Tan Son Nhat denies rumors about the time of operation of terminal T3

Anh Tú |

HCMC - On March 10, Tan Son Nhat International Airport denied rumors of spreading the T3 terminal exploited since May 5, 2025, affirming that this is not official information.

In recent days, social networks have spread information that from May 5, terminal T3 will take over procedures for domestic flights of Vietnam Airlines and Vietjet Air, while the old terminal T1 (domestic terminal) will complete procedures for domestic flights operated by Bamboo Airways, Pacific Airlines, Vietravel Airlines and Vasco.

However, the representative of Tan Son Nhat International Airport affirmed that this is not information provided by the Port, passengers need to be careful when reading this information. Currently, the units have not yet officially announced the exploitation plan at terminal T3 as well as the existing terminal after terminal T3 is put into use.

According to Vietnam Airports Corporation (ACV), the investor, the goal of completing and inaugurating Terminal T3 is set for the April 30, 2025 holiday. Currently, items such as completed architecture, roof steel structure and aircraft parking lot have reached a high construction volume.

The T3 terminal project started construction in December 2022 with a total investment of VND 10,990 billion. The project consists of four main items: passenger terminal, high-rise parking lot combined with non-airspace services, overpass system in front of the terminal and aircraft parking lot. When completed, terminal T3 will have a capacity of more than 20 million passengers/year, serving 7,000 passengers during peak hours, contributing to reducing the load on terminal T1.

Currently, airline service businesses at the airport are also actively preparing passenger service areas. Relevant units are speeding up the progress, ensuring the station is put into operation at the expected time.

Anh Tú
RELATED NEWS

Shortening the time to complete the Long Thanh airport passenger terminal

|

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.

Prime Minister inspects Tan Son Nhat Terminal T3 project for the third time

|

HCMC - On the afternoon of February 1 (the 4th day of Tet), Prime Minister Pham Minh Chinh inspected and encouraged officials and workers who are constructing Terminal T3 at Tan Son Nhat Airport.

Terminal T3 is about to be completed, reducing the load at Tan Son Nhat airport

|

HCMC - The T3 terminal project at Tan Son Nhat airport has reached about 83% of the total volume, expected to be completed on April 30, 2025, 2 months earlier than the original plan.

Reasons why teachers do not enjoy the regime of teaching disabled people to integrate in Quang Tri

|

Quang Tri - In some communes, the regime for teachers directly participating in teaching disabled people to integrate has not been paid according to regulations.

U23 Vietnam vs U23 UAE Preview in the quarter-finals of the 2026 AFC U23 Championship

|

Football prediction for the match between U23 Vietnam vs U23 UAE in the quarter-finals of the 2026 AFC U23 Championship taking place at 10:30 PM tonight (January 16).

Parents' representative board accused of overcharging, Gia Lai Chairman directs handling

|

Gia Lai - Before the reflection that the Parents' Representative Board was accused of overcharging, the Provincial Chairman directed Quy Nhon Nam ward to investigate, verify, and handle the case.

Livestream selling flowers helps farmers in Cho Lach proactively consume Tet crops

|

Vinh Long - Livestream selling flowers in Cho Lach commune helps many farmers adapt to the weather, reduce output pressure, and open up Tet flower consumption markets.

Intersection with expressway becomes spontaneous rest stop in Quang Tri causing traffic unsafety

|

Quang Tri - Hundreds of trucks and containers leave the highway to stop and park at the intersection of National Highway 9, forming a chain of spontaneous "stops and rest stops", causing traffic unsafety.

Shortening the time to complete the Long Thanh airport passenger terminal

PHẠM ĐÔNG |

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.

Prime Minister inspects Tan Son Nhat Terminal T3 project for the third time

MINH QUÂN |

HCMC - On the afternoon of February 1 (the 4th day of Tet), Prime Minister Pham Minh Chinh inspected and encouraged officials and workers who are constructing Terminal T3 at Tan Son Nhat Airport.

Terminal T3 is about to be completed, reducing the load at Tan Son Nhat airport

MINH QUÂN |

HCMC - The T3 terminal project at Tan Son Nhat airport has reached about 83% of the total volume, expected to be completed on April 30, 2025, 2 months earlier than the original plan.