Hanoi reclaims land from more than 2,400 households to build 2 road projects

HỮU CHÁNH |

Hanoi - To implement the project to expand Tam Trinh and Linh Nam streets, Hoang Mai district will reclaim about 152,000 square meters of land from more than 2,400 households and 39 organizations.

The Tam Trinh road construction investment project was approved by the Hanoi People's Committee in 2012, with a total investment of VND 2,066 billion.

The invested construction route is about 3.5km long, starting point connecting with Minh Khai street, ending point intersecting with Ring Road 3.

The project started in 2016 and was expected to be completed after 3 years, but was delayed due to difficulties in site clearance.

By December 2023, the Hanoi People's Committee issued a decision to adjust the project, increasing the investment capital to VND 3,354 billion, an increase of VND 1,287 billion. At the same time, the project implementation period was also adjusted from 2016-2026.

a
Tam Trinh Street is expected to be completed in 2026, with a 40m wide cross-section. Photo: Huu Chanh

To implement the project, Hoang Mai district will reclaim land (after adjusting the boundary) of about 54,009 square meters, related to 1,590 households and 20 organizations in the area of ​​3 wards: Mai Dong, Hoang Van Thu and Yen So.

Up to now, Hoang Mai district has approved all plans of organizations, nearly 400 plans related to households and individuals.

Hoang Mai District Land Fund Development Center and wards have conducted investigation, counting, and verification of time, origin, and land use process for the remaining cases.

Hoang Mai District aims to complete site clearance for the Tam Trinh road construction project in 2024 and complete the project in 2026.

q
People dismantled the construction and handed over land for the project. Photo: Huu Chanh

Another important traffic project that Hoang Mai district is focusing on implementing is the project to upgrade and expand Linh Nam road.

The project was approved for investment in 2013 with a length of 3.4km, starting at Tam Trinh intersection and ending at Nguyen Khoi embankment intersection. Part of the route (from Vinh Hung intersection to Nguyen Khoi embankment) is the section of Hanoi Ring Road 2.5.

According to the plan, Linh Nam road will be expanded on the basis of the existing road, with 2 sections with cross-sections of 22.5m and 40m respectively.

Duong Linh Nam sap duoc thi cong mo rong sau nhieu nam dinh tre. Anh: Huu Chanh
Linh Nam Road is about to be expanded after many years of stagnation. Photo: Huu Chanh

By August 2024, the Hanoi People's Committee approved the adjustment of the implementation time of the project to upgrade and expand Linh Nam Street according to the plan, to be completed in 2027.

The reason for the adjustment is due to difficulties and problems in site clearance, leading to the project not ensuring progress.

According to the People's Committee of Hoang Mai district, 829 households and 19 organizations in 4 wards, including Mai Dong, Vinh Hung, Linh Nam and Tran Phu, will have their land recovered with a total area of ​​98,300 square meters to serve the project.

a
Hoang Mai District will reclaim more than 98,000 square meters of land to expand Linh Nam Street. Photo: Huu Chanh

Currently, the People's Committee of Hoang Mai district has assigned the Land Fund Development Center to organize the selection of a unit to measure and map the site clearance, and coordinate with the People's Committees of the wards to continue to organize the issuance of land recovery notices, investigation and counting.

From October 2024, Hoang Mai district will prepare documents and approve specific land prices for site clearance compensation.

This locality strives to start construction by June 2025 and complete the project by 2027.

The upgrading and expansion of Tam Trinh and Linh Nam roads helps to complete the southern gateway traffic infrastructure, reduce traffic congestion, and contribute to the socio-economic development of Hanoi in general and Hoang Mai district in particular.

HỮU CHÁNH
RELATED NEWS

Mr. Nguyen The Phuoc elected Deputy Secretary of Lao Cai Provincial Party Committee

|

Lao Cai - Mr. Nguyen The Phuoc - Standing Vice Chairman of the Provincial People's Committee was elected to hold the position of Deputy Secretary of the Provincial Party Committee.

2 Senior Colonels, 1 Lieutenant Colonel of the Army receive new assignments

|

2 Senior Lieutenant Colonels, 1 Lieutenant Colonel have just been assigned the task of Deputy Attaché of National Defense, in charge of the Border Guard field.

Ministry of Education and Training awards certificates of merit to students who rushed into a fire to save people

|

Nguyen Le Tu - a student at Hanoi University of Science and Technology, who rushed into the fire that occurred in Linh Nam (Hanoi) - to save people was awarded a certificate of merit by the Ministry of Education and Training.

Hanoi requests leaders to overcome the situation of "talking a lot - doing little"

|

Hanoi - Each Party Committee member, leading and managing cadre, especially the head, must resolutely overcome the situation of "hot above - cold below", "talking a lot - doing little".

Gasoline and oil prices forecast to continue to decrease in the next operating session

|

According to current market developments, it is predicted that in the next operating period, gasoline and oil prices may continue to decrease.

Hanoi plans to reduce 35 public schools at commune and ward levels, keeping high schools the same

|

It is expected that in the period 2026-2027, Hanoi will maintain high schools under the Department, reducing 35 public schools under wards and communes.

The youth force continues to promote its pioneering role and spirit of innovation

|

According to the Vice Chairman - Secretary General of the Central Committee of the Vietnam Fatherland Front, the youth force needs to continue to promote its pioneering role and spirit of innovation.

The road opening project in Hanoi has been around for nearly 10 years but has not been implemented yet

HỮU CHÁNH |

Hanoi - The investment policy was approved in 2015, but the project to expand alley 381 Nguyen Khang has not yet been implemented, affecting people's lives.

People demolish houses, hand over land to expand central Hanoi road

HỮU CHÁNH |

Hanoi - Many projects of organizations and individuals are being dismantled to make way for the construction of the 720m Nguyen Tuan Street expansion project, with a capital of about 400 billion VND.

People simultaneously handed over land to open 21m road in the center of Hanoi

Nguyễn Chánh |

Hanoi - More than 100 households have agreed to hand over land for the project to renovate and expand Nguyen Tuan Street, more than 700m long, with an investment capital of about 400 billion VND.