On December 9, the monitoring delegation of the Standing Committee of the City Party Committee led by Member of the Standing Committee of the City Party Committee, Vice Chairman of the Hanoi People's Committee Nguyen Xuan Luu worked with Lang Ward on 8 urgent key topics at the end of 2025.
The ward has completed the 90-day and night campaign to clean up the land database early. Decentralization and delegation of authority associated with administrative procedure reform and digital transformation are implemented synchronously and on schedule. From July 1 to November 30, 2025, the ward received and processed 9,418 records on the system and ranked 20/126 in the whole city.
The most urgent issue that the monitoring team is concerned about in Lang Ward is the progress of site clearance (GPMB) for Ring Road 1.
The total land area in Lang Ward within the GPMB boundary of the Ring Road 1 project is about 30 thousand m2 of land. The total number of land acquisition options along the entire route is 597 options. The number of plans for the site handover is 240. The number of plans for site handover is 357. There are 57 options that have not yet been decided to be revoked and decided to be enforced.
To ensure the site clearance progress according to the direction of the City Party Committee must be completed before December 15, Lang Ward proposed that the City People's Committee allow the Ward People's Committee to carry out the shortened process, issue a Land Acquisition Decision, and a Enforcement Decision at the same time. From December 10 to 15, 2025, the People's Committee of the ward will enforce all 357 households that have not yet handed over the site.
According to regulations, enforcement will only be carried out until 10:00 p.m., the ward recommends that the City allow enforcement overnight to complete a large amount of work.
The ward also recommended that the Department of Construction soon issue a Decision on selling the house so that the Ward People's Committee can take steps according to regulations, ensuring the project's progress. For cases of housing difficulties but not eligible for resettlement, the proposal to buy social housing must not go through document approval.
Concluding this content, Vice Chairman of the City People's Committee Nguyen Xuan Luu requested the Hanoi Civil Works Construction Investment Project Management Board and the investor of the Ring Road 1 project to focus on working day and night with the locality to complete this important political task.
Mr. Luu requested the Department of Construction to promptly issue decisions to sell houses to serve the site clearance work, it is impossible to enforce without arranging houses for people.
The volume of site clearance work in Lang ward is very large, the countdown time is only 6 days, requiring all professional departments and wards to consider this as a common task, working together to complete the work in accordance with the direction of the City Party Secretary.