In January 2025, the People's Committee of Ninh Binh province focused on leading and directing the relevant units to closely follow the project's implementation progress, focusing and drastically implementing the assigned tasks. Therefore, the appraisal and approval of construction design and implementation after the basic design for investment in construction of Ninh Binh - Hai Phong Expressway route, the section through Ninh Binh province has ensured timely completion. As prescribed.
Mr. Pham Quoc Chinh - Director of the Ninh Binh Provincial Traffic Construction Investment Project Management Board (investor) said that as of February 7, the investor had handed over all site clearance markers to localities with projects passing through for declaration and counting according to regulations.
Up to now, the districts have declared and tallyed 1,353/2.501 organizations, individuals and households affected. In particular, Yen Khanh district is 361/1,438 organizations, individuals and households affected and has paid 157,825 billion dong of compensation and support.
In addition, the resettlement plan has also been built including 10 resettlement areas with 10 sub-projects and has completed the appraisal and approval of environmental impact assessment reports. At the same time, it has reviewed and preliminarily determined the plan to return the affected technical infrastructure works.
The allocation of capital for the project, on 7.2, the budget of Ninh Binh province, has arranged 28 billion dong to carry out the task of preparing investment, making feasibility study reports and applying capital from the land development fund. Ninh Binh province is VND 49 billion to carry out the site clearance. Public investment plan in 2025 was delivered to VND 25 billion, and the central budget capital, Ninh Binh People's Committee gave in detail the public investment plan in 2025 was VND 3,000 billion.
Regarding the material mine applied to the project, Mr. Chinh said that the Ministry of Natural Resources and Environment has submitted to the Prime Minister for approval to adjust part of the area of Dap Thien Lake and Vai Mountain out of the area where mineral activities are prohibited in Ninh Binh province.
"Currently, the Department of Planning and Investment of Ninh Binh province has approved the plan to select additional contractors for the project, including insurance packages, construction packages, construction supervision consultants and some other packages. We are currently issuing bidding documents for bidding packages to select contractors according to regulations. The project is expected to start construction at the end of March or early April" - Mr. Chinh said.
The investment project to build the Ninh Binh - Hai Phong expressway, the section through Ninh Binh province, has a route length of 25.3km; the starting point is at Mai Son intersection connecting with the North-South expressway in the East (in Mai Son commune, Yen Mo district), the end point is at the Day River overpass connecting Ninh Binh and Nam Dinh provinces (in Khanh Cuong commune, Yen Khanh district).
The project has a scale of 4 complete lanes, a design speed of 120km/h, a roadbed width of nearly 25m, and a road surface width of 15m. The entire route will have 12 bridges, including 3 overpasses and 3 interconnecting intersections. The total investment is 6,865 billion VND, including the central budget and the Ninh Binh provincial budget. The project is expected to be completed in 2029.