Deadline for handing over the site of 2 billion-dong roads in Tuyen Quang

Việt Bắc |

Tuyen Quang is currently implementing 2 routes connecting to Bac Kan and Thai Nguyen, the site clearance progress for the projects is being accelerated.

The project to build the Bac Kan city road - Ba Be lake connecting to Na Hang, Tuyen Quang has a total length of 37km with a total investment of more than VND 3,800 billion. Part of the project was completed and opened to traffic at the end of April.

The section through Da Vi commune, Na Hang district, Tuyen Quang province is 7.26 km long, the scale of a grade IV mountainous road is currently in the stage of roadbed and bridge construction on the route.

The total number of households within the scope of land clearance (GPMB) for land and assets on the land is 105 households with an expected land area of 27.74 hectares. However, there are still some construction locations that have not been handed over. This is required by the People's Committee of Tuyen Quang province to be completed before June 30, 2025.

Cau vuot song tren tuyen duong Ba Be (Bac Kan) - Na Hang dang duoc thi cong. Anh: Viet Bac.
The river-crossing bridge on the Ba Be (Bac Kan) - Na Hang route is under construction. Photo: Viet Bac

On May 10, speaking with reporters, Mr. Chau Van Bich - Chairman of the People's Committee of Da Vi commune - said that the locality is coordinating with relevant agencies to resolve problems to hand over the site for the project.

"There are still 24/82 households that have not received property support money on the land. These households use land in the records of the hydropower reservoir area recovery. The locality is mobilizing households to receive money, dismantle assets, and at the same time develop a plan to enforce against cases of intentional delay," Mr. Bich informed.

For the Ho Chi Minh Road Project, the Cho Chu (Thai Nguyen) - Trung Son Intersection (Tuyen Quang) section is 29km long, with a total investment of more than 1,600 billion VND. The route started construction in June 2024.

Of which, 17.1 km passing through Yen Son district, Tuyen Quang province, 17.1 km long, is currently being mobilized by the contractor to build a site. After 1 year of construction, many locations of roadbeds, bridges, and culverts on the route have been formed,

According to information from the People's Committee of Yen Son district, the total expected reclaimed area is 61.6 hectares with 105 resettlement plots in Trung Son and Hung Loi 70 communes.

Yen Son district has approved a compensation plan for households and individuals of 106.1 billion VND, reaching 100% of the area to be recovered. Currently, VND100.1 billion has been paid. The construction of 2 resettlement areas to serve the project is expected to be completed in May 2025.

Mat bang thi cong du an duong Ho Chi Minh qua Tuyen Quang dang duoc day nhanh tien do ban giao. Anh: Viet Bac.
The construction site of the Ho Chi Minh road project through Tuyen Quang is being accelerated. Photo: Viet Bac

The relocation and return plan for power and telecommunications works on the route has also been approved with a total amount of 11.1 billion VND. These items are required to be relocated before May 15.

At the inspection of the progress of compensation for site clearance for the Ho Chi Minh road project on May 9, Mr. Nguyen Manh Tuan - Permanent Vice Chairman of the People's Committee of Tuyen Quang province - requested relevant units to speed up the progress of site clearance, relocate works, and promptly hand over the entire site to the construction unit.

Mr. Nguyen Manh Tuan also suggested that Yen Son district should be flexible in arranging temporary accommodation for households subject to relocation and resettlement, to give land to the project. Speed up the construction of resettlement areas so that people can soon stabilize their lives.

Việt Bắc
RELATED NEWS

Procedures for site clearance when the State reclaims land

|

The 2024 Land Law clearly stipulates the procedures for land recovery to help people understand and protect their rights.

Ba Dinh Square on the important days of the nation

|

Hanoi - Ba Dinh Square space takes on a new face, spreading people's beliefs and expectations on the new development path of the nation.

Party Congress XIV receives 559 congratulatory letters and telegrams from international friends

|

As of January 19, the 14th Party Congress received 559 congratulatory letters and telegrams from 109 political parties, 6 international and regional organizations, 16 individuals, 122 people's organizations...

U23 Vietnam before the opportunity to repeat history

|

U23 Vietnam will re-establish the "Snow White Changzhou" record if they defeat U23 China to participate in the 2026 AFC U23 Championship final.

6 LED screens on Nguyen Hue pedestrian street are ready to fuel U23 Vietnam in the semi-finals

|

Ho Chi Minh City - On the morning of January 20, the installation of 6 large LED screens along Nguyen Hue pedestrian street is completing the final stage to serve U23 Vietnam fans in time.

US deploys military aircraft to Greenland, Denmark increases troops

|

The US and Denmark are increasing their military presence in Greenland as Mr. Trump promotes the idea of controlling this strategic Arctic island.

Hue Museum prepares to relocate more than 33,000 artifacts

|

HUE - Hue The relocation of artifacts of Hue City Museum of History to headquarters 24 To Huu opens a better display space for tens of thousands of artifacts.

Promoting intelligence, solidarity, and innovation - The foundation for the new development phase of Ho Chi Minh City

|

The 14th National Party Congress takes place at a time of special significance: the country celebrates 40 years of persistent renovation, its international position and prestige are constantly being enhanced. At the same time, the world and regional context is volatile, complex, and unpredictable, posing increasingly high requirements for the Party's leadership and governance capacity.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Procedures for site clearance when the State reclaims land

Như Hạ (T/H) |

The 2024 Land Law clearly stipulates the procedures for land recovery to help people understand and protect their rights.

Sống mòn bên loạt dự án treo giữa lòng thành phố Tuyên Quang

Nhóm PV |

Tuyên Quang - Nhiều dự án quy hoạch treo hàng chục năm giữa lòng thành phố khiến cuộc sống người dân gặp nhiều khó khăn, bất tiện.

Giữa lòng thành phố Tuyên Quang, người dân có đất nhưng không thể xây nhà

Nhóm PV |

Tuyên Quang - Sống trên chính mảnh đất của mình nhưng hàng chục hộ dân giữa lòng thành phố Tuyên Quang vẫn không được thực hiện quyền sử dụng đất.