Dozens of construction teams speed up the VND2,296 billion road project

Khánh Linh |

Lang Son - The National Highway 4B upgrade project, section Km18 - Km80, with a total capital of more than VND 2,296 billion, is being accelerated after a period of delay.

The National Highway 4B upgrade project, section Km18 - Km80, was approved by the Ministry of Transport (now the Ministry of Construction) on April 28, 2023, with a total length of 62.56 km, playing an important role in the inter-regional connection between Lang Son and Quang Ninh provinces.

The investor is the Department of Transport (now the Department of Construction) of Lang Son province, expected to be basically completed in 2024.

The investment scale is divided into many sections according to different technical standards, in which the section Km18 to the intersection of provincial road 236 is built according to the standards of a grade III plain road, speed of 80 km/h, roadbed of 24.5 m wide, 4 lanes. Other sections are suitable for mountainous standards, 12m roadbed, design speed 6080 km/h.

Cac mui thi cong dang duoc trien khai. Anh: Nguyen Thuong
The construction teams are being deployed. Photo: Nguyen Thuong

The total area of recovered land is more than 100 hectares, affecting 1,930 households. Although the site has been handed over 100%, the progress is currently about 2 months behind schedule due to prolonged rain, causing many difficulties for people's lives.

"My house has demolished almost all of it to hand over the site since the end of last year, promised to be constructed quickly, but now there is still mud and mud, the roads are messy. During the rainy season, trucks passing by also cause water to flood into the yard, children do not dare to go to school alone," said Ms. Nguyen Thi Sam, a resident living next to the route.

Mr. Phan Van Cuong (Binh Xa commune) said: "We support the general policy, but if it is prolonged like this, it will affect too much. My store has few customers due to dust and unfinished construction roads. We hope that units will speed up the progress".

According to Mr. Duong Cong Vi - Director of the Department of Construction of Lang Son province - this is a key project, approved by the National Assembly to extend the disbursement until the end of 2025.

a
Some sections of the project are paved with asphalt concrete. Photo: Thuong Nguyen

Currently, the construction site is mobilizing 44 construction teams, 181 equipment and more than 600 officers and workers. The roadbed construction has reached over 90%, 3 large bridges have been technically opened to traffic, the remaining bridges have been completed over 80%.

The volume of asphalt concrete pavement has been paved with 22.5/63 km, equivalent to about 35% of the route length.

"We have directed the contractor to take advantage of favorable weather and work overtime to make up for the progress. Strive to complete package No. 8 (Km43-Km80) by September 30, 2025 and package No. 7 (Km18-Km43) by the fourth quarter of 2025, said Mr. Vi.

Khánh Linh
TIN LIÊN QUAN

grasp leaders in Hai Phong inspect the progress of key projects in the area

|

Hai Phong - Many projects in Tu Minh ward are being accelerated, removing obstacles to site clearance.

Early payment of support money to people affected by Ninh Thuan nuclear power project

|

Khanh Hoa is meeting to discuss, remove obstacles to site clearance and soon pay support to people affected by Ninh Thuan 1 and 2 nuclear power projects.

Speed up the progress of the Ca Ty River Apartment project worth 800 billion VND for resettlement

|

Lam Dong - The Ca Ty River Apartment Project serves the resettlement of people whose land has been recovered, with a total investment of nearly 800 billion VND from the local budget.

Ninh Binh Department of Tourism leaders talk about the ferry problem in Tam Coc

|

Ninh Binh - The leader of the provincial Department of Tourism informed about the boat problem in Tam Coc Tourist Area on the afternoon of July 19.

New developments in the case of a series of leaders of Apatit Tam Dinh Company being suspended from work

|

Lao Cai - The Board of Supervisors of Apatit Tam Dinh Joint Stock Company has just issued a preliminary verification report on the " scandals" that occurred at this company.

Strongly spreading the patriotic emulation movement of the working class

|

During the resistance war against the US (1954 - 1975), the Vietnam General Confederation of Labor gathered, united, and promoted the pioneering role of the working class in overcoming countless difficulties, hardships, and sacrifices, contributing to the army and people of the whole country in the victory on April 30, 1975 .

HCMC reclaims 110 hectares of land, clears 61 households to build the North-South high-speed railway

|

Ho Chi Minh City will reclaim more than 110 hectares of land, clear 61 households with compensation and site clearance costs of more than VND 2,100 billion to build the North-South high-speed railway section.

Vietnam successfully stayed in the league after the Davis Cup

|

At the end of the Davis Cup Group III tennis tournament - Asia/Pacific in 2025, the Vietnam men's tennis team successfully stayed in the league.

grasp leaders in Hai Phong inspect the progress of key projects in the area

Mai Hương |

Hai Phong - Many projects in Tu Minh ward are being accelerated, removing obstacles to site clearance.

Early payment of support money to people affected by Ninh Thuan nuclear power project

Bình Quý |

Khanh Hoa is meeting to discuss, remove obstacles to site clearance and soon pay support to people affected by Ninh Thuan 1 and 2 nuclear power projects.

Speed up the progress of the Ca Ty River Apartment project worth 800 billion VND for resettlement

Duy Tuấn |

Lam Dong - The Ca Ty River Apartment Project serves the resettlement of people whose land has been recovered, with a total investment of nearly 800 billion VND from the local budget.