Billion-dollar residential project on prime land in Thai Nguyen is sluggish

VIỆT BẮC |

After more than 10 years of implementation, the infrastructure construction project of Residential Area No. 1 (Thai Nguyen City) is sluggish in progress, tens of thousands of square meters of prime land are in a state of disrepair and desolation.

As reported by Lao Dong Newspaper, the infrastructure construction project of Residential Area No. 1 (Residential Area No. 1), Quyet Thang Commune (Thai Nguyen City) was reported to have used a large amount of soil of unknown origin for site clearance.

The illegally exploited land area is located about 2 km from the project, in Quyet Thang commune. Mining and transportation activities have been going on for many days, mainly at night.

In addition to using land of unknown origin, the Residential Area No. 1 project, although implemented for more than 10 years with 2 adjustments and extensions, has yet to be completed.

Sau 10 nam trien khai, du an khu dan cu tien ti o Thai Nguyen van chi la bai dat trong. Anh: Viet Bac.
After 10 years of implementation, the billion-dollar residential project in Thai Nguyen is still just an empty lot. Photo: Viet Bac.

Residential Area No. 1 Project has an area of ​​9.8 hectares in Quyet Thang commune, invested by Tu Son Forest Products Processing and Trading Company Limited.

Deployed since 2013 with an initial total investment of 65 billion VND, by 2019, the project was adjusted and the investment capital was supplemented up to 80 billion VND.

According to the reporter's records in mid-December 2024, this project is still just an empty lot, the technical infrastructure items are not finished, materials are lying around, weeds are growing wildly, and it is messy.

Inside, there were no workers or machines, and no signs that the project was under construction, even though the expected completion date was only a few days away.

Having a house near the project, every time it is mentioned, Mr. Nguyen Van Minh (Thai Nguyen City) cannot help but feel fed up. Mr. Minh shared that the situation of the project being abandoned and not implemented has been going on for many years.

"For more than 10 years, the company has not finished the work. During that time, I only occasionally see them stirring to fill in a little soil and then stop. Seeing tens of thousands of square meters of land left empty like that looks very wasteful and heartbreaking," said Mr. Minh.

Sharing the same sentiment, Ms. Pham Thi Quynh (Thai Nguyen City) said that in 2013, when information about the Residential Area No. 1 project was announced, people in the surrounding area were looking forward to it and hoped to enjoy the benefits that the project would bring in the future.

According to Ms. Quynh, initial expectations gradually turned to disappointment when the project progressed slowly, stagnated for a long time, and then fell into a state of desolation and squalor.

Ha tang ky thuat chua co, mot so noi co moc, bi xuong cap. Anh: Viet Bac.
Technical infrastructure is not yet available, some places are overgrown with grass and are degraded. Photo: Viet Bac.

"The project has been here for a long time, I don't see them finishing it, I don't know if they will continue construction or not. I hope that the authorities at all levels will soon have a plan to complete the project soon, leaving it like this not only wastes land but also spoils the urban beauty" - Ms. Quynh shared more.

Speaking with reporters, a leader of Quyet Thang Commune People's Committee confirmed that the Residential Area No. 1 project is still unfinished and not completed.

"According to the expected time, it should be completed by December 2024, but according to the current situation and the fact that the land has not been cleared yet, it is very difficult to complete it this year. It is likely that we will have to request a fourth extension.

During the implementation process in the area managed by the locality, the commune repeatedly requested the unit to provide records and documents about the project, but the investor was very uncooperative" - ​​this leader informed.

*Names have been changed upon request.

VIỆT BẮC
TIN LIÊN QUAN

Forecast of changes in La Nina and weather in the summer of 2025

|

The impact of La Nina is forecast to affect the weather in the summer of 2025.

Fierce tanker truck on fire on Noi Bai - Lao Cai Expressway

|

A tanker truck caught fire fiercely on the Noi Bai - Lao Cai Expressway this morning (January 1).

After April 10, unreported projects will be considered untroubled

|

After April 10, the national public investment system will not receive further information about investment projects with difficulties, long backlogs and is considered no longer stuck.

Gold prices increase sharply, Germanyans worry about gold reserves in the US

|

In the context of the continuous increase in gold prices, Germans are starting to worry about more than 110 billion euros in gold reserves in the US.

Apartment residents in Ho Chi Minh City check houses after earthquake in Myanmar

|

HCMC - After the earthquake in Myanmar, many HCMC residents are worried, proactively checking their homes and assessing their safety level.

Repairing a billion-dollar road after a report from Lao Dong Newspaper

|

Bac Kan - After Lao Dong Newspaper's reflection on the billion-dollar Nong Ha - Khe Thi route: DH.75 (Cho Moi) is damaged, so far, this project has been repaired.

Criteria for selecting commercial housing pilot projects

|

The selection of pilot projects must meet the criteria such as urban planning areas and land acquisition projects must be approved by the Provincial People's Council.

Dien Bien has experienced 2 of the biggest earthquakes in the past 100 years in Vietnam

|

Dien Bien is considered the cradle of earthquakes in Vietnam because there were 2 strong earthquakes of 6.7 and 6.9 richter - the largest in the history of the past 100 years.

Bến xe tiền tỉ ở Thái Nguyên bỏ hoang trên đất vàng, thành nơi trồng ngô

Việt Bắc |

Thái Nguyên - Sau nhiều năm hoàn thành nhưng chưa thể đưa vào khai thác, bến xe khách TP Phổ Yên tổng mức đầu tư gần 20 tỉ đồng hiện bỏ không, gây lãng phí cả chục nghìn m2 đất vàng.

Loạt dự án xây chợ trăm tỉ bất động trên đất vàng ở Thái Nguyên

Việt Bắc |

Nắm giữ hàng chục nghìn m2 đất giữa lòng TP Thái Nguyên nhưng suốt gần 10 năm qua, nhiều dự án xây chợ mới với mức đầu tư cả trăm tỉ đồng vẫn dang dở và rơi vào cảnh bất động kéo theo lo lắng, bất an của người dân.

Dự án nhà ở hơn 500 tỉ tại Thái Nguyên 12 năm bất động trên đất vàng

Nhóm PV |

Đã 12 năm kể từ ngày khởi công cùng 3 lần được gia hạn tiến độ, đến nay Dự án Khu nhà ở Bắc Sơn - Sông Hồng vẫn trong trạng thái bất động trên khu đất vàng giữa trung tâm TP Thái Nguyên.