Phan Thiet airport civil works expected to start in 2025

Duy Tuấn |

Binh Thuan - The progress of the Phan Thiet Airport project, civil project under BOT contract form, is waiting for the Prime Minister to review and approve the investment policy.

On the afternoon of October 29, the Propaganda Department of Binh Thuan Provincial Party Committee and the Department of Information and Communications of the province held a conference to provide information to the press in October 2024.

At the Conference, Mr. Huynh Ngoc Thanh - Deputy Director of the Department of Transport of Binh Thuan province provided information on the implementation process of "Phan Thiet Airport Construction Investment Project, BOT civil category".

ong Huynh Ngoc Thanh - Pho Giam doc So Giao thong Van tai tinh Binh Thuan cung cap thong tin ve du an Cang hang khong Phan Thiet hang muc dan dung BOT. Anh: Duy Tuan
Mr. Huynh Ngoc Thanh - Deputy Director of the Department of Transport of Binh Thuan province provided information about the Phan Thiet Airport project, civil BOT category. Photo: Duy Tuan

Phan Thiet Airport was approved for planning by the Ministry of Transport in 2013 as a combined civil and military airport.

In the civil aviation category, the Prime Minister agreed to invest in construction under the BOT form in 2014. The People's Committee of Binh Thuan province organized the implementation of investment procedures, selected investors according to regulations and approved the results of selecting investors to implement the project, which is Rang Dong Joint Stock Company.

The project was initially designed as a 4C airport, then the Prime Minister agreed to upgrade it to a 4E airport, with a 3,050m long runway and a passenger terminal with a designed capacity of 2 million passengers/year.

Due to the adjustment of project scale and increase in total investment, the investment policy must be adjusted according to regulations.

On July 17, 2023, Binh Thuan Provincial People's Committee and Rang Dong Joint Stock Company signed a document agreeing to terminate the project contract ahead of schedule.

Regarding the progress of adjusting the project investment policy according to the PPP Law, the Department of Transport will coordinate with the consulting unit and relevant departments and branches to complete the Pre-Feasibility Study Report of the Phan Thiet Airport project, civil aviation category under the form of BOT contract.

Duong vao san bay Phan Thiet, chieu 29.10. Anh: Duy Tuan
Road to Phan Thiet airport, afternoon of October 29. Photo: Duy Tuan

On September 20, 2024, the People's Committee of Binh Thuan province submitted Document 3513 to the Prime Minister on approving the adjustment of the investment policy and terminating the contract ahead of schedule for the Phan Thiet Airport project, civil aviation item under the form of a BOT contract with the old investor.

Most recently, the Department of Transport of Binh Thuan province coordinated with the Department of Planning and Investment of the province to advise the Provincial People's Committee to send official dispatches to the Ministry of National Defense and The State Bank of Vietnam on October 25, 2024 to seek opinions on the content of the explanation of the dossier to adjust the investment policy of the Phan Thiet Airport project, civil items under the form of BOT contract.

Currently, the Ministry of Planning and Investment is coordinating with relevant agencies to review and comment on the content of the acceptance and explanation of the Provincial People's Committee in Document 3513 to report and advise the Prime Minister to consider adjusting the approval of the investment policy and terminate the contract before the deadline of the above project.

After the Prime Minister approves the adjustment of the investment policy, the Department of Transport of Binh Thuan province organizes the implementation of procedures for preparing, submitting for appraisal and approval of the project feasibility study report and coordinates with the Department of Planning and Investment to organize the selection of new investors according to current legal regulations.

Cac ha tang dang duoc xay dung o san bay Phan Thiet. Anh: Duy Tuan
Infrastructure under construction at Phan Thiet airport. Photo: Duy Tuan

More information about the current Phan Thiet airport, Mr. Huynh Ngoc Thanh - Deputy Director of the Department of Transport of Binh Thuan province said that the military project has completed all items. The 4 km long road to the airport is being paved with asphalt concrete, paved with sidewalk tiles and lighting.

"According to the Department of Transport's plan, if a replacement investor is selected in 2025, the civil project of Phan Thiet airport will be implemented at the end of 2025, and 1 year later, the civil aviation project will be operational," Mr. Thanh added.

Duy Tuấn
RELATED NEWS

General Secretary and President of Laos congratulates Vietnam on hosting the opening ceremony of the Hanoi Convention

|

General Secretary and President of Laos Thongloun Sisoulith especially congratulated Vietnam on hosting the opening ceremony of the Hanoi Convention.

Border crossings to Thailand increase after Myanmar fines scams

|

More than 1,000 people have flocked to Thailand this week after the Myanmar military attacked one of the country's largest fraud centers.

Approving the dismissal of Ms. Pham Thi Thanh Tra from the position of Minister of Home Affairs

|

The National Assembly voted to pass a Resolution approving the proposal to dismiss Ms. Pham Thi Thanh Tra from the position of Minister of Home Affairs.

Remove Mr. Do Duc Duy from the position of Minister of Agriculture and Environment

|

The National Assembly approved the dismissal of Mr. Do Duc Duy from the position of Minister of Agriculture and Environment for the 2021-2026 term.

Cao Bang mobilizes and appoints a series of key leaders

|

Cao Bang - On the afternoon of October 24, the Provincial People's Committee held a conference to announce the decision on personnel work and appoint key leaders.

Many times raising the ground, repairing houses but still having to live in flooding due to high tides

|

HCMC - Despite having raised the ground and repaired it many times, every time the tide rises, water still overflows into the house. Furniture must be positioned high, only a little carelessness will make it wet and damaged.

Heavy rain causes flooding in the Nam Hai Lang canal area, people travel by boat

|

Quang Tri - Heavy rain caused deep flooding in many low-lying areas along the O Lau River, people in Nam Hai Lang commune had to move by boat and boat.

Sân bay Phan Thiết hạng mục dân dụng sẽ có nhà đầu tư mới

DUY TUẤN |

Bình Thuận - Sau khi Thủ tướng Chính phủ phê duyệt điều chỉnh chủ trương đầu tư dự án sân bay Phan Thiết hạng mục dân dụng, Bình Thuận sẽ lựa chọn nhà đầu tư mới.

Thẩm định điều chỉnh chủ trương đầu tư hạng mục dân dụng sân bay Phan Thiết

DUY TUẤN |

Bình Thuận – Đến đầu tháng 4.2024, Bộ Kế hoạch và Đầu tư đang tổ chức thẩm định điều chỉnh chủ trương đầu tư dự án Cảng hàng không Phan Thiết, hạng mục hàng không dân dụng theo hình thức hợp đồng BOT từ cấp 4C lên cấp 4E.

Dự án Cảng hàng không Phan Thiết vướng mắc lớn nhất là giải phóng mặt bằng

DUY TUẤN |

Bình Thuận - Dự án Cảng hàng không Phan Thiết khởi công từ cách đây hơn 8 năm, sau đó được Bộ GTVT phê duyệt từ 4C lên cấp 4E. Hiện các hạng mục quân sự trong sân bay đang được các đơn vị của quân đội thi công. Tuy nhiên, hạng mục dân dụng (hình thức BOT) vẫn còn nhiều khó khăn và vẫn chưa chọn được nhà đầu tư xây dựng mới để thay thế.