Expanding 2 expressway intersections, connecting border trade

Đinh Đại |

The investment in upgrading the IC 18 and IC 19 intersections of the Noi Bai - Lao Cai expressway plays an important role in developing border traffic infrastructure.

The IC18 intersection of Noi Bai - Lao Cai expressway will be constructed and renovated in early 2023. The project includes the following items: road, overpass, underpass, intersection with the Cam Duong - Thong Nhat planned road (2 communes and wards in Lao Cai city), lighting system...

Based on the existing IC 18 intersection at Km245 (in Xuan Tang ward, Pom Han ward and Cam Duong commune), the project will renovate 2 branches currently in operation (direction from Binh Minh ward, Lao Cai city - Hanoi and vice versa), and build 2 additional branches (direction from Binh Minh - Kim Thanh and vice versa) to create a complete intersection.

Vi tri nut giao IC 18 tai thanh pho Lao Cao. Anh: Dinh Dai
Location of IC 18 intersection in Lao Cai city. Photo: Dinh Dai

The total length of the new and renovated route is about 2.8 km. The starting point is at the intersection with Cam Duong - Thong Nhat route (waiting for planning), the ending point is at the intersection with Noi Bai - Lao Cai expressway. The project is invested by the Department of Transport with a capital of more than 50 billion VND.

According to the reporter's records on October 15, the upgrading of the branches of IC 18 intersection has been completed. Currently, all vehicles can move easily and conveniently.

Dong bo cac nhanh ket noi cua nut giao cao toc giup cac phuong tien giao thong di chuyen de dang hon. Anh: Dinh Dai
Synchronizing the connecting branches of the expressway interchange helps vehicles move more easily. Photo: Dinh Dai

Speaking to Lao Dong, Mr. Pham Minh Hai - Deputy Director of the Management Board of Investment and Construction of Traffic Works in Lao Cai Province - said: "Upgrading IC 18 intersection helps vehicles move more conveniently and easily in getting on and off the highway in many directions. Thereby shortening travel time, creating momentum for economic development."

According to Mr. Pham Minh Hai, the renovation of IC 18 intersection is now complete.

Hinh hai nut giao cao toc IC 18 hoan chinh sau khi duoc dau tu 50 ti dong de nang cap, mo rong. Anh: Dinh Dai
The completed shape of the IC 18 expressway interchange after an investment of 50 billion VND for upgrading and expansion. Photo: Dinh Dai

"Because it has to go through many stages and management units, for many months we have had to wait for related legal procedures from the Road Management Department. Up to now, all procedures have been completed and the road is ready to operate at full capacity," added the Deputy Director of the Lao Cai Province Traffic Construction Investment Project Management Board.

The next intersection with expanded connecting branches is IC 19 connecting with National Highway 4E and Provincial Road 155, near Dong Tuyen commune (Lao Cai city).

Cao toc Noi Bai - Lao Cai dong vai tro quan trong trong viec giao thuong, xuat khau hang hoa cua Viet Nam. Anh: Dinh Dai
Noi Bai - Lao Cai Expressway plays an important role in Vietnam's trade and export of goods. Photo: Dinh Dai

According to research, the project has an investment of nearly 19 billion VND, including items, connecting roads, drainage system, bridges, lighting, trees...

Project implementation period is from 2023 - 2025. Of which, 8 households in Dong Tuyen commune are affected and must relocate.

When the connecting branches are completed, traveling from National Highway 4E and Provincial Road 155 to Noi Bai - Lao Cai Expressway and vice versa will also become more convenient. From there, it will meet the increasing number of vehicles passing through Lao Cai.

Khoang cach tu nut giao IC 18 den IC 19 (nut giao cuoi cua cao toc Noi Bai Lao Cai) la 11 km. Anh: Dinh Dai
The distance from IC 18 to IC 19 (the final intersection of Noi Bai - Lao Cai highway) is 11 km. Photo: Dinh Dai

Mr. Bui Van Tuyen (Dong Tuyen commune, Lao Cai city) said: "Our people strongly agree and support the upgrading of this expressway intersection to increase trade and economic development.

We hope that the relevant authorities will consider the specific factors and arrange the resettlement areas in accordance with our production and business conditions. At the same time, we will soon implement the project.”

Noi Bai - Lao Cai Expressway has a total length of 263.5 km.

The total investment cost of the project in phase 1 is 19,984 billion VND, equivalent to 1.249 billion USD, of which 1.096 billion USD is borrowed from ADB.

The section through Lao Cai province is 73 km long, passing through 4 districts and cities.

Đinh Đại
RELATED NEWS

Speeding up construction of 1,300 billion VND road connecting Noi Bai - Lao Cai expressway

|

Yen Bai - The route connecting Nghia Lo with Noi Bai - Lao Cai expressway is being accelerated, with the goal of completion by 2025.

300 billion VND intersection connecting Noi Bai - Lao Cai expressway

|

Yen Bai - After 1.5 years of construction, the IC 13 intersection project of Noi Bai - Lao Cai expressway has gradually been completed, ready for completion in the first quarter of 2025.

Noi Bai - Lao Cai Expressway opens to traffic after 8 days of landslide

|

A landslide has rendered the Noi Bai – Lao Cai expressway interchange (IC18) inoperable and will take many days to repair.

Hour 9: Should we get married? - Part 2

|

Hour 9 No. 167 - The husband reunites with his first love after catching his wife cheating and demanding a divorce. Should they get married again?

School apologizes for publicizing the list of students in difficulty at the opening ceremony

|

Hanoi - Thai Thinh Primary School, Dong Da, Hanoi has just issued an apology letter for a major mistake at the opening ceremony.

U23 Vietnam beat U23 Singapore, holding the top spot in Group C of the U23 Asian qualifiers

|

On the evening of September 6, the U23 Vietnam team won U23 Singapore with a score of 1-0 in the second match of Group C of the 2026 U23 Asian qualifiers.

The State Bank coordinates with the Ministry of Public Security to manage the gold market

|

The State Bank will closely coordinate with the Ministry of Public Security, the Government Inspectorate and agencies to implement the management of the gold market.

Thousands of military officers and soldiers marched back to their units after the A80

|

The military units in the Southern region used 85 cars to transport 1,374 people and materials and equipment to Hanoi Station and Noi Bai Airport.

Speeding up construction of 1,300 billion VND road connecting Noi Bai - Lao Cai expressway

Trần Bùi |

Yen Bai - The route connecting Nghia Lo with Noi Bai - Lao Cai expressway is being accelerated, with the goal of completion by 2025.

300 billion VND intersection connecting Noi Bai - Lao Cai expressway

Trần Bùi |

Yen Bai - After 1.5 years of construction, the IC 13 intersection project of Noi Bai - Lao Cai expressway has gradually been completed, ready for completion in the first quarter of 2025.

Noi Bai - Lao Cai Expressway opens to traffic after 8 days of landslide

Đinh Đại |

A landslide has rendered the Noi Bai – Lao Cai expressway interchange (IC18) inoperable and will take many days to repair.