Journey connecting the two banks of the Tien River at the Rach Mieu 2 bridge project

Thành Nhân |

Ben Tre - Rach Mieu 2 Bridge, connecting Tien Giang and Ben Tre, has been officially closed after more than 3 years of construction.

At the end of March 2022, the Rach Mieu 2 bridge project officially started construction. However, after 1 year of implementation, many difficulties have surrounded this key project.

One of the biggest obstacles is site clearance in Tien Giang and Ben Tre provinces, causing many difficulties in construction.

At that time, Mr. Tran Van Hung - Technical Officer of Dinh An Group Co., Ltd., the unit implementing the XL -04 Package of Rach Mieu Bridge Project 2 - said that Tien Giang provincial authorities carry out slow and uneven site clearance work, continuously caused difficulties for the contractor to execute the XL -04 bidding package on Tien Giang. There are construction areas that still have electric cylinders, cables, houses, ... have not been relocated. The ground is not clean, so the contractor is difficult to implement construction.

Cuoi thang 2.2023, du an cau Rach Mieu bi vuong mat bang. Anh: Thanh Nhan
At the end of February 2023, the Rach Mieu 2 bridge project was stuck in site clearance. Photo: Thanh Nhan

After that, the Prime Minister Pham Minh Chinh had many actual inspections at the construction site of Rach Mieu 2 Bridge project. Here, the Prime Minister asked to complete the project on the occasion of February 2, 2025. At the same time, requiring two localities in Ben Tre and Tien Giang to urgently clear the clean ground to assign the contractor.

With the Prime Minister promptly removing the problem and giving close instructions, on April 19, 2025, the Rach Mieu 2 bridge project was organized, marking an important milestone, symbolizing the solidarity, perseverance and dedication of hundreds of engineers and workers who have poured sweat on the construction site throughout the 3 years of construction.

Du an cau Rach Mieu 2 duoc to chuc le hop long vao ngay 19.4.2025. Anh: Thanh Nhan
The Rach Mieu 2 bridge project will officially close on April 19, 2025. Photo: Thanh Nhan

Rach Mieu 2 Bridge - although not yet completed - has become a symbol of development aspiration, of perseverance in overcoming difficulties and the spirit of solidarity between the government, businesses and people. Each bridge span that is taking shape is a steady advance for a better and more connected West.

The journey connecting the two banks of the Tien River is not only the story of building a bridge - it is the story of faith, of the transformation of an entire fertile land that is reaching strongly into the future.

As of April 19, 2025, the Rach Mieu 2 Bridge project has completed 85% of the volume, exceeding the general progress by 5.04% compared to the plan. In particular, the main bridge (Rach Mieu 2 bridge) is more than 15% ahead of schedule.

The Rach Mieu 2 Bridge project has a starting point at the intersection between National Highway 1 and Provincial Road 870 in Chau Thanh District, Tien Giang Province, and an end point connecting to National Highway 60 at the Ham Luong Bridge approach road in Ben Tre Province. This project has a scale of 4 lanes, a design speed of 80km/h, with a total investment of more than VND 6,810 billion, expected to be completed in early September 2025.

Thành Nhân
RELATED NEWS

Rach Mieu 2 Bridge worth over VND6,800 billion officially closed

|

Ben Tre - Rach Mieu 2 Bridge has just held a closing ceremony, marking an important milestone in the construction progress.

Rach Mieu Bridge is congested, waiting for Rach Mieu 2 Bridge

|

Ben Tre - Rach Mieu Bridge often occurs congestion, Rach Mieu 2 bridge is expected to reduce traffic pressure for the existing bridge.

Workers quickly ate a bowl of rice, determined to bring Rach Mieu 2 bridge to the finish line

|

Ben Tre - As of December 9, the overall progress of the Rach Mieu 2 bridge project has reached more than 71%, 0.49% faster than planned.

South Korea suspends all 7 generals of the counterpartition unit for Military policy

|

Three more generals of the South Korean National Defense Intermediary Command were suspended from work on September 18 for alleged martial law.

Paying traffic fines using QR Codes, people in Ho Chi Minh City say quickly and transparently

|

HCMC - Traffic violators in HCMC believe that the procedure for paying traffic fines using on-site QR Codes is transparent and time-saving.

Thaco announces profit increase of 14%, total assets increase to more than 195.5 trillion VND

|

Thaco's financial report recorded that equity and total assets of enterprises in 2024 continue to increase sharply, but after-tax profits have not broken out.

Appointment and reappointment of 2 Army Major Generals and 1 Vice Admiral of the Navy

|

The Prime Minister appointed and reappointed 3 military personnel, of which Major General Le Dinh Cuong held the position of Commander of the Vietnam Coast Guard.

Da Nang calls for help because the expired BOT station still blocks the national highway, trucks avoid the station to overflow into residential areas

|

Da Nang - An Thang Ward has proposed to dismantle the expired BOT station but still blocks the national highway, causing trucks to avoid the station and rush into residential areas near schools.

Rach Mieu 2 Bridge worth over VND6,800 billion officially closed

Thành Nhân |

Ben Tre - Rach Mieu 2 Bridge has just held a closing ceremony, marking an important milestone in the construction progress.

Rach Mieu Bridge is congested, waiting for Rach Mieu 2 Bridge

Thành Nhân |

Ben Tre - Rach Mieu Bridge often occurs congestion, Rach Mieu 2 bridge is expected to reduce traffic pressure for the existing bridge.

Workers quickly ate a bowl of rice, determined to bring Rach Mieu 2 bridge to the finish line

Thành Nhân |

Ben Tre - As of December 9, the overall progress of the Rach Mieu 2 bridge project has reached more than 71%, 0.49% faster than planned.