Lang Son clears land for 2 key highways

Khánh Linh |

Lang Son - 2 key expressways are urgently clearing land to reach the finish line.

Efforts to hand over clean site for the project

The Dong Dang (Lang Son province) - Tra Linh (Cao Bang province) Expressway Construction Investment Project under the public-private partnership form was approved by the Prime Minister in Decision No. 1212 dated August 10, 2020 and assigned the People's Committee of Cao Bang province as the competent state agency for the project.

The project has a total length of about 93.35 km (phase 1). In Lang Son province, this route passes through Van Lang and Trang Dinh districts with a length of about 52 km, with a total land use area of ​​361.13 ha.

The section passes through Van Lang district with a land acquisition area of ​​166.66 hectares and Trang Dinh district with a land acquisition area of ​​194.47 hectares.

On November 17, according to information from the Steering Committee for compensation and site clearance for key projects in Lang Son province, up to now, in Van Lang district, the project has measured and counted 138.9 hectares, reaching 83.34% and has paid advances to 342 households with the amount of 32.1 billion VND.

The result of the handover of 42 hectares of land, equivalent to about 9.1 km of route length; 314 graves have been moved, the remaining number of graves counted is 57 graves.

Hinh anh thi cong tai cong trinh cao toc Dong Dang - Tra Linh. Anh: Viet Trung
Construction images at the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway. Photo: Viet Trung

In Trang Dinh district, the expected recovered area is 194.47 hectares, with about 682 households affected by the project in Hung Viet, Hung Son, De Tham, Chi Lang and Chi Minh communes.

The result of the handover of the site reached 49.77 hectares, 473 graves/197 households were counted, the advance payment for grave relocation costs was made to 76 households/204 graves with the amount of 2.07 billion VND, and 199/473 graves were moved.

Thus, up to now, the project's site clearance work has reached 93.6%. The two provinces strive to hand over 100% of the project site by the end of December 2024.

The Huu Nghi - Chi Lang border gate expressway is component project 2 of the Bac Giang - Lang Son expressway project.

This project is represented by the Provincial Traffic Infrastructure Construction and Maintenance Investment Management Board. The investor implementing the project is the Consortium of Deo Ca Construction Joint Stock Company - Deo Ca Group Joint Stock Company - Construction Joint Stock Company 568 - Lizen Joint Stock Company.

Total investment for the project in the phased phase is 11,024 billion VND.

Tren cong truong xay cao toc Huu Nghi - Chi Lang. Anh: Khanh Linh
On the construction site of the Huu Nghi - Chi Lang highway. Photo: Khanh Linh

The project has a total length of 59.87 km, including 2 routes. Route 1 is about 43.43 km long, starting at Km1+800 (QL.1 route) connecting to the entrance to Huu Nghi border gate in Dong Dang town, Cao Loc district and ending at Km44+749.67 (Bac Giang - Lang Son expressway route) in Mai Sao commune, Chi Lang district. Route 2 is the route connecting Tan Thanh border gate and Coc Nam border gate, about 16.44 km long, including 2 sections.

The project has a total recovered land area of ​​594.69 hectares, passing through the districts of Chi Lang, Van Lang, Cao Loc and Lang Son city; with a total of 2,356 affected cases.

According to the assessment of the Steering Committee for compensation and site clearance for key projects in Lang Son province, the 4 districts and cities where the project passes through have done a good job of propaganda and mobilization, so they have received the consensus of people whose land is recovered right from the beginning.

People have agreed to receive advance payment and hand over part of the land to implement the project.

Up to now, site clearance work has reached 67%, striving to hand over 100% of the site by the end of December 2024.

"Just work, no back talk"

On the afternoon of November 14, at a working session with the two provinces of Lang Son and Cao Bang, Prime Minister Pham Minh Chinh requested the two provinces to speed up the progress of the above projects.

Prime Minister Pham Minh Chinh emphasized that the Dong Dang - Tra Linh and Huu Nghi - Chi Lang expressway projects are two important road projects that not only connect expressways in the region, but also connect with the North - South expressway and connect with China.

Thu tuong Pham Minh Chinh kiem tra, dong vien cong nhan thi cong du an cao toc Dong Dang - Tra Linh. Anh: Nhat Bac
Prime Minister Pham Minh Chinh inspects and encourages workers constructing the Dong Dang - Tra Linh expressway project. Photo: Nhat Bac

Prime Minister Pham Minh Chinh highly appreciated the importance of time, intelligence, determination, drasticness, self-reliance, self-strengthening, mobilizing the strength of the entire political system, people, and businesses to implement, in the spirit of "only discussing action, not retreating".

In particular, the Prime Minister requested the rapid completion of two projects in 2025, contributing to the opening of the expressway from Cao Bang to Ca Mau.

Khánh Linh
TIN LIÊN QUAN

Why is the largest industrial park in Lang Son still slow in clearing land

|

VSIP Lang Son Industrial Park (IP) is still behind schedule in site clearance.

Lang Son declares natural disaster emergency at 2 irrigation lakes

|

Lang Son - The Provincial People's Committee has just decided to declare a natural disaster emergency to repair two irrigation lakes in Van Lang district.

Lang Son border district is about to have a 460 billion VND Industrial Cluster

|

Lang Son - Na Duong 2 Industrial Park, Loc Binh district with a total investment of 464 billion VND is about to be built.

Thanh Oai land auction: Few participants

|

On the morning of November 23, an auction of 23 land plots took place in Thanh Oai district, Hanoi.

Vietnam team and the fear of lacking a leader

|

The captain's armband can be given to any player on the Vietnam National Team, but not all of Mr. Kim Sang Sik's students have the qualities to take on this position.

Found 1 body in garbage truck crash on Binh Thanh bridge in Hue

|

HUE - Found 1 of 2 missing victims of garbage truck falling off Binh Thanh bridge (Huong Tra town, Thua Thien Hue).

Supplementing regulations on handling cases of asset undervaluation

|

The auditing agency proposed to supplement regulations on handling cases of undervaluation of assets and enterprise value, causing loss of State capital.

No regulations on salary payment mechanism at the enterprise

|

The Draft on Management and Investment of State Capital in Enterprises (amended) does not stipulate the content and mechanism for paying salaries and bonuses in enterprises.

Why is the largest industrial park in Lang Son still slow in clearing land

Khánh Linh |

VSIP Lang Son Industrial Park (IP) is still behind schedule in site clearance.

Lang Son declares natural disaster emergency at 2 irrigation lakes

Khánh Linh |

Lang Son - The Provincial People's Committee has just decided to declare a natural disaster emergency to repair two irrigation lakes in Van Lang district.

Lang Son border district is about to have a 460 billion VND Industrial Cluster

Khánh Linh |

Lang Son - Na Duong 2 Industrial Park, Loc Binh district with a total investment of 464 billion VND is about to be built.