Deadline for handing over the site of 2 billion-dong roads in Tuyen Quang

Việt Bắc |

Tuyen Quang is currently implementing 2 routes connecting to Bac Kan and Thai Nguyen, the site clearance progress for the projects is being accelerated.

The project to build the Bac Kan city road - Ba Be lake connecting to Na Hang, Tuyen Quang has a total length of 37km with a total investment of more than VND 3,800 billion. Part of the project was completed and opened to traffic at the end of April.

The section through Da Vi commune, Na Hang district, Tuyen Quang province is 7.26 km long, the scale of a grade IV mountainous road is currently in the stage of roadbed and bridge construction on the route.

The total number of households within the scope of land clearance (GPMB) for land and assets on the land is 105 households with an expected land area of 27.74 hectares. However, there are still some construction locations that have not been handed over. This is required by the People's Committee of Tuyen Quang province to be completed before June 30, 2025.

Cau vuot song tren tuyen duong Ba Be (Bac Kan) - Na Hang dang duoc thi cong. Anh: Viet Bac.
The river-crossing bridge on the Ba Be (Bac Kan) - Na Hang route is under construction. Photo: Viet Bac

On May 10, speaking with reporters, Mr. Chau Van Bich - Chairman of the People's Committee of Da Vi commune - said that the locality is coordinating with relevant agencies to resolve problems to hand over the site for the project.

"There are still 24/82 households that have not received property support money on the land. These households use land in the records of the hydropower reservoir area recovery. The locality is mobilizing households to receive money, dismantle assets, and at the same time develop a plan to enforce against cases of intentional delay," Mr. Bich informed.

For the Ho Chi Minh Road Project, the Cho Chu (Thai Nguyen) - Trung Son Intersection (Tuyen Quang) section is 29km long, with a total investment of more than 1,600 billion VND. The route started construction in June 2024.

Of which, 17.1 km passing through Yen Son district, Tuyen Quang province, 17.1 km long, is currently being mobilized by the contractor to build a site. After 1 year of construction, many locations of roadbeds, bridges, and culverts on the route have been formed,

According to information from the People's Committee of Yen Son district, the total expected reclaimed area is 61.6 hectares with 105 resettlement plots in Trung Son and Hung Loi 70 communes.

Yen Son district has approved a compensation plan for households and individuals of 106.1 billion VND, reaching 100% of the area to be recovered. Currently, VND100.1 billion has been paid. The construction of 2 resettlement areas to serve the project is expected to be completed in May 2025.

Mat bang thi cong du an duong Ho Chi Minh qua Tuyen Quang dang duoc day nhanh tien do ban giao. Anh: Viet Bac.
The construction site of the Ho Chi Minh road project through Tuyen Quang is being accelerated. Photo: Viet Bac

The relocation and return plan for power and telecommunications works on the route has also been approved with a total amount of 11.1 billion VND. These items are required to be relocated before May 15.

At the inspection of the progress of compensation for site clearance for the Ho Chi Minh road project on May 9, Mr. Nguyen Manh Tuan - Permanent Vice Chairman of the People's Committee of Tuyen Quang province - requested relevant units to speed up the progress of site clearance, relocate works, and promptly hand over the entire site to the construction unit.

Mr. Nguyen Manh Tuan also suggested that Yen Son district should be flexible in arranging temporary accommodation for households subject to relocation and resettlement, to give land to the project. Speed up the construction of resettlement areas so that people can soon stabilize their lives.

Việt Bắc
RELATED NEWS

Procedures for site clearance when the State reclaims land

|

The 2024 Land Law clearly stipulates the procedures for land recovery to help people understand and protect their rights.

International beauties, used cars add sparkling beauty to Da Lat streets

|

Da Lat - Da Lat City of Thousands of Flowers is more sparkling with the participation of nearly 80 international beauties and dozens of ancient cars participating in the parade through the streets.

Electricity says Ecohome Nhon Binh lacks cooperation in power generation

|

Gia Lai - Regarding the prolonged power outage at Ecohome Nhon Binh Social Housing Apartment, the Electricity sector said it has provided full support but the repair process is still very slow.

Thien Khoi FC crowned champion of the 2025 National 7-a-side Football Cup

|

Defeating Dai Tu in a dramatic final match, Thien Khoi FC became the champion of the 2025 Hyundai Thanh Cong Cup National 7-a-side Football Cup (VSC-S5).

Traffic ban on Prenn Pass to Da Lat from tomorrow afternoon, December 8

|

Lam Dong - The ban on traffic on Prenn Pass will take place from 11am to 5pm on December 8 to cut down trees at risk of falling, causing traffic insecurity.

Gia Bac Pass in Lam Dong opens to traffic after 5 days of paralysis due to serious landslides

|

Lam Dong - At 5:00 p.m. this afternoon, Gia Bac Pass officially opened the route, vehicles on National Highway 28 began traveling again after a period of paralysis due to landslides.

Updated gold price at the end of session 7.12: gloomy end of the week

|

Updated gold price at the end of the session on December 7: Gold prices last week decreased simultaneously in both domestic and international markets.

Long Thanh airport resettlement area is spacious with villas and townhouses after nearly 5 years

|

Dong Nai - The 280-hectare Long Thanh airport resettlement area has become a bustling urban area, bringing a better life than before to the people.

Procedures for site clearance when the State reclaims land

Như Hạ (T/H) |

The 2024 Land Law clearly stipulates the procedures for land recovery to help people understand and protect their rights.

Sống mòn bên loạt dự án treo giữa lòng thành phố Tuyên Quang

Nhóm PV |

Tuyên Quang - Nhiều dự án quy hoạch treo hàng chục năm giữa lòng thành phố khiến cuộc sống người dân gặp nhiều khó khăn, bất tiện.

Giữa lòng thành phố Tuyên Quang, người dân có đất nhưng không thể xây nhà

Nhóm PV |

Tuyên Quang - Sống trên chính mảnh đất của mình nhưng hàng chục hộ dân giữa lòng thành phố Tuyên Quang vẫn không được thực hiện quyền sử dụng đất.