Journey connecting the two banks of the Tien River at the Rach Mieu 2 bridge project

Thành Nhân |

Ben Tre - Rach Mieu 2 Bridge, connecting Tien Giang and Ben Tre, has been officially closed after more than 3 years of construction.

At the end of March 2022, the Rach Mieu 2 bridge project officially started construction. However, after 1 year of implementation, many difficulties have surrounded this key project.

One of the biggest obstacles is site clearance in Tien Giang and Ben Tre provinces, causing many difficulties in construction.

At that time, Mr. Tran Van Hung - Technical Officer of Dinh An Group Co., Ltd., the unit implementing the XL -04 Package of Rach Mieu Bridge Project 2 - said that Tien Giang provincial authorities carry out slow and uneven site clearance work, continuously caused difficulties for the contractor to execute the XL -04 bidding package on Tien Giang. There are construction areas that still have electric cylinders, cables, houses, ... have not been relocated. The ground is not clean, so the contractor is difficult to implement construction.

Cuoi thang 2.2023, du an cau Rach Mieu bi vuong mat bang. Anh: Thanh Nhan
At the end of February 2023, the Rach Mieu 2 bridge project was stuck in site clearance. Photo: Thanh Nhan

After that, the Prime Minister Pham Minh Chinh had many actual inspections at the construction site of Rach Mieu 2 Bridge project. Here, the Prime Minister asked to complete the project on the occasion of February 2, 2025. At the same time, requiring two localities in Ben Tre and Tien Giang to urgently clear the clean ground to assign the contractor.

With the Prime Minister promptly removing the problem and giving close instructions, on April 19, 2025, the Rach Mieu 2 bridge project was organized, marking an important milestone, symbolizing the solidarity, perseverance and dedication of hundreds of engineers and workers who have poured sweat on the construction site throughout the 3 years of construction.

Du an cau Rach Mieu 2 duoc to chuc le hop long vao ngay 19.4.2025. Anh: Thanh Nhan
The Rach Mieu 2 bridge project will officially close on April 19, 2025. Photo: Thanh Nhan

Rach Mieu 2 Bridge - although not yet completed - has become a symbol of development aspiration, of perseverance in overcoming difficulties and the spirit of solidarity between the government, businesses and people. Each bridge span that is taking shape is a steady advance for a better and more connected West.

The journey connecting the two banks of the Tien River is not only the story of building a bridge - it is the story of faith, of the transformation of an entire fertile land that is reaching strongly into the future.

As of April 19, 2025, the Rach Mieu 2 Bridge project has completed 85% of the volume, exceeding the general progress by 5.04% compared to the plan. In particular, the main bridge (Rach Mieu 2 bridge) is more than 15% ahead of schedule.

The Rach Mieu 2 Bridge project has a starting point at the intersection between National Highway 1 and Provincial Road 870 in Chau Thanh District, Tien Giang Province, and an end point connecting to National Highway 60 at the Ham Luong Bridge approach road in Ben Tre Province. This project has a scale of 4 lanes, a design speed of 80km/h, with a total investment of more than VND 6,810 billion, expected to be completed in early September 2025.

Thành Nhân
TIN LIÊN QUAN

Rach Mieu 2 Bridge worth over VND6,800 billion officially closed

|

Ben Tre - Rach Mieu 2 Bridge has just held a closing ceremony, marking an important milestone in the construction progress.

Rach Mieu Bridge is congested, waiting for Rach Mieu 2 Bridge

|

Ben Tre - Rach Mieu Bridge often occurs congestion, Rach Mieu 2 bridge is expected to reduce traffic pressure for the existing bridge.

Workers quickly ate a bowl of rice, determined to bring Rach Mieu 2 bridge to the finish line

|

Ben Tre - As of December 9, the overall progress of the Rach Mieu 2 bridge project has reached more than 71%, 0.49% faster than planned.

Discovering violations at a housing project, the Government Inspectorate recommends the Ministry of Public Security to intervene

|

The Government Inspectorate requested the Ministry of Public Security to receive information and documents for consideration and investigation with the Hoa Lan Housing Project (Ward 8, Vinh Long City).

Nam Dinh held to a draw by Da Nang in round 19 of V.League

|

On the evening of April 20, Da Nang held Nam Dinh to a 0-0 draw in round 19 of LPBank V.League 2024-2025.

Motorcycle emission inspection facilities must be more than 50m from hospitals

|

Currently, the Government is still developing a roadmap to apply motorbike emission testing.

Dong Bac Corporation proposes bauxite exploitation associated with security and defense tasks

|

Quang Ninh - Dong Bac Corporation is implementing procedures to prepare for investment in bauxite mining projects associated with security and defense tasks in the Central Highlands.

HCMC shaping the future on a new foundation, aspiring to reach global level

|

Ho Chi Minh City is shaping the future on the basis of new space and resources, aiming to become a smart, modern, green-growing global city.

Rach Mieu 2 Bridge worth over VND6,800 billion officially closed

Thành Nhân |

Ben Tre - Rach Mieu 2 Bridge has just held a closing ceremony, marking an important milestone in the construction progress.

Rach Mieu Bridge is congested, waiting for Rach Mieu 2 Bridge

Thành Nhân |

Ben Tre - Rach Mieu Bridge often occurs congestion, Rach Mieu 2 bridge is expected to reduce traffic pressure for the existing bridge.

Workers quickly ate a bowl of rice, determined to bring Rach Mieu 2 bridge to the finish line

Thành Nhân |

Ben Tre - As of December 9, the overall progress of the Rach Mieu 2 bridge project has reached more than 71%, 0.49% faster than planned.