Trillion-dollar road surface to ease traffic jams in Go Vap

Anh Tú |

HCMC - The Duong Quang Ham Street expansion project (Go Vap) is speeding up construction progress, with the goal of completing the expansion to 6 lanes in 2025.

The project to expand and upgrade Duong Quang Ham Street (Go Vap District, Ho Chi Minh City) started construction in early August 2023.

The entire project is divided into 3 packages: the first package from the beginning of the route (Binh Thanh district) to Nguyen Thai Son street, the second package from Nguyen Thai Son street to street number 2, the third package from street number 2 to Nguyen Van Luong street (Go Vap cultural park).

Of which the total investment is more than 2,300 billion VND, site clearance costs account for the majority, about 1,750 billion VND.

According to reporters, these days the construction site of the project is getting busier and busier.

The 2.5km long road is like a big construction site racing to the finish line. The working atmosphere at the construction site is extremely urgent.

Cac cong nhan dang tang toc tren cong truong du an duong Duong Quang Ham. Ảnh: Anh Tu
Workers are speeding up at the Duong Quang Ham road project site. Photo: Anh Tu

Construction units are mobilizing workers and machinery to compact and pave the road surface and curb the sidewalks to complete the project.

People on both sides of the road are also rushing to repair, build new ones, and complete the final items in time to welcome the new year.

 Nhieu doan thuoc du an da thong thoang sau khi duoc mo rong len 6 lan xe .Ảnh: Anh Tu
Many sections of the project have been cleared after being expanded to 6 lanes. Photo: Anh Tu

According to Mr. Khac Viet (living on Duong Quang Ham street), the project has completed the clearance work a long time ago and has been under construction for several years.

Currently, the site clearance project is almost complete. On both sides of the road, people have repaired and rebuilt their houses to stabilize their lives.

However, due to the construction process, dust and electric poles are still scattered in the middle of the road, affecting the daily life of the people. Mr. Viet hopes that the project will be completed quickly so that business and life can return to normal.

Mot lo cot nam giua duong chua duoc thao do. Ảnh: Anh Tu
A bunker in the middle of the road has not been dismantled. Photo: Anh Tu
Nhieu tru dien van an ngu giua duong. Ảnh: Anh Tu
Many electric poles still block the road. Photo: Anh Tu

According to the HCM City Traffic Construction Investment Project Management Board (Traffic Board - investor), up to now, the locality has only handed over the site for 420/425 cases. The remaining 4 cases have not been resolved, causing difficulties for synchronous construction.

Nguoi dan sua sang nha cua on dinh cuoc song. Ảnh: Anh Tu
People repair their houses to stabilize their lives. Photo: Anh Tu

"Sections like from Nguyen Thai Son Street to Road No. 2 still have 1 household and 2 bunkers.

The section from Highway 2 to the end of the route also encountered obstacles because of a case of national defense land and a bunker that had not been relocated.

The Traffic Committee recommends that the Ho Chi Minh City People's Committee soon issue a document reporting to the Ministry of National Defense on the relocation and dismantling of the bunkers.

Go Vap District needs to hand over the remaining land as soon as possible and the electricity sector needs to speed up the progress of undergrounding the power grid and reclaiming existing power poles to ensure that the project can be constructed synchronously and completed early in 2025," said the Traffic Department.

Mot so doan sau khi hoan thanh viec mo rong va tai lap mat bang dang duoc phia dien luc thuc hien viec ngam hoa luoi dien va gan tru den.
Some sections after completing the expansion and re-establishment of the land are being covered by the underground power grid and the installation of lamp posts. Photo: Anh Tu

Duong Quang Ham Street is one of the important backbone roads of Go Vap district, sharing traffic with several roads such as Phan Van Tri, Le Duc Tho, Quang Trung... which have often been in a state of traffic congestion, especially during rush hour.

Therefore, when the expansion is completed, the traffic infrastructure in Go Vap district will have many significant improvements.

Anh Tú
TIN LIÊN QUAN

The 500 billion VND bridge at the western gateway of Ho Chi Minh City will open to traffic in early 2025

|

HCMC - The nearly 500 billion VND Tan Ky - Tan Quy Bridge at the western gateway of HCMC has reached about 85% of construction progress, expected to open to traffic on January 15, 2025.

The road worth over 1,000 billion VND at the western gateway of Ho Chi Minh City has been completed

|

The project to expand 2 km of Tan Ky Tan Quy Street (Binh Tan District) has reached its completion after more than 1 year of construction, helping to solve the traffic jam problem at the western gateway of Ho Chi Minh City.

The 2,300 billion VND project to relieve traffic jams in Go Vap is still in disarray

|

HCMC - The project to expand Duong Quang Ham Street (Go Vap) with a total capital of 2,300 billion VND is still in disarray and unfinished despite the goal of opening to traffic by the end of 2024.

Ho Chi Minh City residents dance in the rain to watch the gathering because it only happens once every 50 years

|

HCMC - Although it rained in the center of HCMC, with a heart for the April 30 festival, people still patiently stood in the rain to watch the drill.

Submitting to the National Assembly a pilot policy on specific policies for social housing development

|

The draft Resolution on a number of specific mechanisms and policies for social housing development is eligible for submission to the National Assembly for consideration and approval at the 9th Session.

Appointing the Provincial Party Secretary and Deputy Secretary after completing the merger

|

The Central Organizing Committee will advise and submit to the Politburo and the Secretariat to appoint secretaries and deputy secretaries of provincial and municipal Party committees after the localities complete the merger.

Yen Bai Chairman directs handling of illegal sand mining and gathering

|

Yen Bai - The Chairman of the Provincial People's Committee directed departments and branches to inspect and strictly handle illegal sand mining and gathering after the reflection of Lao Dong Newspaper.

Live football The Cong Viettel 1-0 Song Lam Nghe An: Round 2

|

Live match between The Cong Viettel and Song Lam Nghe An in round 20 of V.League, taking place at 7:15 p.m. today (April 25).

The 500 billion VND bridge at the western gateway of Ho Chi Minh City will open to traffic in early 2025

Tâm Tú |

HCMC - The nearly 500 billion VND Tan Ky - Tan Quy Bridge at the western gateway of HCMC has reached about 85% of construction progress, expected to open to traffic on January 15, 2025.

The road worth over 1,000 billion VND at the western gateway of Ho Chi Minh City has been completed

Tâm Tú |

The project to expand 2 km of Tan Ky Tan Quy Street (Binh Tan District) has reached its completion after more than 1 year of construction, helping to solve the traffic jam problem at the western gateway of Ho Chi Minh City.

The 2,300 billion VND project to relieve traffic jams in Go Vap is still in disarray

TÚ QUÂN |

HCMC - The project to expand Duong Quang Ham Street (Go Vap) with a total capital of 2,300 billion VND is still in disarray and unfinished despite the goal of opening to traffic by the end of 2024.