Current status of the billion-dollar intersection in Ho Chi Minh City has been congested for 9 years due to land clearance

TÚ QUỲNH |

HCMC - Construction started in 2016, but the My Thuy intersection (Thu Duc City) has not yet been completed due to land clearance problems.

The My Thuy intersection construction project (Thu Duc City) started in 2016 with a total investment of VND1,998 billion and by 2022, this project was adjusted to increase to more than VND3,600 billion.

The My Thuy intersection construction project is invested by the Ho Chi Minh City Traffic Construction Investment Project Management Board. According to the plan, this project has a scale of 3 floors, in phase 1, large items such as underpass, overpass, My Thuy 3 bridge, Ky Ha 3 bridge have been completed. However, due to lack of land, the project was temporarily suspended and it was not until April 2024 that the project was restarted.

Toan canh khu vuc nut giao my thuy
Panorama of My Thuy intersection. Photo: Anh Tu

According to Lao Dong at My Thuy intersection (Thu Duc City), the number of vehicles passing through is very large. This is a traffic hot spot connecting Cat Lai port, so during peak hours, traffic becomes complicated and conflicts easily occur.

  Nut giao My Thuy co mat do giao thong rat lon, thuong xuyen un u phuong tien. Ảnh: Anh Tu
My Thuy intersection has a very high traffic density, often congested with vehicles. Photo: Anh Tu

At the My Thuy intersection project area, many items are being implemented to continue to be completed, however, the progress is not guaranteed. It is noted that the construction area of Ky Ha 4 bridge started in April 2024, the right turn from Ring Road 2 ( Vo Chi Cong) to Nguyen Thi Dinh, and is currently under construction at a slow pace.

Along with that, the construction package for the left overpass from Cat Lai to Phu My bridge also started on January 18, but had to be temporarily suspended due to lack of land. Up to now, only two bored piles have been deployed, with no workers at the construction site.

Cau Ky Ha 4 dang tam ngung thi cong vi thieu mat bang. Ảnh: Anh Tu
Ky Ha 4 Bridge is temporarily suspended due to lack of land. Photo: Anh Tu
  Viec giai phong mat bang dang dien ra kha cham tai du an xay dung nut giao My Thuy. Ảnh: Anh Tu
Site clearance is quite slow at the My Thuy intersection construction project. Photo: Anh Tu

The project's delay has caused traffic pressure here to increase, greatly affecting traffic and people's lives.

Mot so nha dan dang thuc hien thao do mat bang. Ảnh: Anh Tu
Some houses are demolishing the site. Photo: Anh Tu

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board, many items at My Thuy intersection are temporarily suspended due to land clearance problems. The two packages for the construction of branches on the left and right banks of My Thuy canals have only reached the progress of 15% and 50% respectively, but have been forced to stop. Similarly, Ky Ha 4 Bridge and the branch from Phu My Bridge to Cat Lai, which started construction in April 2024, have only reached 15% and have been temporarily suspended due to lack of land.

The Ho Chi Minh City Traffic Construction Investment Project Management Board said that the site clearance was carried out by the Thu Duc City People's Committee in 2016 with a budget of VND1,190 billion, but by January 2025, only 9/195 cases had been handed over. The slow progress has forced the project's completion date to be postponed from the end of 2025 to April 2026.

To ensure progress, the Ho Chi Minh City Traffic Construction Investment Project Management Board proposed that Thu Duc City soon hand over the construction site of Ky Ha 4 Bridge and Cat Lai Overpass in February 2025, and complete the entire project before March 31, 2025 to ensure project progress.

A representative of the Thu Duc City Compensation and Site Clearance Board said that Thu Duc City is currently reviewing the cases and carrying out procedures to promptly hand over the site to the investor. It is expected that the site will be handed over to the investor in the first quarter of 2025.

