Expanding nearly 40km of road in Dong Nai connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade and expand DT 773 route, nearly 40km long, passes through 3 districts of the province connecting Ho Chi Minh City Ring Road 4 and Long Thanh airport.

On March 16, the Dong Nai Province Traffic Construction Investment Project Management Board said that the project to upgrade and expand DT 773 road passing through Xuan Loc, Cam My, and Long Thanh districts, nearly 40km long, is expected to complete the approval of the feasibility study report in 2025.

The project to upgrade and expand DT 773 route has a total length of 39km, starting point intersecting with National Highway 1 (Km1789+300) in Xuan Tam commune, Xuan Loc district, ending point of the route to Huong Lo 10 intersecting with Ho Chi Minh City Ring Road 4.

The project has a total investment of about 4,311 billion VND, of which the construction cost is about 1,927 billion VND from the provincial budget.

The implementation period is 2022-2027.

Up to now, the project has completed the appraisal work at the Department of Construction Investment Management - Ministry of Transport (now Ministry of Construction) and has submitted a document to the Department of Planning and Investment (now Department of Finance) for consideration and submission to the Provincial People's Committee for approval of the project.

In April 2025, the Dong Nai Province Traffic Construction Investment Project Management Board contacted the People's Committee of Cam My District to adjust the route in accordance with the general construction planning of Long Giao Town, Cam My District to ensure the conditions for project approval.

The Dong Nai Province Traffic Construction Investment Project Management Board also plans to complete the approval of the feasibility study report in 2025 as a basis for implementing the next steps.

The project to upgrade and expand DT 773 route helps connect and shorten travel time from Cam My, Xuan Loc, Long Thanh districts as well as the provinces of the Central Highlands and South Central regions to Long Thanh airport. Quadrangle connection of Bien Hoa - Long Thanh - Trang Bom - Nhon Trach industrial parks to meet traffic and transportation needs, reduce traffic volume for National Highway 1 contributes to the economic and social development of districts with the route in particular and the entire Dong Nai province, the key economic region in the South in general.

Currently, Dong Nai province is investing in expanding 3 projects including: DT 769 road, DT 770B and DT 773 with a total investment of more than VND 18,000 billion to connect Long Thanh airport.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Over 121 billion VND to train 4,800 on-site human resources for Long Thanh airport

|

The Long Thanh airport project is expected to be put into operation in 2026. Dong Nai province is urgently preparing human resources for the project, prioritizing vocational training and solving employment for people whose land is recovered.

Prime Minister gives lucky money to workers constructing Long Thanh airport

|

Dong Nai – Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officials, engineers and workers who are working during Tet at Long Thanh airport.

Construction through Tet, racing to meet progress of Long Thanh airport project

|

Dong Nai - Although it is the 2025 Lunar New Year holiday, thousands of officers, engineers and workers at Long Thanh airport are still speeding up construction throughout Tet.

Opening a peak period against fake drugs, milk and health protection foods

|

The Ministry of Health recommends that localities launch a peak period from May 15 to June 15 to fight against fake drugs, dairy and health protection foods.

Use the remaining salary reform funds to pay for the restructuring of the apparatus

|

The National Assembly resolved to use the remaining salary reform funds to pay for regimes and policies for cadres and civil servants when restructuring the apparatus.

Hour 9: Who is the worthy one? - Part 2

|

Hour 9 No. 155 - Father remarries after his wife passes away. The wife is pregnant, the children suspect that their property will be appropriated. What will be the ending of this story?

Places with Uncle Ho's footsteps in Hue

|

HUE - The ancient capital of Hue is a place that sows the seeds of aspiration, fosters patriotism and the will to overcome Uncle Ho's time.

Russia responds to news about the proposal to resume dialogue with NATO

|

Sooner or later, Russia and NATO will also have to discuss security issues, Kremlin Spokesman Dmitry Peskov said.

Over 121 billion VND to train 4,800 on-site human resources for Long Thanh airport

Hà Anh Chiến |

The Long Thanh airport project is expected to be put into operation in 2026. Dong Nai province is urgently preparing human resources for the project, prioritizing vocational training and solving employment for people whose land is recovered.

Prime Minister gives lucky money to workers constructing Long Thanh airport

HÀ ANH CHIẾN - NHƯ QUỲNH |

Dong Nai – Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officials, engineers and workers who are working during Tet at Long Thanh airport.

Construction through Tet, racing to meet progress of Long Thanh airport project

HÀ ANH CHIẾN - NHƯ QUỲNH |

Dong Nai - Although it is the 2025 Lunar New Year holiday, thousands of officers, engineers and workers at Long Thanh airport are still speeding up construction throughout Tet.