Scene of the demolition of a cultural house in Phu Tho is in disarray

Tô Công |

Phu Tho - The cultural house project in Go 1 area, Minh Tan commune, Cam Khe district is having to be demolished due to sunken foundations, the scene is littered with concrete, steel...

Regarding the incident of the Go 1 cultural house, Minh Tan commune, Cam Khe district (Phu Tho) being demolished while under construction, which Lao Dong Newspaper reported, the demolition is now almost complete.

Coming to Minh Tan commune on the afternoon of March 18, Lao Dong Newspaper reporters recorded that the Go 1 village cultural house was built on a pond, surrounded by a fairly crowded population. The foundation of the project has been filled with corrugated iron and elevated by village roads.

Nha van hoa duoc xay dung tren mot ao beo kha rong. Anh: To Cong.
The cultural house was built on a fairly large pond. Photo: To Cong

It can be seen that almost all of this cultural house has been demolished, a large amount of bricks, concrete, steel... are lying around at the scene.

Hien truong ngon ngang sau khi nha van hoa bi pha bo. Anh: To Cong.
The scene was in disarray after the cultural house was demolished. Photo: To Cong

Previously, the image of an excavator destroying the Go 1 cultural house recorded by residents and shared on Facebook caused a stir, many comments expressed waste and regret when the project had to "break down and rebuild".

Truoc do, nha van hoa nay duoc xay gan hoan thien. Anh cat tu clip tren mang xa hoi.
Previously, this cultural house was built near completion. Photo cut from a clip on social media.

According to Mr. Nguyen Hong Son - Chairman of Minh Tan Commune People's Committee, the Go 1 cultural house project is invested by the Commune People's Committee.

The reason why this cultural house was demolished while under construction was due to weak soil, causing a corner of the house to sink, the construction contractor had to dismantle the entire construction to rebuild it.

Tru so UBND xa Minh Tan, huyen Cam Khe. Anh: To Cong.
Headquarters of the People's Committee of Minh Tan commune, Cam Khe district. Photo: To Cong

"After inspection, it was found that the contractor had constructed the cultural house according to the design, but because it was built on borrowed land and had weak geology, it sank. The contractor has paid for this project first, there is no budget and the people have not contributed" - Mr. Son shared.

Some images recorded by the reporter:

Tô Công
RELATED NEWS

Commune Chairman states the reason why the cultural house was being demolished while it was under construction

|

Phu Tho - Chairman of the People's Committee of Minh Tan Commune, Cam Khe District explained the reason for the demolition of a cultural house in the area under construction.

Close-up of the nearly 400 billion VND Cultural and Artistic House in Phu Tho

|

The Phu Tho Province Cultural and Artistic House project with a total investment of nearly 400 billion VND in the center of Viet Tri city is in the process of completion.

Deputy Director of Quang Ninh Provincial Police becomes Deputy Head of the Provincial Party Committee's Internal Affairs Commission

|

Quang Ninh - On the morning of March 23, the Standing Committee of the Quang Ninh Provincial Party Committee held a conference to announce decisions on personnel work of the Provincial Party Committee's Internal Affairs Committee.

High interest rates are cyclical, real estate is still a long-term accumulation channel

|

According to experts, the general level of home loan interest rates is currently high in the short term, but this is a cyclical development of the economy.

Kim Jong Un re-elected Chairman of North Korea

|

Mr. Kim Jong Un was re-elected Chairman of the North Korean State Council Committee in the first session of the 15th Supreme People's Assembly.

Hanoi plans to build a 2,000 billion VND theater, 9,000m2 wide

|

Hanoi - In the period 2026-2030, the city will build a theater of about 9,000 m2 on Vo Thi Sau street with an investment of about 2,000 billion VND.

Iranian nuclear power plant at risk of attack

|

US President Donald Trump declares he will eradicate the Iranian nuclear power plant unless Tehran reopens the Strait of Hormuz.

Long traffic jam on Mai Chi Tho street, people struggle to get to the center of Ho Chi Minh City

|

On the first morning of the week, the flow of vehicles pouring into the eastern gateway of Ho Chi Minh City increased sharply, causing prolonged traffic jams on Mai Chi Tho street, and people struggled to move into the center.

Commune Chairman states the reason why the cultural house was being demolished while it was under construction

Tô Công |

Phu Tho - Chairman of the People's Committee of Minh Tan Commune, Cam Khe District explained the reason for the demolition of a cultural house in the area under construction.

Dân không đồng tình việc mở đường cắt qua nhà văn hóa

Minh Hạnh |

Hà Nội – Một dự án đường giao thông liên xã tại huyện Hoài Đức dài khoảng 800m cắt qua nhà văn hóa, gây phản ứng trong dư luận vì lo ngại lãng phí.

Close-up of the nearly 400 billion VND Cultural and Artistic House in Phu Tho

Tô Công |

The Phu Tho Province Cultural and Artistic House project with a total investment of nearly 400 billion VND in the center of Viet Tri city is in the process of completion.