 Mot so goi thau da hoan thanh gom: cau Ky Ha 3, cau vuot tren vanh dai 2 (duong Vo Chi Cong) va ham chui re trai tu vanh dai 2 di Cat Lai, cau My Thuy 3 (ke ca duong dan hai dau cau). Ảnh: Anh Tu
Some completed packages include: Ky Ha 3 bridge, overpass on Ring Road 2 ( Vo Chi Cong Street) and left turn underpass from Ring Road 2 to Cat Lai, My Thuy 3 bridge (including access roads at both ends of the bridge). Photo: Anh Tu

My Thuy intersection has an important traffic location and is the main route of Thu Duc City, connecting the eastern gateway of Ho Chi Minh City and Cat Lai ferry. This area is one of the black spots of traffic congestion that has lasted for many years in Ho Chi Minh City.

Therefore, the My Thuy intersection construction project, once completed, is expected to solve huge traffic pressure at the eastern gateway of Ho Chi Minh City.

TÚ QUỲNH
TIN LIÊN QUAN

The VND3,600 billion intersection in Ho Chi Minh City is stalled due to 186 land congestion

|

HCMC - The My Thuy intersection project with a total capital of more than VND3,600 billion continues to be stalled because Thu Duc City has not yet handed over 186 sites, greatly affecting the construction progress.

An Phu intersection gradually takes shape after 2 years of construction

|

After 2 years of construction, the An Phu intersection project is entering the final stage, expected to reduce traffic congestion and improve traffic connections in the East of Ho Chi Minh City upon completion.

Principal speaks out after male student was electrocuted to death while performing

|

Quang Ngai - Mr. Nguyen Van Loc - Principal of Ba To Town Secondary School - has reported to the Quang Ngai Department of Education and Training about the incident in which a student died while performing a performance.

Hour 9: Reversal - Part 2

|

Hour 9 No. 152 - A man with a warm family, suddenly fell in love with a woman who also had a family. When his wife discovered it, would he be able to wake up in time?

Quang Nam, Da Nang arrange 4,291 headquarters and 760 public vehicles after merger

|

After Da Nang and Quang Nam officially merged, the rearrangement of 4,291 working headquarters and 760 public vehicles is a top concern.

New hypothesis about the origin of 18 skulls found in a cave

|

Nghe An - Local people believe that the 18 skulls and remains discovered in the Len Chua rock cave may have been taken from another place.

Nam Dinh Club beat Binh Duong 3-1 at Thien Truong

|

Nam Dinh Club won 3-1 against Binh Duong, thereby continuing to lead the V.League 2024-2025 rankings.

Dak Lak takes action in the case of unusually high water prices after Lao Dong Newspaper's reflection

|

Dak Lak - The Provincial People's Committee has directed relevant units to clarify the issue of high water prices, businesses using free infrastructure after the reflection of Lao Dong Newspaper.

The VND3,600 billion intersection in Ho Chi Minh City is stalled due to 186 land congestion

MINH QUÂN |

HCMC - The My Thuy intersection project with a total capital of more than VND3,600 billion continues to be stalled because Thu Duc City has not yet handed over 186 sites, greatly affecting the construction progress.

An Phu intersection gradually takes shape after 2 years of construction

Tú Tâm |

After 2 years of construction, the An Phu intersection project is entering the final stage, expected to reduce traffic congestion and improve traffic connections in the East of Ho Chi Minh City upon completion.

Hình ảnh nút giao 3 tầng hơn 3.600 tỉ đồng giải cứu kẹt xe cửa ngõ phía Đông TPHCM

ANH TÚ - NHƯ QUỲNH |

TPHCM - Dự án xây dựng nút giao thông Mỹ Thủy (TP Thủ Đức) với quy mô 3 tầng được tái khởi động sau nhiều năm trì trệ, tăng vốn đầu tư từ hơn 1.998 tỉ đồng lên hơn 3.600 tỉ đồng, dự kiến hoàn thành năm 2025, giúp giảm kẹt xe, tai nạn cho cửa ngõ cảng Cát Lái - cảng đứng đầu cả nước về sản lượng hàng hoá.