taxes - the foundation of a strong nation

|

Vietnam has achieved almost comprehensive tax management digitalization: 99% of businesses declare and pay taxes online, hundreds of foreign suppliers declare via electronic portals, millions of declarations are processed automatically each year. Vietnam's digital tax infrastructure has reached the point that many developing countries still dream of. But when data has gone very far, a bigger question arises: Is the level of self-awareness of taxpayers keeping pace with technology?

Ninh Binh - Hai Phong Expressway will start construction in December 2024

NGUYỄN TRƯỜNG |

Ninh Binh - As planned, the Ninh Binh - Hai Phong expressway project, the section passing through Ninh Binh province, will start construction in December 2024.

Sẽ đầu tư 6 km còn lại dự án cao tốc Ninh Bình - Hải Phòng

Xuyên Đông |

Tuyến cao tốc Ninh Bình - Hải Phòng dài 109 km, cơ quan chức năng đã đầu tư và triển khai gần xong, chỉ còn đúng 6 km qua Hải Phòng.

Cao tốc Ninh Bình - Hải Phòng kết nối hành lang kinh tế

NGUYỄN TRƯỜNG |

Cao tốc Ninh Bình - Hải Phòng, đoạn qua địa bàn tỉnh Ninh Bình hoàn thành sẽ tạo thành hành lang phát triển kinh tế trọng điểm phía Bắc của tỉnh Ninh Bình.