The reason why the billion-dollar hospital in Thai Nguyen is in ruins

Việt Bắc |

Thai Nguyen - After more than 10 years of implementation but unable to complete, the Phuc Thai General Hospital project with a total investment of thousands of billions of VND is in a state of desolation.

As Lao Dong has reported many times, the Phuc Thai General Hospital Project in Song Cong City (Thai Nguyen) with an investment of more than 2,000 billion VND, located on 2.7 hectares of prime land in Cai Dan Ward, Song Cong City has been in operation for more than 10 years but has not been completed.

Phuc Thai General Hospital was expected to meet the needs of medical examination and treatment and create jobs for local people. The project was not put into use on time, wasting land resources and causing resentment among the people.

On October 2, the reporter noted that inside the project, the 5-story building had only completed the frame and was still lying motionless, exposed to the sun and rain, causing loss of urban beauty.

The area inside and outside the building is overgrown with weeds, and some items have deteriorated. Over the years, the project has become a place for cattle grazing, with syringes and trash appearing in many places.

V
A trillion-dollar hospital project on "golden" land has been lying dormant for more than a decade in Thai Nguyen, in a state of desolation. Photo: Viet Bac

According to the investigation of the reporter, the reason for the project being stalled and "shelved" for more than 10 years is because the investor could not arrange financial resources according to Decision No. 190/QD-UBND dated January 27, 2022 of the People's Committee of Thai Nguyen province on the Decision to approve the adjustment of the project investment policy.

Mr. Nguyen Tien Manh (Song Cong City) said: "This project has been abandoned for many years, so many rice fields that people have had to take back are now left empty, it's heartbreaking to see. I don't know if the project will continue, I think it looks very shabby like this, some drug addicts gather here, it's very unsafe for the area."

On October 2, speaking with reporters, Mr. Nguyen Cong Viet - Deputy Director of the Department of Planning and Investment of Thai Nguyen province - informed that there is still no decision to revoke the Phuc Thai General Hospital project.

Also related to this project, Mr. Luu Van Thang - Chairman of Cai Dan Ward People's Committee (Song Cong City) - said: "Up to now, the project has expired and the implementation time has expired. The investor also has no more construction activities here.

The project has not yet been handed over to any other unit and the entire land area of ​​the project is public land managed by the locality.

Some images recorded by reporter:

1
The project is located in the center of Song Cong City. Photo: Viet Bac
2
This trillion-dollar project has been in ruins for many years. Photo: Viet Bac
3
3
The first floor of the 5-storey building became a place where people gathered to inject drugs. Photo: Viet Bac
5
Local people are waiting for an official decision soon on this unfinished trillion-dollar project. Photo: Viet Bac

Many favors but cannot be fulfilled

Phuc Thai General Hospital project invested by Phuc Thai Industrial, Commercial and Medical Services Joint Stock Company was granted the first investment certificate by Thai Nguyen Provincial People's Committee on March 8, 2010.

By the end of 2011, Phuc Thai Company still had not implemented it. In mid-2012, the project was adjusted for the first time, increasing the investment capital to more than 2,000 billion VND. The completion of phase 1 was extended to the fourth quarter of 2013 and phase 2 to the fourth quarter of 2018. However, when the frame of the 5-storey building was just completed, the project stopped and remained inactive for a long time.

On January 27, 2022, the People's Committee of Thai Nguyen province continued to adjust the investment registration certificate for the second time, extending the project implementation period until the end of the fourth quarter of 2022. At the same time, it required Phuc Thai Company to implement the project on schedule as committed. Up to now, almost the end of 2024, the Phuc Thai General Hospital Project is still motionless and desolate.

 

Việt Bắc
TIN LIÊN QUAN

Appointing the Provincial Party Secretary and Deputy Secretary after completing the merger

|

The Central Organizing Committee will advise and submit to the Politburo and the Secretariat to appoint secretaries and deputy secretaries of provincial and municipal Party committees after the localities complete the merger.

Yen Bai Chairman directs handling of illegal sand mining and gathering

|

Yen Bai - The Chairman of the Provincial People's Committee directed departments and branches to inspect and strictly handle illegal sand mining and gathering after the reflection of Lao Dong Newspaper.

Updated gold price at the end of session 25.4: All decreased

|

Updated gold price at the end of the session on September 25: Decreased in both domestic and international markets. However, experts are still positive.

Live football The Cong Viettel 1-0 Song Lam Nghe An: Round 2

|

Live match between The Cong Viettel and Song Lam Nghe An in round 20 of V.League, taking place at 7:15 p.m. today (April 25).

Need for institutional push for green credit to spread

|

Although considered the main capital flow for green transformation, green credit in Vietnam is still unlikely to spread due to lack of support from policies.

The Ministry of National Defense reorganizes the Command to Protect President Ho Chi Minh's Mausoleum

|

The Ministry of National Defense held a ceremony to announce the Decision to reorganize the Ho Chi Minh Mausoleum Protection Command into the Ho Chi Minh Mausoleum Command.

Dự án trăm tỉ hoang tàn ở Thái Nguyên, phớt lờ lệnh trả đất

Lam Thanh |

Thái Nguyên - Dự án Trung tâm Nông nghiệp ứng dụng công nghệ cao vẫn ngang nhiên tồn tại, mặc dù bị yêu cầu tháo dỡ công trình, bàn giao đất.

Cụm công nghiệp trăm tỉ ở Thái Nguyên lâm cảnh hoang tàn

Việt Bắc |

Thái Nguyên - Sau hơn 5 năm triển khai, dự án Cụm công nghiệp Bá Xuyên (TP Sông Công) tổng mức đầu tư trên 431 tỉ đồng vẫn dang dở, lâm vào cảnh hoang tàn.

Hoang tàn bên trong dự án nông nghiệp trăm tỉ ở Thái Nguyên

Lam Thanh |

Sau 6 năm triển khai, Dự án Trung tâm Nông nghiệp ứng dụng công nghệ cao tại TP. Thái Nguyên vẫn hoang tàn, một số hạng mục xuống cấp nghiêm trọng.