Quang Ninh's largest intersection 760 billion VND countdown to finish

Đoàn Hưng |

Quang Ninh - The 760 billion VND Dam Nha Mac Intersection Project is 80% complete, determined to reach the finish line by the end of 2024, opening the way for economic development in the West of Quang Ninh.

The Dam Nha Mac Interchange Project, at Km20+50 of Hai Phong - Mong Cai Expressway, is a key traffic project of Quang Ninh with a total investment of 760.68 billion VND, approved by the Provincial People's Committee on October 31, 2019.

This is the largest traffic intersection in the province, designed in the shape of an asterisk with 9 branches, total length of more than 10km, on an area of ​​83.4ha.

Ham  chui cao toc. Anh: Doan Hung
Highway underpass. Photo: Doan Hung

The project started in 2020, but due to many difficulties related to forest land conversion, scarcity of filling materials, and elevation design adjustments, the progress had to be extended 4 times.

According to the report from the Project Management Board for Investment and Construction of Civil and Industrial Works (project investor), up to now, the project has completed about 80% of the total volume.

Some major items such as the underpass across the highway have been completed. Large box culverts (2x4x6m), cross-road culverts are 100% completed. The asphalt concrete pavement in the highway expansion area is completely completed, the asphalt pavement in the branch area is over 4.5km/10km.

dsdfdsf
All directional signs have been installed. Photo: Doan Hung

Guardrails, paint, highway lighting and all directional signs have been installed.

Currently, contractors are focusing on reinforcing the slope of the branch line, digging molds, filling with K98 soil, spreading crushed stone and asphalt concrete on the subsidence-free sections.

According to the representative of the joint consulting and supervision contractor Thang Long Construction Consulting Company and Viet Long Technology Development Company, the construction units have mobilized over 50 equipment units and more than 100 workers divided into 3 shifts, determined to complete the project before December 31, 2024.

Dam Nha Mac Interchange is not only a large-scale traffic project but also has important significance in connecting Hai Phong - Mong Cai expressway with key economic areas of the province.

Upon completion, this interchange will expand the connectivity of Quang Yen coastal economic zone. Support the development of Dam Nha Mac industrial park and neighboring areas. Attract investment and promote economic development in the West of Quang Ninh province.

With the determination of contractors and investors, the project is expected to be completed on schedule by the end of 2024, creating a new development momentum for Quang Ninh.

Đoàn Hưng
TIN LIÊN QUAN

Quang Ninh elects 1,452 village chiefs on December 15, 2024

|

Quang Ninh will simultaneously vote to elect village, ward, and commune chiefs for the 2025-2027 term on December 15, 2024. Time will start from 5:00 a.m. to 7:00 p.m. on the same day.

EVNGENCO3 supports Quang Ninh people to overcome the consequences of storm No. 3

|

Quang Ninh - Power Generation Corporation 3 (EVNGENCO3) has had many activities to support and raise funds to help localities and people overcome the consequences of storm No. 3.

New roads bring Chinese tourists to Quang Ninh

|

Quang Ninh - In an effort to promote Vietnam - China tourism, new border and sea routes are bringing many opportunities to Quang Ninh.

Update on the closing price of gold on November 23: Pessimistic sentiment disappears

|

Update on the closing price of gold on November 23: Most experts believe that gold prices will increase in the short term.

School brawl, 2 teachers must review

|

Nghe An - A fight between two teachers at Van Phong Secondary School (Dien Chau) caused a stir in public opinion.

Quang Ninh's largest intersection 760 billion VND countdown to finish

|

Quang Ninh - The 760 billion VND Dam Nha Mac Intersection Project is 80% complete, determined to reach the finish line by the end of 2024, opening the way for economic development in the West of Quang Ninh.

The West is "sitting on fire" because of Russia's new hypersonic missile

|

The West is "sitting on fire" because Russia has just launched its latest Oreshnik hypersonic missile into Ukraine.

Miss Thanh Thuy reveals the story about coffee and the reason for crying

|

In the Saturday Afternoon Coffee program, Miss International 2024 Huynh Thi Thanh Thuy revealed the gift she gave to her international friends and the reason for crying.

Quang Ninh elects 1,452 village chiefs on December 15, 2024

Nguyễn Hùng |

Quang Ninh will simultaneously vote to elect village, ward, and commune chiefs for the 2025-2027 term on December 15, 2024. Time will start from 5:00 a.m. to 7:00 p.m. on the same day.

EVNGENCO3 supports Quang Ninh people to overcome the consequences of storm No. 3

Lan Anh |

Quang Ninh - Power Generation Corporation 3 (EVNGENCO3) has had many activities to support and raise funds to help localities and people overcome the consequences of storm No. 3.

New roads bring Chinese tourists to Quang Ninh

Đoàn Hưng |

Quang Ninh - In an effort to promote Vietnam - China tourism, new border and sea routes are bringing many opportunities to Quang Ninh.