Scene of the demolition of a cultural house in Phu Tho is in disarray

Tô Công |

Phu Tho - The cultural house project in Go 1 area, Minh Tan commune, Cam Khe district is having to be demolished due to sunken foundations, the scene is littered with concrete, steel...

Regarding the incident of the Go 1 cultural house, Minh Tan commune, Cam Khe district (Phu Tho) being demolished while under construction, which Lao Dong Newspaper reported, the demolition is now almost complete.

Coming to Minh Tan commune on the afternoon of March 18, Lao Dong Newspaper reporters recorded that the Go 1 village cultural house was built on a pond, surrounded by a fairly crowded population. The foundation of the project has been filled with corrugated iron and elevated by village roads.

Nha van hoa duoc xay dung tren mot ao beo kha rong. Anh: To Cong.
The cultural house was built on a fairly large pond. Photo: To Cong

It can be seen that almost all of this cultural house has been demolished, a large amount of bricks, concrete, steel... are lying around at the scene.

Hien truong ngon ngang sau khi nha van hoa bi pha bo. Anh: To Cong.
The scene was in disarray after the cultural house was demolished. Photo: To Cong

Previously, the image of an excavator destroying the Go 1 cultural house recorded by residents and shared on Facebook caused a stir, many comments expressed waste and regret when the project had to "break down and rebuild".

Truoc do, nha van hoa nay duoc xay gan hoan thien. Anh cat tu clip tren mang xa hoi.
Previously, this cultural house was built near completion. Photo cut from a clip on social media.

According to Mr. Nguyen Hong Son - Chairman of Minh Tan Commune People's Committee, the Go 1 cultural house project is invested by the Commune People's Committee.

The reason why this cultural house was demolished while under construction was due to weak soil, causing a corner of the house to sink, the construction contractor had to dismantle the entire construction to rebuild it.

Tru so UBND xa Minh Tan, huyen Cam Khe. Anh: To Cong.
Headquarters of the People's Committee of Minh Tan commune, Cam Khe district. Photo: To Cong

"After inspection, it was found that the contractor had constructed the cultural house according to the design, but because it was built on borrowed land and had weak geology, it sank. The contractor has paid for this project first, there is no budget and the people have not contributed" - Mr. Son shared.

Some images recorded by the reporter:

Tô Công
RELATED NEWS

Commune Chairman states the reason why the cultural house was being demolished while it was under construction

|

Phu Tho - Chairman of the People's Committee of Minh Tan Commune, Cam Khe District explained the reason for the demolition of a cultural house in the area under construction.

Close-up of the nearly 400 billion VND Cultural and Artistic House in Phu Tho

|

The Phu Tho Province Cultural and Artistic House project with a total investment of nearly 400 billion VND in the center of Viet Tri city is in the process of completion.

Contracts signed with actors, singers and tax calculation methods

|

Before the review and retroactive collection of personal income tax in Ho Chi Minh City, the transparency in film contracts and the payment of actors' cát-xê is being concerned by audiences.

Live football Philippines vs Thailand at ASEAN Cup 2026

|

Live football match between Philippines and Thailand in Group B ASEAN Cup 2026 at 8:00 p.m. on August 4.

Hanoi requests review of many officials involved in land violations in Soc Son

|

Many officials of Soc Son district were previously required to self-criticize for allowing land violations to occur that have not been resolved thoroughly.

Ben Thanh - Can Gio Metro accelerates construction of 920m long Soai Rap river overpass

|

Ho Chi Minh City - Ben Thanh - Can Gio Metro is accelerating the construction of the 920m long Soai Rap river overpass with many simultaneous construction fronts, aiming to be completed in 2028.

Ho Chi Minh City students are expected to be supported with 700,000 VND to learn to swim

|

Ho Chi Minh City - Students who do not know how to swim in Ho Chi Minh City are expected to be supported with 700,000 VND per swimming course from the 2026-2027 school year.

Commune Chairman states the reason why the cultural house was being demolished while it was under construction

Tô Công |

Phu Tho - Chairman of the People's Committee of Minh Tan Commune, Cam Khe District explained the reason for the demolition of a cultural house in the area under construction.

Dân không đồng tình việc mở đường cắt qua nhà văn hóa

Minh Hạnh |

Hà Nội – Một dự án đường giao thông liên xã tại huyện Hoài Đức dài khoảng 800m cắt qua nhà văn hóa, gây phản ứng trong dư luận vì lo ngại lãng phí.

Close-up of the nearly 400 billion VND Cultural and Artistic House in Phu Tho

Tô Công |

The Phu Tho Province Cultural and Artistic House project with a total investment of nearly 400 billion VND in the center of Viet Tri city is in the process of completion.