Workers who do not take a day off on the trillion-dong expressway in Tuyen Quang

Việt Bắc |

Tuyen Quang - Ha Giang Expressway construction site during the April 30 and 1.5 holidays is still bustling with the sound of engines, racing with progress.

Recorded on April 30, in the bustling atmosphere of the whole country celebrating the 50th anniversary of the Liberation of the South and National Reunification Day, at the Tuyen Quang - Ha Giang Expressway construction site, people and vehicles are still working tirelessly.

Everyone is racing to complete the project as well as contribute to creating a vibrant atmosphere, competing to celebrate the grand ceremony of river unification.

In package No. 19, the construction of the road section from Km0+00 - Km3+875.98 and from Km10+256 - Km23+00 by Truong Son Construction Company and Thanh Hung Construction and Investment Company Limited, nearly 100% of human resources and machinery were mobilized at the construction site.

Mr. Nguyen Van Toan, a locomotive driver, said: "Everyone wants to visit their home during the holidays, but because of the progress of the project, the workers still stick to the construction site, working day and night with great determination to complete the project on time".

Currently, the progress of package 19 has reached 38.71% of the contract value. Contractors are organizing 17 construction teams, mobilizing136 vehicles and equipment along the route. Many items such as underpasses for people have been completed 23/25 times, large box culverts have been completed 19/21 times, reaching over 90%.

"Although it is the holiday season, we still mobilize all human resources and machinery for construction. The day off work regime is guaranteed, so workers are excited and feel secure at work," said Mr. Nguyen Ngoc Dinh - Director of Thanh Hung Investment and Construction Company Limited.

Hang tram cong nhan, nguoi lao dong van tang toc thi cong tren cong truong cao toc Tuyen Quang - Ha Giang dip nghi le. Anh: Viet Bac.
Hundreds of workers and laborers are still speeding up construction at the Tuyen Quang - Ha Giang expressway construction site during the holiday. Photo: Viet Bac.

According to the report of the Tuyen Quang Province Traffic Construction Investment Project Management Board (project investor), the progress of the packages is currently from 24 to 47%, basically meeting the required progress.

During the April 30 and May 1 holidays this year, despite the long holidays, contractors have organized people and vehicles along with "3 shifts, 4 teams" construction teams with an urgent and bustling atmosphere to join in the atmosphere of the national unity festival.

The entire route has been handed over the site to 99.57%, currently there is only 0.3km that is being closely coordinated by investors and local authorities at all levels to resolve existing problems, difficulties and problems.

Currently, the People's Committee of Tuyen Quang province has approved the policy of exploiting fill soil at 7 locations and allowed to increase the exploitation capacity of 6 quarries to solve the problem of a shortage of 1.97 million m3 of soil and 0.35 million m3 of rock compared to demand.

Some recorded images.

Cao toc Tuyen Quang - Ha Giang doan nut giao voi QL.37. Anh: Viet Bac.
Tuyen Quang - Ha Giang Expressway at the intersection with QL.27. Photo: Viet Bac.
Cong nhan tren cong truong cao toc Tuyen Quang - Ha Giang thi cong xuyen le, dam bao tien do du an. Anh: Viet Bac.
Workers at the Tuyen Quang - Ha Giang expressway construction site are working through the ceremony, ensuring the project's progress. Photo: Viet Bac.
Doc tuyen cao toc ron vang tieng may du trong nhung ngay nghi le. Anh: Viet Bac.
The expressway is bustling with the sound of machinery even during holidays. Photo: Viet Bac.
Việt Bắc
RELATED NEWS

Deadline for handing over the Tuyen Quang - Ha Giang expressway site

|

The Chairman of Tuyen Quang Provincial People's Committee requested localities to complete the handover of the entire Tuyen Quang - Ha Giang expressway site before April 5.

Construction across holidays on key traffic projects

|

To speed up progress, on New Year's Day, January 1, 2025, workers on many key traffic projects in the North Central provinces will still focus on construction.

A series of notable actions related to Shark Binh

|

Some videos on Shark Binh's fanpage suddenly disappeared, while the NextTech ecosystem company confirmed it had nothing to do with AntEx.

Son La has a new Provincial Party Secretary

|

Son La - Mr. Hoang Van Nghiem has just been transferred to hold the position of Secretary of the Son La Provincial Party Committee.

Live volleyball VTV Binh Dien Long An 2-1 Vietinbank: Set 3

|

Live match between VTV Binh Dien Long An vs Vietinbank in the semi-finals of the 2025 national volleyball tournament, taking place at 5:30 p.m. today (October 12).

44 billion VND stadium project in Phu Tho completed early

|

Phu Tho - After more than 9 months of construction, the project to renovate and upgrade the Phu Tho town stadium (now in Phu Tho ward) is ready to be completed.

Proposal to increase retirement age, shift from minimum wage to salary enough to raise 2 children

|

Prof. Dr. Nguyen Thien Nhan said that Vietnam needs to continue raising the retirement age to ensure a labor source and avoid waste.

Construction through ceremony on two billion-dong expressways in the border area of Lang Son

Khánh Linh |

Lang Son - Throughout the holiday, workers and engineers are still working hard on the Huu Nghi - Chi Lang and Dong Dang - Tra Linh expressways.

Deadline for handing over the Tuyen Quang - Ha Giang expressway site

Việt Bắc |

The Chairman of Tuyen Quang Provincial People's Committee requested localities to complete the handover of the entire Tuyen Quang - Ha Giang expressway site before April 5.

Construction across holidays on key traffic projects

Nhóm PV Bắc Trung bộ |

To speed up progress, on New Year's Day, January 1, 2025, workers on many key traffic projects in the North Central provinces will still focus on construction.