Reasons for the delay in the progress of the river bridge project in Hai Phong

Mai Dung |

Hai Phong - After 20 months of construction, the investment project to build Lai Xuan bridge and renovate and expand provincial road 352 has only reached 68% progress.

Construction of Lai Xuan bridge has reached 68% progress.

The investment project to build Lai Xuan bridge and renovate and expand provincial road 352 connecting Thuy Nguyen district of Hai Phong city and Dong Trieu town of Quang Ninh province across Da Bach river was started on February 2, 2023. The total investment of the project is nearly 1,335 billion VND from the Hai Phong city budget; Quang Ninh province pays for site clearance costs in this province.

Phoi canh du an cau Lai Xuan noi TP Hai Phong voi tinh Quang Ninh sau khi hoan thanh. Anh: BQL Du an cac cong trinh giao thong Hai Phong
Perspective of Lai Xuan bridge project connecting Hai Phong city with Quang Ninh province after completion. Photo: Hai Phong Traffic Works Project Management Board

The project is expected to improve the capacity of transport services, create an inter-regional transport connection system, meet the transport needs between industrial parks and industrial clusters, serve the travel needs of people in Thuy Nguyen district, Dong Trieu town in particular and the two localities of Hai Phong and Quang Ninh in general. At the same time, gradually complete the transport network of Hai Phong city, Quang Ninh province and the Northern key economic region, contributing to the socio-economic and cultural development of localities in the project area.

Den 17.10, du an moi dat khoang 70% khoi luong. Anh: Hoang Khoi
As of October 17, the project has only reached about 70% of its volume. Photo: Hoang Khoi

According to the report of the Hai Phong Traffic Construction Investment Project Management Board, by October 18, contractors had completed 104/130 bored piles, and were working at 12/16 abutment and pier locations; the main span was closed on September 3, 2024. The estimated completed volume is about 354/518.8 billion VND (about 68% of the contract).

Construction of renovation and expansion of provincial road 352, currently, contractors are focusing on constructing the road foundation and paving the road surface with asphalt concrete. The value of completed volume is about 192/351.4 billion VND (about 55% of the contract).

Slow due to land clearance

According to the plan, the project construction period is expected to be from February 2023 to December 2024. However, the construction is still quite slow, the progress is increasing slowly. Accordingly, on August 7, the progress of Lai Xuan bridge project reached 63%, but by October 18, the progress only increased by 5%.

Explaining this situation, Mr. Pham Van Chinh - Chief Project Supervision Consultant said that the main difficulties and problems come from site clearance.

On the bank of Thuy Nguyen district, Hai Phong city, there is currently a remaining area of ​​land recovered from Xuan Nguyen Prison (about 9,800 m2) for the construction of 3 pillars. The City People's Committee issued Document No. 1744/UBND-DC4 dated July 31, 2024 requesting the Ministry of Public Security to agree to transfer to the City People's Committee a 0.98ha land plot to implement the project.

On the bank of Dong Trieu town, Quang Ninh province (Yen Duc commune), the contractor is still stuck with the site to construct 1 pillar. The locality is resolving the problem of land allocation for resettlement of 1 household. Due to the slow progress of site clearance on the Quang Ninh side for many months, Hai Phong City People's Committee has issued Document No. 1716/UBND-XD1 requesting Quang Ninh province to direct relevant agencies and units to promptly hand over the site for the project.

"After the remaining site is handed over, the contractor will strive to complete the project within 3 months," said a representative of the Project Management Board.

Do vuong mac giai phong mat bang, du an kho ve dich dung tien do. Anh: Hoang Khoi
Due to land clearance problems, the project is unlikely to finish on schedule. Photo: Hoang Khoi
Mai Dung
RELATED NEWS

96.64% of people are satisfied with medical services in Hai Phong

|

Hai Phong - Hai Phong City Department of Health has just announced the results of measuring people's satisfaction with public health services in 2024.

Hai Phong City Labor Federation increases funding to take care of union members during Tet

|

Hai Phong - On the afternoon of October 16, the Hai Phong City Labor Federation held the 7th meeting of the Standing Committee, term XV.

Project scale of 235 billion VND to restore K15 Ben relic in Hai Phong

|

Hai Phong - It is expected that in the first quarter of 2025, the investment project to construct, restore and embellish the relic complex of K15 Wharf - No-number Wharf in Hai Phong will start construction.

Bank interest rates today 4: 2: Unexpected reversal

|

Bank interest rates today 4: 2: Deposit interest rates reverse to decrease. Summary of savings interest rates Vietcombank, VietinBank, Agribank, BIDV, VPBank...

Gia Lai Provincial Chairman directs handling of teacher's exam paper revision case

|

Gia Lai - Provincial Chairman requests functional sectors to intervene to definitively handle the case at Nguyen Van Cu Elementary School, clarify the responsibilities of violating collectives and individuals.

Designing an administrative center for 6,000 Ho Chi Minh City officials in Thu Thiem

|

Ho Chi Minh City - A large-scale administrative center serving 6,000 officials, along with a theater and central lake park, is being built in Thu Thiem New Urban Area.

Musician To Hieu is ready to confront Tan Bo in the scandal of owing hundreds of millions of VND

|

Regarding Tan Bo's denunciation related to money disputes, musician To Hieu affirmed that he is not worried and is ready to work with functional agencies.

Beauty" of the first horse mascots to appear in Hue City

|

HUE - "Beauty" of the first horse mascots appearing in the Ancient Capital creates a highlight for the Binh Ngo Tet 2026, brightening up the space along the Perfume River.

96.64% of people are satisfied with medical services in Hai Phong

Mai Dung |

Hai Phong - Hai Phong City Department of Health has just announced the results of measuring people's satisfaction with public health services in 2024.

Hai Phong City Labor Federation increases funding to take care of union members during Tet

Mai Dung |

Hai Phong - On the afternoon of October 16, the Hai Phong City Labor Federation held the 7th meeting of the Standing Committee, term XV.

Project scale of 235 billion VND to restore K15 Ben relic in Hai Phong

Mai Dung |

Hai Phong - It is expected that in the first quarter of 2025, the investment project to construct, restore and embellish the relic complex of K15 Wharf - No-number Wharf in Hai Phong will start construction.