Images of 2 hundred billion urban projects changing the face of Yen Bai city

Trần Bùi |

With the goal of upgrading infrastructure, flood protection embankment of Cau Dai stream and connecting route Nguyen Tat Thanh - Au Co, it is expected to change the appearance of Yen Bai city.

The project to comprehensively develop dynamic urban areas has been implemented in Yen Bai city since 2019 with a total investment of 63.27 million USD, equivalent to more than 1,423 billion VND, invested by the Yen Bai Provincial Construction Investment Project Management Board.

Among the components that make up this project, the Cau Dai stream flood control embankment and the road connecting Nguyen Tat Thanh street to Au Co street are the two most important works.

Flood control embankment 192 billion VND

The project to build the Cau Dai stream flood control embankment, constructed by Dong Tien Limited Liability Company, with a total investment of more than 192 billion VND, started on February 16, 2022 and is expected to be completed in March 2025.

The project includes many items such as: Construction of embankment, embankment corridor road and works on embankment.

Cong trinh duoc khoi cong ngay 16.2.2022, du kien hoan thanh vao thang 3.2025. Anh: Tran Bui
Construction started on February 16, 2022 and is expected to be completed in March 2025. Photo: Tran Bui

According to records, right after the flood, dozens of heavy machinery and workers were rushing to complete the project on schedule.

Ms. Nguyen Thi Xuan (Yen Ninh ward, Yen Bai city) said that in the past, all waste was dumped directly into the stream by people, which both narrowed the flow and caused pollution.

"When the project was built, the stream gradually regained its clarity, creating a clean and beautiful environment," said Ms. Xuan.

300 billion VND connecting route

The construction project of the road connecting Nguyen Tat Thanh Street to Au Co Street is about 4.2km long, constructed by the joint venture of Nam Phong Investment, Construction and Trading Joint Stock Company, Yen Bai Traffic Construction Joint Stock Company and Thanh Trung Construction and Trading Company Limited, with a total investment capital of nearly 300 billion VND.

Construction started in December 2022 and is expected to be completed in April 2025.

Tuyen duong co tong so von dau tu gan 300 ti dong. Anh: Tran Bui
The route has a total investment capital of nearly 300 billion VND. Photo: Tran Bui

According to Lao Dong's report on October 11, after days of storms and rain, hundreds of workers have returned to work at the construction site.

Mr. Dinh Van Son (Tan Thinh ward, Yen Bai city) said that people have high expectations for this road to be completed soon.

"Once completed, the route will shorten the travel distance from home to the city center," said Mr. Son.

He thong ha tang tren tuyen duong dang duoc hoan thien. Anh: Tran Bui
The infrastructure system on the route is being completed. Photo: Tran Bui

Speaking with Lao Dong, Mr. Doan Van Hai - project manager said that according to the contract, the route is expected to be completed in April 2025.

"The unit is striving to take advantage of favorable weather to pave the entire road surface by December 2024. Currently, the total completed work volume has reached more than 60%," Mr. Hai informed.

At a recent field inspection of the Dynamic Urban Development Project - Yen Bai City Sub-project, Standing Vice Chairman of the Provincial People's Committee Nguyen The Phuoc emphasized that the project aims to upgrade infrastructure, minimize damage caused by floods, connect traffic, and develop trade.

Once completed, this project is expected to contribute to changing the face of Yen Bai city.

Trần Bùi
RELATED NEWS

Gasoline and oil prices today 11:4: Simultaneously sharply decrease

|

Gasoline and oil prices today 11:4: World oil prices fell sharply. WTI oil fell below 97 USD/barrel; Brent oil reached 95 USD/barrel.

Grassroots trade unions support living expenses for more than 2,000 workers

|

Lam Dong - The grassroots trade union of the garment company supports living expenses for all workers in the face of market price fluctuations.

Gold price update morning of 11/4: Domestic gold faces risk of decline

|

Gold price update morning of 11:4: World gold last night fell sharply, possibly pulling domestic gold down as the new trading session opens.

Vietnam futsal team meets Australia in the 3rd place match of the Southeast Asian Championship

|

The Vietnamese futsal team will meet the Australian futsal team in the 3rd place match of the 2026 Southeast Asian Futsal Championship taking place on April 12.

Ho Chi Minh City sets off 7-point fireworks on the evening of April 30

|

Ho Chi Minh City will set off fireworks simultaneously at 7 locations on the evening of April 30, from 9pm to 9:15pm.

Hanoi apartments cool down, the market records a noteworthy shift trend

|

Hanoi apartments in the first quarter of 2026 cooled down as supply and absorption rates decreased, while the trend of shifting to the suburbs became increasingly clear.

Ho Chi Minh City proposes scanning cards and electronic identification to take free buses

|

Ho Chi Minh City - To take the free bus, passengers must present their card or electronic identification (ID card, VNeID, bank card, e-wallet, MultiGo application...).

Tuyến đường huyết mạch đầy ổ voi, ổ gà ở Yên Bái

Trần Bùi |

Yên Bái - Tuyến đường huyết mạch ĐT 166 xuất hiện nhiều ổ voi, ổ gà ảnh hưởng đến việc di chuyển của người dân.

Cutting hills and mountains to build a 300 billion VND road in Yen Bai

Trần Bùi |

Dozens of workers and machines are working hard to bring the route connecting Nguyen Tat Thanh Street to Au Co Street (Yen Bai City) to the finish line on schedule.

Two intersections connecting Yen Bai city with Noi Bai - Lao Cai highway

Trần Bùi |

The two IC 12 and IC 13 intersections that have been and will be completed soon play a particularly important role in connecting Yen Bai City with the Noi Bai - Lao Cai highway.