Reasons why 2/5 intersections in Can Tho have not started construction

Tạ Quang |

Can Tho - Construction of 2/5 intersections in Ninh Kieu district has not started yet because it is close to Lunar New Year 2025, therefore, construction is expected to start in the first quarter of 2025.

The investment project to build, renovate and expand 5 key intersections in Ninh Kieu district was approved by Can Tho City People's Committee in November 2023.

The 5 intersections to be renovated include: intersection No. 1 (Mau Than - 3/2 - Tran Hung Dao); intersection No. 2 (Mau Than - Nguyen Van Cu - Vo Van Kiet); intersection No. 3 (Nguyen Van Linh - Nguyen Van Cu); intersection No. 4 (Nguyen Van Linh - 3/2) and intersection No. 5 (Nguyen Van Linh - 30/4). The project has a total investment of more than 1,196 billion VND from the State budget, assigned to the People's Committee of Ninh Kieu district as the investor.

Nut so 1 (Mau Than - 3/2 - Tran Hung Dao). Anh: Ta Quang
Intersection No. 1 (Mau Than - 3/2 - Tran Hung Dao) in Ninh Kieu district, Can Tho city. Photo: Ta Quang

The project has two phases, with implementation time not exceeding 4 years from the date of project approval. In which, phase 1 will expand the intersection at the same level, controlled by traffic lights, arrange independent right turns, with the following items: renovation, expansion of 5 intersections, sidewalks, trees, public lighting system, rainwater drainage system, fire protection water supply system, traffic signals... Phase 2 will consider arranging overpasses or underpasses according to traffic needs.

In 2023-2024, priority will be given to implementing the two intersections with high traffic volume, intersection No. 1 and intersection No. 4. In 2025, the next intersections will be implemented in accordance with regulations. When necessary, the project will be adjusted accordingly.

Nut so 1 (Mau Than - 3/2 - Tran Hung Dao) thuong xuyen un tac trong gio cao diem. Anh: Ta Quang
Interchange No. 1 (Mau Than - 3/2 - Tran Hung Dao) is often congested during rush hour. Photo: Ta Quang

Mr. Lu Quoc Viet - Director of the Project Management and Land Fund Development Board of Ninh Kieu District (Can Tho City) said that currently, the procedures have been completed and the bidding for the construction of 2 intersections in the inner city area has been organized. However, they are still waiting for people to continue handing over the land.

According to Mr. Lu Quoc Viet, it is impossible to urge people to hand over the land near Tet. Therefore, after Tet 2025, the unit will mobilize and request people to hand over the land to start construction. The construction start date will be postponed to the first quarter of 2025 instead of mid-December 2024.

Intersections No. 1 and No. 4 of the Project to renovate and expand 5 key intersections in Can Tho City have a land area of ​​about 6.1 hectares; about 160 households and organizations are affected (intersection No. 1 has about 112 households and 10 organizations; intersection No. 4 has about 38 households); it is expected that about 45 resettlement sites will be arranged (intersection No. 1 has about 30 sites, intersection No. 4 has about 15 sites).

Regarding resettlement locations, the planned Ninh Kieu Resettlement Area, An Binh Resettlement Area and the Resettlement Area on both sides of Nguyen Van Cu Street are expected to be approximately VND801.83 billion for the two intersections (over VND698.83 billion for intersection 1 and about VND103 billion for intersection 4).

The project's objective is to expand and build intersections to meet current and future traffic demands, reduce traffic congestion; build modern intersections, contribute to improving urban aesthetics, and develop the economy and society of Ninh Kieu district in particular and Can Tho city in general...

Tạ Quang
RELATED NEWS

Merging 4 agencies, considering dissolving 1 center in Can Tho

|

Can Tho - The City People's Committee has just sent an official dispatch to the Department of Home Affairs regarding the deployment and implementation of the plan to arrange and perfect the organizational apparatus in accordance with Resolution No. 18-NQ/TW.

BOT station in Can Tho degraded after more than 5 years of inactivity

|

Can Tho - BOT Station T2 stopped collecting tolls since the beginning of 2019 but has not been dismantled yet, is currently degraded and does not ensure traffic safety.

Iran rejects proposal for temporary ceasefire

|

Iran rejects proposal for temporary ceasefire, demands permanent end of conflict.

Case of sick pork entering the kitchen, police continue to verify whether or not there is collusion for consumption

|

Hanoi - Functional agencies are continuing to clarify whether there is collusion between businesses and Cuong Phat Company in the consumption of diseased pork.

Spontaneous landfills reoccur in Hanoi, challenging efforts to preserve the environment

|

Hanoi - Many spontaneous landfills still appear, despite the efforts of the government, local people and environmental workers.

Ambiguous confirmation of whether teachers of Song Hong Intermediate School are civil servants or laborers

|

Phu Tho - According to a report by Phu Tho Vocational College, one of the difficulties in merging Song Hong Intermediate School is the difficulty in identifying whether the 29 officials of this school are civil servants or employees.

How long will the widespread intense heat wave last

|

According to the meteorological agency, from tomorrow, April 7, hot weather will continue to expand in the North and Central regions and last for many days to come.

Factory fire in Ho Chi Minh City leaves 3 people burned

|

Ho Chi Minh City - In Vinh Tan ward, a factory fire occurred, causing 3 people to be burned and hospitalized for emergency treatment.

Merging 4 agencies, considering dissolving 1 center in Can Tho

Tạ Quang |

Can Tho - The City People's Committee has just sent an official dispatch to the Department of Home Affairs regarding the deployment and implementation of the plan to arrange and perfect the organizational apparatus in accordance with Resolution No. 18-NQ/TW.

BOT station in Can Tho degraded after more than 5 years of inactivity

Tạ Quang |

Can Tho - BOT Station T2 stopped collecting tolls since the beginning of 2019 but has not been dismantled yet, is currently degraded and does not ensure traffic safety.

Thông tin mới về cải tạo 5 nút giao hơn 1.196 tỉ đồng ở Cần Thơ

Tạ Quang |

Cần Thơ - Ngày 4.7, tại Kỳ họp thứ 16 HĐND TP Cần Thơ khóa X, ông Huỳnh Trung Trứ - Chủ tịch UBND quận Ninh Kiều đã thông tin về dự án cải tạo, mở rộng 5 nút giao trọng điểm trên địa bàn quận.