Proposing the Government to include 5 Dak Nong wind power projects in the VIII power plan

BẢO LÂM |

Dak Nong proposed that the Government and the Prime Minister consider updating 5 wind power projects into the Power Plan VIII.

On May 10, the Dak Nong Provincial People's Committee sent a document to the Government Office regarding wind power projects in the area.

Dak Nong province has 5 wind power projects under implementation, including: Nam Binh 1 Wind Power Plant Project has completed investment (total investment capital is about over 1,000 billion VND);

The three Dak N'Drung 1, 2, and 3 Wind Power Plant projects have invested VND 5,800 billion out of a total investment of VND 10,525 billion (reaching 55%);

The Asia Dak Song 1 Wind Power Plant project has not yet been implemented (total investment capital is about 1,693 billion VND).

It is expected that the 5 completed investment projects will contribute to the National grid of about 380MW.

At the same time, projects also pay the state budget about 200 billion VND/year from value added tax.

In the context of Dak Nong being a poor province with economic difficulties, the early completion and operation of wind power projects is very important in the socio-economic development of the locality.

Therefore, the Dak Nong Provincial People's Committee proposed that the Government and the Prime Minister consider updating the projects in the Plan to implement the VIII Power Plan as proposed by the Ministry of Industry and Trade.

As reported by Lao Dong Newspaper, Dak Nong province's wind power projects are stuck due to overlapping planning between energy projects and mineral planning areas.

Specifically, wind power projects are included in the power plan approved by the Government in June 2020.

At the same time, these projects are also in the bauxite planning area for the period 2021 - 2025 approved by the Government in July 2023.

BẢO LÂM
RELATED NEWS

Quang Tri issues deadline for handling wind power projects that are delayed and do not have collateral

|

Quang Tri - The provincial Department of Finance requires wind power projects with slow progress to deposit funds to ensure and speed up progress, otherwise they will be considered for termination of operations.

Reasons why 5 wind power projects are required to terminate investment policies

|

Quang Tri - The province directed relevant units to carry out procedures to terminate investment policies for 5 wind power projects.

Dak Nong proposes the Central Government to remove obstacles for wind power projects

|

Dak Nong - The whole Dak Nong province has 6 wind power projects but only has 1 commercial operation project. The province recommended that the Central Government remove difficulties for the remaining projects.

Gold price update on the morning of December 16: Domestic gold skyrockets

|

Gold price update on the morning of December 16: SJC gold bar increased by 900,000 VND. Meanwhile, gold rings increased by about 500,000 VND/tael.

Social housing investor Kim Chung admits errors in the company's salary table photo, receives back documents

|

Hanoi - In response to the reflection of Lao Dong Newspaper, the representative of the investor of CT3 Kim Chung project admitted that there were errors in the process of receiving documents for purchasing social housing (NOXH).

Resolutely handle households placing containers in the construction site of the Ring Road 2.5 project

|

Hanoi - The authorities of Phuong Liet ward have cleared the areas encroaching on the underpass project and Ring Road 2.5.

Car catches fire in the middle of rush hour in Hanoi

|

Hanoi - During rush hour this afternoon, a car was traveling at the Xuan La - Vo Chi Cong intersection when it suddenly caught fire.

Coach Kim Sang-sik: "We are ready to win the SEA Games"

|

Coach Kim Sang-sik affirmed that U22 Vietnam is ready for the goal of winning the 33rd SEA Games men's football championship.

Quang Tri issues deadline for handling wind power projects that are delayed and do not have collateral

HƯNG THƠ |

Quang Tri - The provincial Department of Finance requires wind power projects with slow progress to deposit funds to ensure and speed up progress, otherwise they will be considered for termination of operations.

Reasons why 5 wind power projects are required to terminate investment policies

HƯNG THƠ |

Quang Tri - The province directed relevant units to carry out procedures to terminate investment policies for 5 wind power projects.

Dak Nong proposes the Central Government to remove obstacles for wind power projects

BẢO LÂM |

Dak Nong - The whole Dak Nong province has 6 wind power projects but only has 1 commercial operation project. The province recommended that the Central Government remove difficulties for the remaining projects.