2025 breakthrough to bring Long Thanh airport to the finish line soon

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport Project Management Board said that 2025 is the year to accelerate and make a breakthrough to bring the project to the earliest progress milestone.

The Long Thanh airport project in Dong Nai province is entering an accelerated phase as a series of important packages are on track to reach the finish line early, while many other packages are about to start construction so that the project can be exploited synchronously.

Reporter of Lao Dong Newspaper interviewed Mr. Duong Quang Dien - Permanent Deputy Director of Long Thanh Airport Project Management Board about the plans and determination to bring the project ahead of schedule, ensuring quality and safety...

Goi thau nha ga hanh khach va goi thau duong cat ha canh san bay Long Thanh. Anh: HAC
Bidding package for passenger terminal and runway of Long Thanh airport. Photo: HAC

Sir, how is the construction progress of the packages at Long Thanh airport project?

- Entering the beginning of 2025, this is a time of great determination and effort from the entire Project Management Board, construction units, engineers, workers, supervision consultants...

In 2025, we are determined to basically complete the construction of the Long Thanh airport project phase 1.

For the passenger terminal project, the construction atmosphere is extremely urgent, striving to complete the roof steel structure work before the 2025 rainy season to ensure the installation of equipment systems inside the terminal project.

In the central part of the passenger terminal, there are also many engineers and workers installing special, modern technical systems of the aviation industry.

Traffic items such as runways have exceeded the schedule by 3 months, the goal is to complete construction of the runway by April 30, 2025 and put it into technical operation.

At the same time, the construction of the connecting traffic route has reached over 70% of the volume, exceeding the contract schedule and determined to put traffic route No. 1 into operation on September 2, 2025.

Regarding other technical systems, recently, Vietnam Airports Corporation (ACV) has started construction of aircraft parking lots, aircraft fuel supply systems, etc. and is currently under urgent construction.

In 2025, we determined, following the direction of the Prime Minister, to be the year of acceleration and breakthrough, creating the premise to bring Long Thanh airport project to the earliest progress milestone.

Thi cong tai goi thau 4.6 - duong cat ha canh san bay Long Thanh. Anh: HAC
Construction at package 4.6 - Long Thanh airport runway. Photo: HAC

What are the difficulties in the construction and implementation of Long Thanh airport project, sir?

- Long Thanh airport project is a new project, building a completely new airport, all construction items are constructed at the same time.

Furthermore, because the project consists of many complex technical systems, the first construction must ensure the correct construction sequence of the technical systems, ensuring the quality of the project.

In particular, it is necessary to ensure the connection between bid packages, between the passenger terminal bid package, the inland port traffic bid package, and related bid packages providing power systems, etc.

Therefore, we must establish the most scientific progress so that the key project achieves the best quality and ensures safety. At the same time, work with contractors to find solutions to shorten the implementation progress as much as possible.

Do you have any recommendations to make the Long Thanh airport project operate effectively as soon as it is put into operation?

- We have repeatedly requested the competent authorities to have a plan to soon expand the main connecting traffic routes from Ho Chi Minh City to Long Thanh airport, such as the Ho Chi Minh City - Long Thanh - Dau Giay expressway.

Currently, traffic density on this highway is quite dense, so it needs to be expanded soon so that when the Long Thanh airport project is put into operation, the routes connecting Long Thanh airport with key areas such as Ho Chi Minh City will ensure convenient time for passengers during the process of carrying out aviation procedures.

Regarding runway number 2, the Long Thanh Airport Project Management Board has had a detailed report, proposing the earliest start date to synchronously complete runway number 2 in phase 1 of the Long Thanh Airport project.

HÀ ANH CHIẾN
TIN LIÊN QUAN

New Year's Eve fireworks at Long Thanh airport resettlement area

|

Dong Nai will set off fireworks on New Year's Eve at 5 locations, including Loc An - Binh Son Resettlement Area (resettlement of Long Thanh airport project).

Hot in Saigon: The "heart" of Long Thanh airport gradually revealed

|

Hot News Saigon January 4: The "heart" of Long Thanh airport is gradually revealed; Images of 2 important bridges at An Phu intersection are about to be completed;...

Long Thanh airport revealed after more than 1 year of rapid construction

|

Dong Nai - After more than 1 year of rapid construction, the Long Thanh airport passenger terminal has gradually emerged, taking on the traditional lotus shape.

Many scandals are happening at the Vietnam Gas Association

|

The Ministry of Home Affairs said that it has just received a document requesting consideration of inspection and examination of the implementation of the Charter of the Vietnam Gas Association.

Completing the legal basis for the arrangement of the Vietnam Fatherland Front and socio-political organizations

|

On April 24, in Hanoi, the Central Committee of the Fatherland Front (Fatherland Front) in Vietnam held a seminar to collect comments on the Law on Amending and Supplementing a Number of Articles of the Vietnam Fatherland Front Law, Youth Law, Trade Union Law, Law on Execution of the grassroots level.

After a series of dry and sunny days, Cao Bang experiences hail

|

Cao Bang - A 10-minute hailstorm fell on Bao Lac town (Bao Lac district) on the afternoon of April 24.

Ho Chi Minh City and Binh Duong no longer have the same name of ward and commune after the arrangement

|

HCMC - Before HCMC named Tan Dinh ward and Binh My commune, Binh Duong province chose new names for the merged wards to avoid overlapping names.

Do not let ambitious people and corrupt people get into the Party Committee

|

The Deputy Prime Minister emphasized that people who are not qualified, show signs of decline, ambition for power, corruption, and negativity should not be allowed to enter the Party Committee.

New Year's Eve fireworks at Long Thanh airport resettlement area

HÀ ANH CHIẾN |

Dong Nai will set off fireworks on New Year's Eve at 5 locations, including Loc An - Binh Son Resettlement Area (resettlement of Long Thanh airport project).

Hot in Saigon: The "heart" of Long Thanh airport gradually revealed

NGỌC ÁNH - CHÂN PHÚC |

Hot News Saigon January 4: The "heart" of Long Thanh airport is gradually revealed; Images of 2 important bridges at An Phu intersection are about to be completed;...

Long Thanh airport revealed after more than 1 year of rapid construction

HÀ ANH CHIẾN |

Dong Nai - After more than 1 year of rapid construction, the Long Thanh airport passenger terminal has gradually emerged, taking on the traditional lotus shape.