Expanding nearly 40km of road in Dong Nai connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade and expand DT 773 route, nearly 40km long, passes through 3 districts of the province connecting Ho Chi Minh City Ring Road 4 and Long Thanh airport.

On March 16, the Dong Nai Province Traffic Construction Investment Project Management Board said that the project to upgrade and expand DT 773 road passing through Xuan Loc, Cam My, and Long Thanh districts, nearly 40km long, is expected to complete the approval of the feasibility study report in 2025.

The project to upgrade and expand DT 773 route has a total length of 39km, starting point intersecting with National Highway 1 (Km1789+300) in Xuan Tam commune, Xuan Loc district, ending point of the route to Huong Lo 10 intersecting with Ho Chi Minh City Ring Road 4.

The project has a total investment of about 4,311 billion VND, of which the construction cost is about 1,927 billion VND from the provincial budget.

The implementation period is 2022-2027.

Up to now, the project has completed the appraisal work at the Department of Construction Investment Management - Ministry of Transport (now Ministry of Construction) and has submitted a document to the Department of Planning and Investment (now Department of Finance) for consideration and submission to the Provincial People's Committee for approval of the project.

In April 2025, the Dong Nai Province Traffic Construction Investment Project Management Board contacted the People's Committee of Cam My District to adjust the route in accordance with the general construction planning of Long Giao Town, Cam My District to ensure the conditions for project approval.

The Dong Nai Province Traffic Construction Investment Project Management Board also plans to complete the approval of the feasibility study report in 2025 as a basis for implementing the next steps.

The project to upgrade and expand DT 773 route helps connect and shorten travel time from Cam My, Xuan Loc, Long Thanh districts as well as the provinces of the Central Highlands and South Central regions to Long Thanh airport. Quadrangle connection of Bien Hoa - Long Thanh - Trang Bom - Nhon Trach industrial parks to meet traffic and transportation needs, reduce traffic volume for National Highway 1 contributes to the economic and social development of districts with the route in particular and the entire Dong Nai province, the key economic region in the South in general.

Currently, Dong Nai province is investing in expanding 3 projects including: DT 769 road, DT 770B and DT 773 with a total investment of more than VND 18,000 billion to connect Long Thanh airport.

HÀ ANH CHIẾN
RELATED NEWS

Over 121 billion VND to train 4,800 on-site human resources for Long Thanh airport

|

The Long Thanh airport project is expected to be put into operation in 2026. Dong Nai province is urgently preparing human resources for the project, prioritizing vocational training and solving employment for people whose land is recovered.

Prime Minister gives lucky money to workers constructing Long Thanh airport

|

Dong Nai – Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officials, engineers and workers who are working during Tet at Long Thanh airport.

Construction through Tet, racing to meet progress of Long Thanh airport project

|

Dong Nai - Although it is the 2025 Lunar New Year holiday, thousands of officers, engineers and workers at Long Thanh airport are still speeding up construction throughout Tet.

The first medical unit in Vietnam to receive investment from the world's leading fund manager

|

Medlatec Group becomes the first medical unit in Vietnam to be invested by Ares Asia Private equity group.

Latest forecast on this year's winter weather trends

|

According to meteorologists, there are many signs that this winter is likely to be colder than the average of many years.

Hanoi Police held to a draw by Australian team in AFC Champions League Two

|

On the evening of October 23, Hanoi Police Club drew 1-1 with Macarthur at the AFC Champions League Two 2025-2026.

Vingroup shares flourish, stocks maintain green

|

The stock market maintained its upward momentum mainly thanks to the attraction of the " themselves" group of Vingroup stocks.

Red rain, The War Elephants do not promise to win big, and the Kite Awards risk not having bonuses

|

The film "Red Rain" with an unprecedented effect in theaters is predicted to reap a "rain" of industry awards such as the Canh Dieu Award.

Over 121 billion VND to train 4,800 on-site human resources for Long Thanh airport

Hà Anh Chiến |

The Long Thanh airport project is expected to be put into operation in 2026. Dong Nai province is urgently preparing human resources for the project, prioritizing vocational training and solving employment for people whose land is recovered.

Prime Minister gives lucky money to workers constructing Long Thanh airport

HÀ ANH CHIẾN - NHƯ QUỲNH |

Dong Nai – Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officials, engineers and workers who are working during Tet at Long Thanh airport.

Construction through Tet, racing to meet progress of Long Thanh airport project

HÀ ANH CHIẾN - NHƯ QUỲNH |

Dong Nai - Although it is the 2025 Lunar New Year holiday, thousands of officers, engineers and workers at Long Thanh airport are still speeding up construction throughout Tet.