Many errors in construction project appraisal in Khanh Hoa

Hữu Long |

Through inspection, the Inspectorate of the Department of Construction of Khanh Hoa province discovered that 158 ​​economic and technical reports on construction investment appraised by the Economic Infrastructure Department of Khanh Vinh district from March 2021 to the end of December 2023 did not evaluate the content on the project's planning compliance.

Looking back at old projects, many shortcomings were discovered.

There is a situation where the appraisal dossier, after the investment policy is issued, the project preparation and appraisal is organized and implemented in just 1 day, leading to many shortcomings in the appraisal dossier. That is the project to reinforce the slope of the cement concrete road in Hop Thuy, Dong village, Song Cau commune, Khanh Vinh district.

After Khanh Vinh district had an investment policy (December 28, 2023), in just 1 day (December 29), the investor, the People's Committee of Song Cau commune, completed many documents and work to appoint a survey consultant; the survey consultant unit carried out the survey work and completed the survey and project documents; the commune submitted a request for appraisal of the technical economic report documents.

The Department of Infrastructure Economics also completed the appraisal of the documents on December 29, 2023. After this Department had the appraisal results and on the same day, Song Cau commune and the Department of Infrastructure Economics submitted a report to Khanh Vinh district to advise them to issue a decision approving the construction technical economic report.

The Department of Construction Inspectorate later discovered that the appraisal report form for this project was not in accordance with regulations; there was no content assessing the capacity of the appraisal consulting unit; there was no confirmation from the competent authority on the appraised economic and technical report...

Also in January 2025, the Inspectorate of the Department of Construction of Khanh Hoa province announced the results of the inspection on the acceptance and handover of 13 construction works. These projects are invested by the Cam Ranh City Construction Project Management Board (Cam Ranh City PMU).

Cam Ranh City Project Management Board issued a document announcing the commencement of construction of 3 projects but did not send it to Cam Ranh City People's Committee as required. The Department of Construction Inspectorate also discovered that the contractor's acceptance minutes were signed without a chief supervisor for the 3 projects, which is not in accordance with regulations. This responsibility belongs to Thuan Hung Construction and Consulting Joint Stock Company; D68 Construction - Real Estate Company Limited and Cam Ranh City Project Management Board.

The composition of the construction contractor signing the acceptance minutes without a commander for 5 projects is not in accordance with regulations. This responsibility belongs to 778 Investment and Construction Company Limited; T.A.L Construction Consulting Joint Stock Company; Dong Do Company Limited; Cam Ranh Urban Joint Stock Company and Cam Ranh City Project Management Board...

Co quan thanh tra chi ra mot so du an thieu sot tai xa Khanh Trung va nhieu xa tren dia ban huyen Khanh Vinh. Anh: Huu Long
The inspection agency pointed out a number of flawed projects in Khanh Trung commune and many communes in Khanh Vinh district. Photo: Huu Long

Investors only learn from experience

Mr. Tran Minh Thuan - Head of the Economic Infrastructure Department of Khanh Vinh district confirmed that after the inspection conclusion, the unit held a meeting to review the experience of the relevant individuals. Mr. Thuan said that the department's file appraisal was wrong but did not affect the settlement and completion of the projects. The Economic Infrastructure Department appraised the files but did not intervene in the bidding of the projects, which responsibility belonged to the communes - the investors.

Meanwhile, for project stt01 - Dike system of Project 773, Cam Lap commune, Cam Ranh city, the investor issued a notice of commencement of construction but did not send it to Cam Ranh City People's Committee as prescribed. However, according to the inspection agency, this project was handed over in November 2021.

The administrative penalty for the above-mentioned violations has expired and there are no remedial measures for these violations. The Department of Construction Inspectorate decided not to impose administrative penalties on the contractors and the Cam Ranh Project Management Board, but only requested them to rectify and learn from their experiences.

Hữu Long
RELATED NEWS

Additional 6.4 hectares of land for golf course construction in Long Bien

|

Recently, the Hanoi People's Committee has allocated more than 64,000 square meters of land to invest in a golf course and service project in Long Bien district (Hanoi).

Hanoi adjusts traffic at Lang Ha - Giang Vo intersection from September 11th

|

Hanoi adjusts traffic at the Lang Ha - Giang Vo - La Thanh intersection from 11:00 PM on September 11th to serve the construction of the overpass under the Ring Road 1 project.

Forecast of thunderstorms and temperature drop from tomorrow, September 10th due to cold air

|

Forecast due to the impact of cold air, the North and North Central regions will have rain; the lowest temperature is commonly 21-24 degrees C, high mountainous areas have places below 19 degrees C.

Close-up of US airstrike sinking 5 Iranian oil tankers

|

US Secretary of State Marco Rubio on September 8 (local time) announced that Washington will continue to target Iranian oil tankers in retaliatory strikes.

Frozen chicken imported massively into Vietnam, priced half as cheap as domestic goods

|

Imported chicken meat to Vietnam, including chicken thighs, frozen chicken wings and other by-products such as chicken feet, chicken hearts... with an average price of only 26,500 VND/kg.

Ministry of Health tightens private clinics: Drawing diseases, extorting money may result in revocation of licenses

|

The Ministry of Health requests localities to conduct surprise inspections of private clinics, strictly handle acts of drawing diseases, extorting money, and even revoke licenses.

Chi tiết 15 tuyến đường sắt đô thị Hà Nội dự kiến xây dựng

KHÁNH AN |

Hà Nội - Hiện tại, thành phố đang có 2 tuyến đường sắt đô thị và đang phấn đấu đến năm 2045 có 15 tuyến với tổng chiều dài 616,9km.

Additional 6.4 hectares of land for golf course construction in Long Bien

Khánh An |

Recently, the Hanoi People's Committee has allocated more than 64,000 square meters of land to invest in a golf course and service project in Long Bien district (Hanoi).

Sơ đồ vị trí 5 cầu vượt nhẹ tại 4 quận Hà Nội được đề xuất xây dựng

Nhóm PV |

Sở Giao thông Vận tải vừa đề xuất UBND TP Hà Nội xây dựng mới 5 cầu vượt nhẹ bằng thép tại một số nút giao có lưu lượng phương tiện lớn.