988 billion VND road embankment in Lang Son cracked

Khánh Linh |

Lang Son - After storm No. 3, many embankment locations of the National Highway 4B Renovation and Upgrade Project (section Km3+700 to Km18) have cracked.

The project to renovate and upgrade National Highway 4B (section Km3+700 to Km18) is designed and invested according to the scale of a grade III road, TCVN 4054:2005, design speed 80 km/h, total length 13,192 m; starting point at Km3+605 (connecting with the invested 4-lane inner-city section), ending point at Km17+707 (intersecting with National Highway 4B at Km17+890).

The project has a total investment of 988 billion VND from the central budget and is invested by the Lang Son Provincial Construction Investment Project Management Board.

Although the project is not yet completed, the embankment was seriously damaged after storm No. 3.

On November 21, according to the reporter's records, severe damage appeared on many embankments.

Subsidence and cracking occurred at many locations on the embankment surface, roof and toe, despite being reinforced with stone and reinforced concrete.

In many places, concrete slabs are broken and hanging from the hillside.

People in Po Khoang village, Khanh Xuan commune, Loc Binh district said that the cracks in some of the above embankment locations appeared a long time ago, after the circulation of storm No. 3 swept through.

According to local people, the project's embankment has been eroded and damaged, making them feel insecure when passing through these roads.

"Sometimes when I pass by, I'm afraid that concrete slabs will accidentally fall from the embankment, so I have to be really careful" - another resident shared.

On the same day, speaking with reporters, a representative of the Lang Son Province Construction Investment Project Management Board said that landslides on some embankments were caused by storm No. 3, including one large landslide.

According to the unit representative, landslides on positive slopes during construction of traffic works often occur.

"Recently, the Board also invited relevant units to the site and agreed to make adjustments. The project is still under construction, and the landslides will soon be fixed," the investor's representative informed.

Some images recorded by reporters at the construction site:

Phan mat ke va mai ke da bi tach roi, mot so vi tri sut lun sau. Anh: Khanh Linh
The embankment surface and roof have been separated, and some areas have sunk deeply. Photo: Khanh Linh
a
Some locations have torn apart concrete slabs. Photo: Khanh Linh
Nhieu tam be tong lo lung tren mai taluy nhu truc cho roi xuong. Anh: Khanh Linh
Many concrete slabs are hanging on the slope as if waiting to fall. Photo: Khanh Linh
a
Consecutive items broke after just one stormy season. Photo: Khanh Linh

 

Khánh Linh
TIN LIÊN QUAN

The 2,000 billion VND road project in Lang Son is behind schedule due to land clearance

|

Lang Son - The project to upgrade section Km18-Km80, National Highway 4B had to request an extension due to difficulties in site clearance.

Lang Son clears land for 2 key highways

|

Lang Son - 2 key expressways are urgently clearing land to reach the finish line.

Why is the largest industrial park in Lang Son still slow in clearing land

|

VSIP Lang Son Industrial Park (IP) is still behind schedule in site clearance.

Chairman of Farmers' Association in Nghe An suddenly disappeared

|

Nghe An - Mr. L.B.P - Chairman of the Farmers' Association of Xa Luong commune, Tuong Duong district - suddenly went missing since the afternoon of November 20.

SEA Games 33 has 50 competitive sports

|

The Organizing Committee of the 33rd Southeast Asian Games (SEA Games 33) has just announced that there will be 50 competitions with 105 sub-events and 3 demonstration events.

Special reasons why Ho Chi Minh City is in the top 25 places to visit in 2025

|

Conde Nast Traveler listed Ho Chi Minh City among the 25 best destinations to visit in 2025, as this is the occasion of the 50th anniversary of the country's reunification.

Temporary suspension of exit for Mr. Nguyen Duc Chi due to tax debt

|

Ninh Thuan Tax Department sent a notice to the Immigration Department regarding the temporary suspension of exit of Mr. Nguyen Duc Chi - Chairman of the Board of Directors of Sunbay Ninh Thuan Joint Stock Company.

Update on the closing price of gold on November 21: Receive positive forecast

|

Update on the closing price of gold on November 21: Experts say many factors are supporting the increase in gold prices.

The 2,000 billion VND road project in Lang Son is behind schedule due to land clearance

Khánh Linh |

Lang Son - The project to upgrade section Km18-Km80, National Highway 4B had to request an extension due to difficulties in site clearance.

Lang Son clears land for 2 key highways

Khánh Linh |

Lang Son - 2 key expressways are urgently clearing land to reach the finish line.

Why is the largest industrial park in Lang Son still slow in clearing land

Khánh Linh |

VSIP Lang Son Industrial Park (IP) is still behind schedule in site clearance.