Proposing the Government to include 5 Dak Nong wind power projects in the VIII power plan

BẢO LÂM |

Dak Nong proposed that the Government and the Prime Minister consider updating 5 wind power projects into the Power Plan VIII.

On May 10, the Dak Nong Provincial People's Committee sent a document to the Government Office regarding wind power projects in the area.

Dak Nong province has 5 wind power projects under implementation, including: Nam Binh 1 Wind Power Plant Project has completed investment (total investment capital is about over 1,000 billion VND);

The three Dak N'Drung 1, 2, and 3 Wind Power Plant projects have invested VND 5,800 billion out of a total investment of VND 10,525 billion (reaching 55%);

The Asia Dak Song 1 Wind Power Plant project has not yet been implemented (total investment capital is about 1,693 billion VND).

It is expected that the 5 completed investment projects will contribute to the National grid of about 380MW.

At the same time, projects also pay the state budget about 200 billion VND/year from value added tax.

In the context of Dak Nong being a poor province with economic difficulties, the early completion and operation of wind power projects is very important in the socio-economic development of the locality.

Therefore, the Dak Nong Provincial People's Committee proposed that the Government and the Prime Minister consider updating the projects in the Plan to implement the VIII Power Plan as proposed by the Ministry of Industry and Trade.

As reported by Lao Dong Newspaper, Dak Nong province's wind power projects are stuck due to overlapping planning between energy projects and mineral planning areas.

Specifically, wind power projects are included in the power plan approved by the Government in June 2020.

At the same time, these projects are also in the bauxite planning area for the period 2021 - 2025 approved by the Government in July 2023.

BẢO LÂM
RELATED NEWS

Quang Tri issues deadline for handling wind power projects that are delayed and do not have collateral

|

Quang Tri - The provincial Department of Finance requires wind power projects with slow progress to deposit funds to ensure and speed up progress, otherwise they will be considered for termination of operations.

Reasons why 5 wind power projects are required to terminate investment policies

|

Quang Tri - The province directed relevant units to carry out procedures to terminate investment policies for 5 wind power projects.

Dak Nong proposes the Central Government to remove obstacles for wind power projects

|

Dak Nong - The whole Dak Nong province has 6 wind power projects but only has 1 commercial operation project. The province recommended that the Central Government remove difficulties for the remaining projects.

Live football Man United vs Man City in the Premier League

|

Live football match Man United - Man City in round 22 of the Premier League, taking place at 7:30 PM on January 17 (Vietnam time).

15-year traffic jam at the eastern gateway of Ho Chi Minh City is about to be removed

|

Ho Chi Minh City - The bottleneck on National Highway 1, the section of the new Mien Dong Bus Station - Tan Van, is expected to be expanded from the end of 2026, helping to eliminate traffic jams at the eastern gateway.

3-year corporate income tax exemption according to Decree 20

|

3 years of corporate income tax exemption for small and medium-sized enterprises from the date of first issuance of the Enterprise Registration Certificate.

Rare monkey herd re-released to the natural forest in Ha Tinh

|

Ha Tinh - Functional forces coordinate to re-release the rare monkey herd to the natural environment in Vu Quang National Park.

Scene of passenger car overturning on National Highway 6, 4 casualties

|

The Chairman of Son La Provincial People's Committee directly attended the scene, directing functional forces to rescue, rescue and overcome the consequences of the accident on National Highway 6.

Quang Tri issues deadline for handling wind power projects that are delayed and do not have collateral

HƯNG THƠ |

Quang Tri - The provincial Department of Finance requires wind power projects with slow progress to deposit funds to ensure and speed up progress, otherwise they will be considered for termination of operations.

Reasons why 5 wind power projects are required to terminate investment policies

HƯNG THƠ |

Quang Tri - The province directed relevant units to carry out procedures to terminate investment policies for 5 wind power projects.

Dak Nong proposes the Central Government to remove obstacles for wind power projects

BẢO LÂM |

Dak Nong - The whole Dak Nong province has 6 wind power projects but only has 1 commercial operation project. The province recommended that the Central Government remove difficulties for the remaining projects.