Dredging hundreds of sewers to reduce flooding in Quang Ngai City

VIÊN NGUYỄN |

Quang Ngai City is dredging mud and soil on sewers to reduce local flooding during heavy rains.

Dredging sewers on 151 roads

Quang Ngai City has nearly 104km of drainage pipes and 6.5km of canals. The reason why Quang Ngai City is often flooded during heavy rains is because the drainage system was built before 2000, is small and not synchronized. The main drainage canals are silted up and overgrown with weeds but have not been dredged or cleared, reducing their capacity, greatly affecting the drainage flow from the inner city to the river.

A survey by the People's Committee of Quang Ngai City shows that the current situation of long-term and quite serious flooding is concentrated in 9 wards with about 19 flooded locations distributed in 5 basins.

Another rare cause of flooding is that Quang Ngai City has a rainwater drainage system and an untreated domestic wastewater drainage system that share a sewer line, leading to low dilution levels and a strong odor coming from the sewers during the dry season.

To reduce the stench from entering the house, affecting daily life and business, people in Quang Ngai City use sacks or other items to cover the drains to prevent the stench. However, when it rains heavily, people “forget” to take these items, causing the water to not drain, which is also the cause of local flooding in Quang Ngai City.

Cong nhan moi truong lien tuc hut tap chat ben trong cac cong thoat nuoc xung quanh Benh vien Da khoa tinh Quang Ngai, nham khoi thong dong chay moi khi co mua lon. Anh: Vien Nguyen
Environmental workers continuously suck out impurities inside the drains around Quang Ngai General Hospital, to clear the flow every time there is heavy rain. Photo: Vien Nguyen

In order to minimize localized flooding, since the 2023 rainy season, authorities have assigned workers to stand guard at manholes on the road to clear the flow and stand right next to the manholes, placing warning signs for passersby.

Talking to Lao Dong Newspaper reporter, Mr. Bui Van Quang - General Director of Quang Ngai Urban Environment Joint Stock Company - said that over the past 45 days, Quang Ngai Urban Environment Joint Stock Company has increased means, equipment, specialized vehicles and workers to focus on dredging mud and soil in all sewers on 151 inner-city roads in Quang Ngai City. In particular, priority is given to sections and sewers in "low-lying areas" on Phan Dinh Phung, Hung Vuong, Nguyen Ba Loan, Nguyen Nghiem, Tran Hung Dao, Quang Trung streets... At the same time, damaged manhole covers are replaced; screens are repaired in front of the manholes to ensure drainage and prevent garbage and hard objects from flowing into the sewers. It is expected that by October 30, the dredging will be completed...

According to Mr. Bui Van Quang, whenever there is heavy rain or storms, the company is always ready to assign about 15 people to be on duty at flood black spots, clearing the flow to increase drainage capacity for the city.

Waiting for the 1,000 billion VND flood prevention project to be implemented

Currently, Quang Ngai City has directed to focus on completing early the work of dredging, maintaining and repairing the drainage system, repairing manholes, sumps, and dredging Bau Ca regulating lake to increase the drainage capacity for the city. At the same time, inspect, review and dismantle encroachments, barriers, temporary bridges and culverts along the canals and Bau Giang River to clear the flow. Currently, the city has focused on completing the project to handle areas that are frequently flooded.

At the end of September 2023, at the 17th Session, the 13th Quang Ngai Provincial People's Council approved the investment policy of 1,000 billion VND to renovate the drainage system, build pumping stations and factories to prevent flooding and treat wastewater for Quang Ngai City. The implementation period is from 2024 to 2027. This project is a fundamental solution to prevent flooding for Quang Ngai City, so people are looking forward to the project being implemented.

VIÊN NGUYỄN
RELATED NEWS

Quang Ngai establishes fake news handling team

|

Quang Ngai will resolutely prevent and remove content and acts of posting, spreading, and sharing fake news and toxic news.

The 10,000 billion VND flood prevention project is "drowned" in legal procedures

|

The 10,000 billion VND anti-flooding project cannot disburse 6,800 billion VND in 2024, Ho Chi Minh City decided to transfer capital to other projects.

Current relationship and the truth about the arrest of Nhat Kim Anh

|

Since 2 days ago, the news of Nhat Kim Anh's arrest has caused a stir in public opinion. What is the singer's current life?

People aged 65 to under 75 need to contact the Ward People's Committee to complete procedures to issue health insurance cards

|

HCMC - People who are eligible but do not have a health insurance card or an expired health insurance card should contact the Ward People's Committee to complete the procedures for issuing a health insurance card.

People suffer because unfinished projects have turned into a pollution gap in the capital

|

The sewer renovation project in Long Bien (Hanoi) has been unfinished for more than ten years, people have to live next to a polluted black water hole.

The Golden Heart Social and Cultural Fund grants support to union members in flooded areas of Nghe An

|

Nghe An - The Golden Heart Social and Cultural Fund coordinated with the Provincial Federation of Labor to provide support to union members in difficult circumstances in the area.

Approving the election results of some personnel in Hanoi and Son La

|

The National Assembly Standing Committee has approved the election results of the Chairman of the Hanoi People's Council and the Chairman of the Son La Provincial People's Council for the 2021-2026 term.

17 days of sprinting before Long Thanh airport welcomes the first flight

|

Dong Nai - With only 17 days left, the Long Thanh airport project must be basically completed, ensuring standards and conditions for inauguration and welcoming the first flight.

Quang Ngai establishes fake news handling team

VIÊN NGUYỄN |

Quang Ngai will resolutely prevent and remove content and acts of posting, spreading, and sharing fake news and toxic news.

The 10,000 billion VND flood prevention project is "drowned" in legal procedures

Lê Thanh Phong |

The 10,000 billion VND anti-flooding project cannot disburse 6,800 billion VND in 2024, Ho Chi Minh City decided to transfer capital to other projects.

Đà Nẵng xây dựng bản đồ nạo vét cống rãnh, khơi thông cửa thu để chống ngập

Văn Trực |

Chiều 2.7, UBND TP Đà Nẵng đã tổ chức Hội nghị chuyên đề phổ biến, quán triệt các nội dung liên quan đến công tác phòng, chống thiên tai và tìm kiếm cứu nạn năm 2024.