slow construction of the only road leading to the capital Tuyen Quang

Lam Thanh |

Tuyen Quang - The sluggish construction situation has caused the road from Tan Thanh commune to Phu Luu commune to be bumpy and littered with construction materials.

The project to upgrade and renovate provincial road 189 from Tan Thanh commune to Phu Luu commune is 11km long, with a total investment of nearly 45 billion VND. The project started in mid-2024 and was constructed by Quang Sang Construction and Trading Company Limited and Linh Giang Joint Stock Company.

This is the only route, leading to the orange capital of Ham Yen with a large volume of traffic. The sluggish, ginger-shaped construction of the road has affected people's lives. Vehicles participating in traffic must swerve to avoid potholes, elephant potholes, foggy roads, dusty sunshine and mud.

Tuyen duong lay loi gay kho khan cho cac phuong tien tham gia giao thong. Anh: Lam Thanh
The muddy road causes difficulties for vehicles participating in traffic. Photo: Lam Thanh

According to the reporter, the 11km provincial road 189 upgrade project is under construction at a slow pace. At the construction site, there are only a few workers paving the sidewalk. The entire route is littered with construction materials, no machinery or workers. Many items such as drainage culverts and unfinished roadbeds are under construction.

Mr. Tran Hien (Tan Thanh commune, Ham Yen district) said that the project to upgrade Provincial Road 189 has been implemented for a long time. However, the construction has been interrupted and is not yet completed. Workers and machinery mobilized to work for a period of time will be off. Recently, only a few groups of workers have been seen paving sidewalks.

Nhieu hang muc tai du an van do dang. Anh: Lam Thanh
Many items at the project are still unfinished. Photo: Lam Thanh

"This is the main road of some communes, while it is being built in disarray and then left in disarray, affecting people's lives. It is dusty when it is sunny, and muddy when it rains. Materials are gathered on the road but are not constructed, vehicles are very dangerous to travel, especially at night.

People hope the project will be completed soon for convenient travel. This sluggish situation is unacceptable," Mr. Hien said indignantly.

Speaking to Lao Dong Newspaper, Mr. Le Van Thai - Director of Ham Yen District Construction Investment Project Management Board said that according to the plan, the project to upgrade Provincial Road 189 through Tan Thanh and Phu Luu communes will be completed in September 2025.

"Near the provincial road 189 upgrade project, there is a Tuyen Quang - Ha Giang expressway construction project, the large number of heavy trucks running through the route has affected the construction process.

In the coming time, the investor has requested contractors to continue constructing items to ensure progress," the leader added.

Some images at the project:

Viec thi cong i ach khien cac phuong tien gap nhieu kho khan. Anh: Lam Thanh
The sluggish construction has caused many difficulties for vehicles. Photo: Lam Thanh
Nhieu hang muc thi cong dang do, vat lieu xay dung chat ngon ngang. Anh: Lam Thanh
Many construction items are unfinished, construction materials are scattered. Photo: Lam Thanh
Day la tuyen duong huyet mach dan vao thu phu cam Ham Yen. Anh: Lam Thanh
This is the main route leading to the capital of Cam Yen. Photo: Lam Thanh
Cong truong du an vang bong cong nhan. Anh: Lam Thanh
The project site is deserted. Photo: Lam Thanh
Xx
The sidewalk has been plowed for a long time but has not been constructed yet. Photo: Lam Thanh

The project to upgrade Provincial Road 189 through Tan Thanh Commune to Phu Luu is a section of DT.189 road with a total length of 54.4km.

DT.189 road is a vital route passing through the center of 7 communes of Binh Xa, Tan Thanh, Phu Luu, Minh Dan, Minh Khuong, Bach Xa and Yen Thuan of Ham Yen district.

The road was invested in for upgrading with a budget of nearly 230 billion VND in 2014. However, after a while it has seriously degraded.

Lam Thanh
RELATED NEWS

Social housing development is still sluggish due to procedures and land funds

|

Social housing is considered the lifeline segment for people's dream of settling down. However, to realize this dream, efforts from many sides are needed.

Slow disbursement of public investment capital in the first 2 months of the year

|

Public investment disbursement in the first 2 months of 2025 only reached 6.9% of the plan, lower than the same period in 2024. Many ministries, branches and localities have not disbursed or have disbursed very low.

A80 exhibition welcomes record 8.6 million visitors

|

The 80th National Achievement Exhibition at the Vietnam Exhibition Center (Dong Anh, Hanoi) welcomed nearly 8.6 million visitors after 17 days of opening.

Proposal on asset and income verification activities when amending the Law on Anti-Corruption

|

The draft Law has new proposals on the content of asset and income verification activities to overcome many current shortcomings.

Russia declares to ensure the highest security if Mr. Zelensky arrives in Moscow

|

Russia has said it will ensure the highest level of security for Ukrainian President Volodymyr Zelensky if he accepts to Moscow to meet President Vladimir Putin.

Officials are absolutely not required to present integrated documents on VNeID

|

Officials, civil servants and public employees are absolutely not required to submit or present documents integrated on VNeID or in a connected database.

Motorcycle collides with tanker truck crossing the road in Lam Dong, killing 2 people

|

Lam Dong - A motorbike collided with a tanker truck crossing the road on National Highway 1, causing 2 motorcyclists to die on the spot.

Mr. Trump issued a letter to NATO on resolving the Russia-Ukraine conflict

|

Mr. Trump said the US would only impose major sanctions on Russia if all of NATO followed suit and ended Russian oil imports.

Social housing development is still sluggish due to procedures and land funds

Như Hạ |

Social housing is considered the lifeline segment for people's dream of settling down. However, to realize this dream, efforts from many sides are needed.

Slow disbursement of public investment capital in the first 2 months of the year

Minh Ánh |

Public investment disbursement in the first 2 months of 2025 only reached 6.9% of the plan, lower than the same period in 2024. Many ministries, branches and localities have not disbursed or have disbursed very low.

Ì ạch thi công mở rộng đường Nguyễn Tuân, Hà Nội

HỮU CHÁNH |

Hà Nội - Hoạt động thi công diễn ra ì ạch trên công trường mở rộng đường Nguyễn Tuân dù mặt bằng đã được bàn giao cách đây gần 3 tháng.