Reasons for the National Highway 8C upgrade project's sluggish construction

TRẦN TUẤN |

Ha Tinh - The slow construction progress has caused the Ministry of Construction to urge and request the replacement of contractors with weak capacity.

Land clearance problems, lack of fill

On May 9, according to a reporter from Lao Dong Newspaper, the project "Renovation and upgrading of National Highway 8C from Thien Cam - National Highway 1" in Cam Xuyen district is still stuck with the power grid in Cam Xuyen town.

This causes difficulties for the contractor, posing a potential safety risk. At each point with electric poles, it is not possible to fill the soil, and seamlessly squeeze, but must be constructed in a "jumping worm" manner to avoid the electric poles.

Mr. Nguyen Ngoc Son - on-site technical officer of Joint Stock Company 484 present at the construction site - said that the Company's construction was very difficult due to many electric poles on both sides of the road and the clean water pipeline system.

Our company is constructing a package with a length of only 700 meters, but after nearly 2 years, the construction volume has not yet reached 50%. According to the plan, the project is expected to be completed by the end of October 2025, but the site clearance problem is unknown. I just try to work overtime and increase shifts, Mr. Son shared.

Nhung cot dien gay kho cho viec thi cong o thi tran Cam Xuyen. Anh: Tran Tuan.
The electric poles make construction in Cam Xuyen town difficult. Photo: Tran Tuan.

At the National Highway 8C Upgrade Project in Huong Son district, the construction volume is also low due to land clearance problems and lack of fill soil.

Mr. Tran Dac Tiep - Commander of Thanh Huy Group Joint Stock Company - said that Thanh Huy Company is constructing a length of more than 10km.

However, there are still problems with site clearance. There are 13 households that have not received compensation, some have received it but have been slow to dismantle the construction. The site was handed over in a sluggish manner, causing the unit to only organize disjointed construction teams.

According to a leader of Thanh Huy Group Joint Stock Company, the entire area of the National Highway 8C Upgrade Project in Huong Son currently has only one soil mine, Thang Bay, providing fill soil.

This land mine has a licensed capacity of 260,000m3/year but the actual exploitation output is only about 500 - 800m3/day, too low compared to the average demand of the contractor of 3,000m3/day.

The project will be implemented from October 2023, and must be completed by October 2025. However, Thanh Huy Group Joint Stock Company has only completed more than 25% of the construction volume, mainly filling K95 foundation, constructing sewers, drainage ditches and gathering materials.

Thi cong Nang cap Quoc lo 8C o huyen Huong Son hien khoi luong cung dat thap. Anh: Tran Tuan.
The construction of the National Highway 8C Upgrade in Huong Son District is also low in volume. Photo: Tran Tuan.

The leader of Thanh Huy Group Joint Stock Company said that the unit is very worried, focusing on accelerating the progress. However, in order to complete the bidding package according to the set time, the decisive factor must be completed the handover of the ground and meet the full amount of embankment.

Urging progress, demanding replacement of contractors

Mr. Le Ngoc Ha - Vice Chairman of Cam Xuyen District People's Committee - said that currently, at the "Renovation and Upgrade of National Highway 8C" project through Cam Xuyen district, there are still many power poles that have not been relocated.

According to Mr. Ha, because previously, when designing the project to renovate and upgrade National Highway 8C in Cam Xuyen, there was no mention of the design to relocate the power line system. During the project implementation, the relocation of new power lines was added, leading to slow site clearance.

Currently, in Cam Xuyen, the relocation of old electric poles and installation of new electric poles are being carried out, expected to be completed in more than a month.

Cong nhan thi cong o Du an Nang cap Quoc lo 8C. Anh: Tran Tuan.
Construction workers at the National Highway 8C Upgrade Project. Photo: Tran Tuan.

The project to renovate and upgrade National Highway 8C from Thien Cam - National Highway 1 (Cam Xuyen District) and from National Highway 8 to Ho Chi Minh Road (Huong Son District) was approved by the Ministry of Transport (now the Ministry of Construction) in March 2022 with a total investment of more than 1,000 billion VND.

The project implementation period is from 2022 to 2025. The project is invested by the Ha Tinh Department of Transport (now the Department of Construction).

Recently, after inspecting the site, the Ministry of Construction assessed that the project started construction in October 2023, and is scheduled to be completed in October 2025. However, the volume achieved is very low. Package 17.XL achieved a volume value of about 40%, package 18.XL achieved a volume of about more than 38%.

Therefore, the Ministry of Construction requires the transfer of volume between contractors, replacing weak contractors. At the same time, it is recommended that Ha Tinh province direct the locality to promptly hand over the site to speed up the project's construction.

TRẦN TUẤN
TIN LIÊN QUAN

Hoa Binh - Moc Chau Expressway seeks contractors to construct the 660 billion VND package

|

The Hoa Binh - Moc Chau Expressway Project (section Km19+00 - Km53+00 in Hoa Binh province) is looking for a contractor to construct the section Km50+260 - Km53+000 worth more than 660 billion VND.

The project to upgrade the road connecting National Highways 70 and 279 is being constructed slowly

|

Lao Cai - The project to upgrade the road connecting National Highway 70 with National Highway 279 is not only behind schedule and poor in quality but also often causes traffic insecurity.

Thousands of workers are tirelessly constructing a national key highway

|

Cao Bang - During major holidays, thousands of workers are still working hard at the Dong Dang - Tra Linh Expressway construction site.

Vietnam aims to reach a fair counterpart tax agreement with the US

|

Vietnam is one of the first countries to negotiate countervailing tariffs with the US. To date, the two sides have concluded 3 negotiation rounds at both the technical and ministerial levels.

Nghe An rectifies temporary suspension of receiving administrative records

|

Nghe An - Localities and units are not allowed to arbitrarily stop receiving administrative procedures during the time of reorganization of commune-level units.

Press actively participates in policy making and development

|

Member of the Party Central Committee, Deputy Prime Minister Tran Hong Ha said: The press agencies have shown flexibility, agility, the ability to analyze forecasts and explanations, and actively participate in planning and policy making. Journalism works are expressed richly and diversely in many types.

Van Hugo takes action after HIUP milk company leader arrested

|

After BTV Quang Minh, it was MC Van Hugo's turn to declare working with a lawyer after the HIUP 27 nutritional product brand was investigated.

Minister of Culture, Sports and Tourism Nguyen Van Hung: Vietnam Revolutionary Press: "Source of knowledge - Connecting trust"

|

In an interview with Van Hoa Nhan celebrating the 100th anniversary of the Vietnam Revolutionary Press Day (June 21,25 - June 21, 2025), Member of the Party Central Committee, Minister of Culture, Sports and Tourism Nguyen Van Hung highly appreciated the contribution and companionship of the press in the cause of building and defending the Fatherland over the past century.

Hoa Binh - Moc Chau Expressway seeks contractors to construct the 660 billion VND package

Tô Công |

The Hoa Binh - Moc Chau Expressway Project (section Km19+00 - Km53+00 in Hoa Binh province) is looking for a contractor to construct the section Km50+260 - Km53+000 worth more than 660 billion VND.

The project to upgrade the road connecting National Highways 70 and 279 is being constructed slowly

Nhóm PV |

Lao Cai - The project to upgrade the road connecting National Highway 70 with National Highway 279 is not only behind schedule and poor in quality but also often causes traffic insecurity.

Thousands of workers are tirelessly constructing a national key highway

Tân Văn |

Cao Bang - During major holidays, thousands of workers are still working hard at the Dong Dang - Tra Linh Expressway construction site.