Hanoi reclaims land from more than 2,400 households to build 2 road projects

HỮU CHÁNH |

Hanoi - To implement the project to expand Tam Trinh and Linh Nam streets, Hoang Mai district will reclaim about 152,000 square meters of land from more than 2,400 households and 39 organizations.

The Tam Trinh road construction investment project was approved by the Hanoi People's Committee in 2012, with a total investment of VND 2,066 billion.

The invested construction route is about 3.5km long, starting point connecting with Minh Khai street, ending point intersecting with Ring Road 3.

The project started in 2016 and was expected to be completed after 3 years, but was delayed due to difficulties in site clearance.

By December 2023, the Hanoi People's Committee issued a decision to adjust the project, increasing the investment capital to VND 3,354 billion, an increase of VND 1,287 billion. At the same time, the project implementation period was also adjusted from 2016-2026.

a
Tam Trinh Street is expected to be completed in 2026, with a 40m wide cross-section. Photo: Huu Chanh

To implement the project, Hoang Mai district will reclaim land (after adjusting the boundary) of about 54,009 square meters, related to 1,590 households and 20 organizations in the area of ​​3 wards: Mai Dong, Hoang Van Thu and Yen So.

Up to now, Hoang Mai district has approved all plans of organizations, nearly 400 plans related to households and individuals.

Hoang Mai District Land Fund Development Center and wards have conducted investigation, counting, and verification of time, origin, and land use process for the remaining cases.

Hoang Mai District aims to complete site clearance for the Tam Trinh road construction project in 2024 and complete the project in 2026.

q
People dismantled the construction and handed over land for the project. Photo: Huu Chanh

Another important traffic project that Hoang Mai district is focusing on implementing is the project to upgrade and expand Linh Nam road.

The project was approved for investment in 2013 with a length of 3.4km, starting at Tam Trinh intersection and ending at Nguyen Khoi embankment intersection. Part of the route (from Vinh Hung intersection to Nguyen Khoi embankment) is the section of Hanoi Ring Road 2.5.

According to the plan, Linh Nam road will be expanded on the basis of the existing road, with 2 sections with cross-sections of 22.5m and 40m respectively.

Duong Linh Nam sap duoc thi cong mo rong sau nhieu nam dinh tre. Anh: Huu Chanh
Linh Nam Road is about to be expanded after many years of stagnation. Photo: Huu Chanh

By August 2024, the Hanoi People's Committee approved the adjustment of the implementation time of the project to upgrade and expand Linh Nam Street according to the plan, to be completed in 2027.

The reason for the adjustment is due to difficulties and problems in site clearance, leading to the project not ensuring progress.

According to the People's Committee of Hoang Mai district, 829 households and 19 organizations in 4 wards, including Mai Dong, Vinh Hung, Linh Nam and Tran Phu, will have their land recovered with a total area of ​​98,300 square meters to serve the project.

a
Hoang Mai District will reclaim more than 98,000 square meters of land to expand Linh Nam Street. Photo: Huu Chanh

Currently, the People's Committee of Hoang Mai district has assigned the Land Fund Development Center to organize the selection of a unit to measure and map the site clearance, and coordinate with the People's Committees of the wards to continue to organize the issuance of land recovery notices, investigation and counting.

From October 2024, Hoang Mai district will prepare documents and approve specific land prices for site clearance compensation.

This locality strives to start construction by June 2025 and complete the project by 2027.

The upgrading and expansion of Tam Trinh and Linh Nam roads helps to complete the southern gateway traffic infrastructure, reduce traffic congestion, and contribute to the socio-economic development of Hanoi in general and Hoang Mai district in particular.

HỮU CHÁNH
TIN LIÊN QUAN

Dự án mở đường ở Hà Nội có gần 10 năm nhưng chưa thấy làm

HỮU CHÁNH |

Hà Nội - Được phê duyệt chủ trương đầu tư năm 2015 song dự án mở rộng ngõ 381 Nguyễn Khang đến nay vẫn chưa triển khai thi công, ảnh hưởng cuộc sống người dân.

Người dân dỡ nhà, giao đất mở rộng đường trung tâm Hà Nội

HỮU CHÁNH |

Hà Nội - Nhiều công trình của các tổ chức, cá nhân đang được tháo dỡ, giao mặt bằng thi công dự án mở rộng đường Nguyễn Tuân dài 720m, vốn khoảng 400 tỉ đồng.

Người dân đồng loạt giao đất mở đường 21m trung tâm Hà Nội

Nguyễn Chánh |

Hà Nội - Hơn 100 hộ dân đã đồng thuận bàn giao mặt bằng cho dự án cải tạo, mở rộng đường Nguyễn Tuân dài hơn 700m, vốn đầu tư khoảng 400 tỉ đồng.

TTCP đề nghị Bộ Công an điều tra nhiều dự án bất động sản

CAO NGUYÊN |

Thanh tra Chính phủ đề nghị Bộ Công an tiếp nhận hồ sơ, tài liệu để điều tra sai phạm tại một số dự án liên quan đến bất động sản tại Hà Nội và TP Hồ Chí Minh.

Hàng trăm học sinh bật khóc khi thầy giáo chuyển trường

VIÊN NGUYỄN |

Hàng trăm học sinh ở Trường Phổ thông dân tộc bán trú TH&THCS Sơn Liên, huyện Sơn Tây, Quảng Ngãi - bật khóc khi thầy Nguyễn Ngọc Duy (38 tuổi) chuyển trường.

Cứu thành công 3 người dân bị nạn trên biển ở Khánh Hoà

TÚ QUỲNH |

Khánh Hoà - Ngày 12.10, tàu Cảnh sát biển 9033, Hải đoàn 32 phối hợp cứu nạn thành công 3 người dân bị nạn trên biển.

Xây nhà ở khu tái định cư 300 tỉ đồng sát Quốc lộ 51

HÀ ANH CHIẾN |

Đồng Nai - Các hộ dân di dời để xây dựng đường cao tốc Biên Hòa - Vũng Tàu đã bắt đầu xây dựng nhà cửa tại khu tái định cư Long Đức ở huyện Long Thành.

Trẻ tăng độ cận chóng mặt, bác sĩ chỉ rõ nhiều nguyên nhân

Nhóm PV |

Cận thị ở trẻ nhỏ phát triển rất nhanh, gây ảnh hưởng tới học tập và sinh hoạt hàng ngày. Vì vậy, bác sĩ cảnh báo nguyên nhân thường gặp khiến trẻ dễ bị cận.

The road opening project in Hanoi has been around for nearly 10 years but has not been implemented yet

HỮU CHÁNH |

Hanoi - The investment policy was approved in 2015, but the project to expand alley 381 Nguyen Khang has not yet been implemented, affecting people's lives.

People demolish houses, hand over land to expand central Hanoi road

HỮU CHÁNH |

Hanoi - Many projects of organizations and individuals are being dismantled to make way for the construction of the 720m Nguyen Tuan Street expansion project, with a capital of about 400 billion VND.

People simultaneously handed over land to open 21m road in the center of Hanoi

Nguyễn Chánh |

Hanoi - More than 100 households have agreed to hand over land for the project to renovate and expand Nguyen Tuan Street, more than 700m long, with an investment capital of about 400 billion VND.