Some households deliberately encroach, do not hand over land for the construction of the 2.5 belt road in Hanoi

HỮU CHÁNH |

Hanoi - Some households deliberately re-encroach on the site and refuse to hand over the site to the contractor for the Ring Road 2.5 project.

In early December, the construction of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being actively implemented by contractors.

The entire route is divided into 5 packages, of which the busiest construction work takes place in package 2 - the construction of the L3 bridge across the Lu River.

a
The L3 bridge over the Lu River under the Ring Road 2.5 project, Dam Hong - National Highway 1A section (Hanoi) is under construction. Photo: Song Huu

Informing Lao Dong, a representative of Hoang Mai Hanoi Construction Investment Company Limited (project enterprise) said that up to now, the site clearance (GPMB) for the Ring Road 2.5 project, Red Dam - National Highway 1A section, has basically been completed.

The volume of construction work on technical infrastructure works (electricity, water, telecommunications) is estimated at 75%, of which the water supply system is 100% complete.

Regarding construction and installation, the main items have been deployed such as traffic roads with many sections, the road surface has been constructed with raw grain asphalt concrete; the drainage system of the 2x3x2m box culvert has been completed.

The L3 bridge over the Lu river (package No. 2) has completed all bridge piers and cast 118/120 girder blades.

a
A section of the route was paved on November 23. Photo: Song Huu

According to the representative of Hoang Mai Hanoi Construction Investment Company Limited, the project was restarted in May 2025, and there are still some difficulties and problems that cannot be completely resolved.

Currently, there are still some locations along the route, where people have not yet handed over all the land within the boundary, some households have deliberately re-offended the land and fiercely opposed not handing over the land or being re-offended for use. This affects the progress of the implementation of the work and items of the package.

The project enterprise has been coordinating with Khuong Dinh, Dinh Cong and Phuong Liet wards to develop a plan to clear these cases, but the implementation progress is still slow.

a
A household re-encroached and built a construction within the Ring Road 2.5 project (Phuong Liet ward). Photo: Song Huu

In addition, the construction site in the area on the left of the route from Tran Nguyen Dan Street (about Km1+284.61) to the right bank of Lu River (about Km1+378) at the beginning of L3 Bridge (Trinh Dinh Cuu Street) is currently assigned by the Housing and Urban Development Investment Corporation (HUD) to manage the site in this area, but the reconstruction work belongs to the Ring Road 2.5 project.

Regarding this, the Hanoi Traffic Construction Investment Project Management Board has proposed and recommended that the City People's Committee consider and direct the final settlement of the site clearance work for this area. However, up to now, the city has not yet issued instructions to remove them.

a
The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is about 1.6km long, with a total investment of more than 1,300 billion VND. Photo: Song Huu

Another problem that the project enterprise also mentioned is that the project's adjusted feasibility study report has not yet been approved, the construction drawing design has not been appraised and approved. This has caused the construction of items and work of the project to be adjusted and cannot be implemented due to inadequacy.

Hoang Mai Hanoi Construction Investment Company Limited requested the Hanoi People's Committee, departments, branches and local authorities to promptly remove the above obstacles to ensure the project is completed in the first quarter of 2026.

Regarding the two households re-encroaching on the site in Phuong Liet ward, the leader of the People's Committee of the ward said that in case the households, after being propagandized, mobilized, and explained, as well as having resolved legal recommendations and proposals according to legal regulations, still do not comply with and hand over the site, the ward will take the next steps.

HỮU CHÁNH
RELATED NEWS

End the dusty and polluted situation at the billion-dollar road project in Hanoi

|

Hanoi - Through inspection, the Department of Construction said that the Dam Hong area of the Ring Road 2.5 project is no longer dusty as reported by the press.

Hanoi Ring Road 2.5 enters the final stage, contractors mobilize maximum human resources for construction

|

Hanoi - The contractor has completed the C15 asphalt paving item at the beginning of the route of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, with a total capital of more than 1,300 billion VND.

Throughout the night of constructing a billion-dollar road in Hanoi, the finishing time is very close

|

Hanoi - The contractor mobilized many machines and workers overnight to construct the Ring Road 2.5 project, ensuring the quality and progress set out.

Witnessing snow covering the top of Mau Son

|

Lang Son - On January 22, the temperature at Mau Son peak dropped to 0 degrees, causing snow and ice, covering from tree branches, lawns to fences, walkways.

Comrade Trinh Van Quyet re-elected to the 14th Central Committee of the Party

|

Comrade Trinh Van Quyet - Secretary of the 13th Party Central Committee, Head of the Central Propaganda and Mass Mobilization Committee - re-elected to the 14th Party Central Committee.

U23 Vietnam list before the 3rd place match of the AFC U23 Championship

|

U23 Vietnam can only register the squad with 21 players in the match against U23 Korea.

Mr. Putin assesses the price of the US purchase of Greenland

|

Mr. Putin said that the Greenland issue is not related to Moscow's interests, and gave an assessment of this deal.

End the dusty and polluted situation at the billion-dollar road project in Hanoi

SÓNG HỮU |

Hanoi - Through inspection, the Department of Construction said that the Dam Hong area of the Ring Road 2.5 project is no longer dusty as reported by the press.

Hanoi Ring Road 2.5 enters the final stage, contractors mobilize maximum human resources for construction

SÓNG HỮU |

Hanoi - The contractor has completed the C15 asphalt paving item at the beginning of the route of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, with a total capital of more than 1,300 billion VND.

Throughout the night of constructing a billion-dollar road in Hanoi, the finishing time is very close

SÓNG HỮU |

Hanoi - The contractor mobilized many machines and workers overnight to construct the Ring Road 2.5 project, ensuring the quality and progress set out.