Metro No. 1 in Ho Chi Minh City asks to postpone construction by another year despite commercial operation

MINH QUÂN |

HCMC - The HCMC Urban Railway Management Board (MAUR) proposed that the HCMC People's Committee adjust the completion time of Metro Line 1 project to the end of the fourth quarter of 2025.

According to MAUR, Decision No. 3975/QD-UBND dated September 24, 2024 of the Ho Chi Minh City People's Committee stipulates that the completion date of Metro Line 1 is the end of the fourth quarter of 2024.

Up to now, the main construction packages and operating equipment have been accepted, ensuring requirements on fire prevention and fighting, environment, system safety, serving the Metro line to be put into commercial operation by the end of the fourth quarter of 2024.

Since the pilot operation, Metro Line 1 has safely served more than 5 million passengers, received support from the people and contributed to the formation of a new transportation culture, promoting socio-economic development for the city.

However, MAUR said that some auxiliary items such as the information technology system for the maintenance and operation building (O&M) and the construction of the O&M office building are still under construction, expected to be completed in June 2025.

Therefore, MAUR recommends that the Ho Chi Minh City People's Committee adjust the time to complete the entire project to the end of the fourth quarter of 2025 to have a basis for acceptance and payment.

Metro Line 1 is the first urban railway line in Ho Chi Minh City, with a total investment of more than 43,757 billion VND. Up to now, the accumulated disbursement of the entire project has reached about 74.7% of the total investment capital.

MAUR emphasized that this adjustment does not affect the operation and exploitation activities of Metro Line 1 nor does it create a total investment for the project. Funding for the remaining items has been allocated in the 2025 public investment plan.

The main packages such as CP1a, CP1b, CP2, CP3 have been accepted and completed in December 2024. Currently, the investor is coordinating with contractors to carry out warranty, repair defects, purchase replacement materials, and sign a consulting contract for operation supervision and maintenance.

MAUR is also closely coordinating with Urban Railway Company No. 1 to ensure safe and efficient operation of the metro line.

According to the instructions of the Ministry of Planning and Investment (now the Ministry of Finance), Metro Line 1 is a group A project, under the decision-making authority of the provincial People's Committee.

Therefore, MAUR recommends that the Ho Chi Minh City People's Committee soon consider and approve the adjustment of the construction completion time to continue implementing acceptance procedures in accordance with regulations.

MINH QUÂN
RELATED NEWS

Inauguration of Metro Line 1 after serving 5 million visitors

|

HCMC - On the morning of March 9, the HCMC People's Committee held the Inauguration Ceremony of Metro Line 1 (Ben Thanh - Suoi Tien) after serving more than 5 million passengers in nearly 3 months.

Prime Minister requests to terminate payment for Metro No. 1 project before April 30

|

Prime Minister Pham Minh Chinh requested to complete payment to the contractor of Metro Line 1 project in Ho Chi Minh City before April 30, 2025

Metro No. 1 in Ho Chi Minh City was once hit by lightning and slid due to heavy rain

|

HCMC - After 2 months of operation, Metro Line 1 (Ben Thanh - Suoi Tien) encountered 5 incidents related to signals, power outages due to lightning and wheelies due to heavy rain.

Live football U23 Vietnam vs U23 Korea in the 3rd place match of the AFC U23 Championship

|

Live broadcast of the 2026 AFC U23 Championship 3rd place match between U23 Vietnam and U23 Korea, taking place at 10:00 PM today (January 23).

General Secretary, President of Laos to pay state visit to Vietnam soon

|

General Secretary and President of Laos Thongloun Sisoulith and his wife will pay a state visit to Vietnam for 2 days.

Announcement about congratulatory telegrams for the Congress

|

From the opening session to now, our Party Congress has received an additional 339 congratulatory letters and telegrams from political parties, organizations, international friends and Vietnamese people abroad, including 58 letters and telegrams from political parties, 11 letters and telegrams, messages from regional and international organizations, 62 letters and telegrams from individuals, 120 letters and telegrams from people's organizations and localities abroad and 88 letters and telegrams from Vietnamese associations abroad.

Land use fees are still a major bottleneck in the real estate market

|

Real estate investors are under great pressure from both project development costs and increased land use fees.

Securities continue to face profit-taking pressure from bluechip stocks

|

The Vietnamese stock market could not regain its green color in the last trading session of the week when investors put unexpected caution first.

Inauguration of Metro Line 1 after serving 5 million visitors

NHÓM PV |

HCMC - On the morning of March 9, the HCMC People's Committee held the Inauguration Ceremony of Metro Line 1 (Ben Thanh - Suoi Tien) after serving more than 5 million passengers in nearly 3 months.

Prime Minister requests to terminate payment for Metro No. 1 project before April 30

Thanh Hà |

Prime Minister Pham Minh Chinh requested to complete payment to the contractor of Metro Line 1 project in Ho Chi Minh City before April 30, 2025

Metro No. 1 in Ho Chi Minh City was once hit by lightning and slid due to heavy rain

MINH QUÂN |

HCMC - After 2 months of operation, Metro Line 1 (Ben Thanh - Suoi Tien) encountered 5 incidents related to signals, power outages due to lightning and wheelies due to heavy rain.