Mr. Phan Minh Tri - Deputy Director of the Project Management Board for Investment in Construction of Transport and Agricultural Works of Can Tho City (Project Management Board) said that the Project to build and upgrade and expand Provincial Road 917 has a total adjusted investment of more than 1,240 billion VND, from the Central budget, local budget and mobilizing other capital sources. Implementation time from 2021 - 2026.
In terms of scale, the starting point of the project is at Km0+000 intersecting with National Highway 91 in Phuoc Thoi ward; the ending point is at Km11+450 intersecting with Nguyen Van Cu road in Phong Dien commune. The road is more than 11km long.
To date, the site handover work on the entire route has handed over 10,456/11.45Km (91.32%), equivalent to 545 cases. The remaining length that has not been handed over is 0.994/11.45Km, equivalent to 34 cases.

At the Provincial Road 918 project (construction and upgrading phase 1 from Lo Buc bridge to the end of the route intersecting with Provincial Road 923) with a total investment of more than 324 billion VND, nearly 99% of site handover has been completed. The total length of the route is about 3.13km. Implementation time from 2020 - 2026.
Regarding site clearance, 3.088/3.13km (reaching 98.65%) have been handed over on the entire route, corresponding to 386 cases. Currently, 0.042/3.13km have not been handed over, corresponding to 2 cases.



For the Provincial Road 918 project (phase 2) with a total investment of nearly 878 billion VND, the implementation time is from 2021 - 2026, with a route length of about 6km.
Regarding the handover of construction site, on the entire route, 5.59/6.27km (reaching 89.2%) has been handed over, corresponding to 270 cases. The remaining length that has not been handed over is 0.68/6.27km, corresponding to 24 cases.