Approaching completion deadline, 3 transportation projects worth more than 2 trillion VND are still facing site clearance issues

Tạ Quang |

Can Tho - There are only about 6 months left to reach the target according to the plan, but 3 key transport projects have not yet been able to open the route due to site clearance obstacles.

Mr. Phan Minh Tri - Deputy Director of the Project Management Board for Investment in Construction of Transport and Agricultural Works of Can Tho City (Project Management Board) said that the Project to build and upgrade and expand Provincial Road 917 has a total adjusted investment of more than 1,240 billion VND, from the Central budget, local budget and mobilizing other capital sources. Implementation time from 2021 - 2026.

In terms of scale, the starting point of the project is at Km0+000 intersecting with National Highway 91 in Phuoc Thoi ward; the ending point is at Km11+450 intersecting with Nguyen Van Cu road in Phong Dien commune. The road is more than 11km long.

To date, the site handover work on the entire route has handed over 10,456/11.45Km (91.32%), equivalent to 545 cases. The remaining length that has not been handed over is 0.994/11.45Km, equivalent to 34 cases.

Cận hạn hoàn thành, 3 dự án giao thông vẫn vướng mặt bằng. Ảnh: Tạ Quang
Close to completion deadline, 3 transportation projects are still facing site clearance issues. Photo: Ta Quang

At the Provincial Road 918 project (construction and upgrading phase 1 from Lo Buc bridge to the end of the route intersecting with Provincial Road 923) with a total investment of more than 324 billion VND, nearly 99% of site handover has been completed. The total length of the route is about 3.13km. Implementation time from 2020 - 2026.

Regarding site clearance, 3.088/3.13km (reaching 98.65%) have been handed over on the entire route, corresponding to 386 cases. Currently, 0.042/3.13km have not been handed over, corresponding to 2 cases.

Dự án đường tỉnh 918 vướng mắc về mặt bằng, thiết bị máy móc để không. Ảnh: Tạ Quang
Provincial road 918 project has problems with land, equipment and machinery left empty. Photo: Ta Quang
Công nhân thi công lác đác. Ảnh: Tạ Quang
Scattered construction workers. Photo: Ta Quang

For the Provincial Road 918 project (phase 2) with a total investment of nearly 878 billion VND, the implementation time is from 2021 - 2026, with a route length of about 6km.

Regarding the handover of construction site, on the entire route, 5.59/6.27km (reaching 89.2%) has been handed over, corresponding to 270 cases. The remaining length that has not been handed over is 0.68/6.27km, corresponding to 24 cases.

Tạ Quang
RELATED NEWS

Can Tho leaders inspect the progress of Dai Ngai bridge project

|

Can Tho - City leaders requested localities to accelerate inventory and complete compensation and support plans for affected households.

Famous Australian candy found to contain foreign objects, Ministry of Health immediately intervenes

|

After Australia urgently recalled a number of Allen's iNSiDE OUTS candies due to the discovery of plastic foreign objects, the Ministry of Health requested a review and suspension of business of this product.

Stock market liquidity unexpectedly drops sharply

|

The stock market still maintained green color but liquidity was quite low with a trading value of less than 14,000 billion VND in the trading session.

Overview of the 692 billion VND road connecting 2 expressways in Phu Tho

|

Phu Tho - The 2.7km longer route connecting Noi Bai - Lao Cai expressway with Tuyen Quang - Phu Tho expressway is in the process of being completed.

Official exam questions and answers for Literature subject of the 10th grade exam in Ho Chi Minh City

|

On the afternoon of June 5, the Ho Chi Minh City Department of Education and Training (GDĐT) announced the official exam questions and answers for Literature in the 10th grade entrance exam for the 2026-2027 school year.

Ministry of Education appoints many directors and principals of directly affiliated universities and colleges

|

The Ministry of Education and Training has completed nearly 95% of the plan to consolidate heads at affiliated educational institutions, with 51/54 units completing the arrangement of leadership personnel.

Can Tho leaders inspect the progress of Dai Ngai bridge project

Tạ Quang |

Can Tho - City leaders requested localities to accelerate inventory and complete compensation and support plans for affected households.

Công an Cần Thơ kêu gọi đối tượng liên quan vụ án giết người ra đầu thú

TẠ QUANG |

Cần Thơ - Công an TP phát thư kêu gọi đối tượng Hà Văn Có liên quan vụ án “Giết người”, sớm ra đầu thú để được hưởng sự khoan hồng của pháp luật.

Từ Cần Thơ ra Hải Phòng bắt đối tượng trộm hơn 1,5 tỉ đồng trong biệt thự

TẠ QUANG |

Cần Thơ - Đối tượng Trần Văn Sơn (Hải Phòng) đã đột nhập biệt thự tại phường Sóc Trăng (Cần Thơ) trộm nhiều vàng nữ trang, trang sức kim cương và tiền mặt.