Tan Son Nhat denies rumors about the time of operation of terminal T3

Anh Tú |

HCMC - On March 10, Tan Son Nhat International Airport denied rumors of spreading the T3 terminal exploited since May 5, 2025, affirming that this is not official information.

In recent days, social networks have spread information that from May 5, terminal T3 will take over procedures for domestic flights of Vietnam Airlines and Vietjet Air, while the old terminal T1 (domestic terminal) will complete procedures for domestic flights operated by Bamboo Airways, Pacific Airlines, Vietravel Airlines and Vasco.

However, the representative of Tan Son Nhat International Airport affirmed that this is not information provided by the Port, passengers need to be careful when reading this information. Currently, the units have not yet officially announced the exploitation plan at terminal T3 as well as the existing terminal after terminal T3 is put into use.

According to Vietnam Airports Corporation (ACV), the investor, the goal of completing and inaugurating Terminal T3 is set for the April 30, 2025 holiday. Currently, items such as completed architecture, roof steel structure and aircraft parking lot have reached a high construction volume.

The T3 terminal project started construction in December 2022 with a total investment of VND 10,990 billion. The project consists of four main items: passenger terminal, high-rise parking lot combined with non-airspace services, overpass system in front of the terminal and aircraft parking lot. When completed, terminal T3 will have a capacity of more than 20 million passengers/year, serving 7,000 passengers during peak hours, contributing to reducing the load on terminal T1.

Currently, airline service businesses at the airport are also actively preparing passenger service areas. Relevant units are speeding up the progress, ensuring the station is put into operation at the expected time.

Anh Tú
RELATED NEWS

Shortening the time to complete the Long Thanh airport passenger terminal

|

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.

Prime Minister inspects Tan Son Nhat Terminal T3 project for the third time

|

HCMC - On the afternoon of February 1 (the 4th day of Tet), Prime Minister Pham Minh Chinh inspected and encouraged officials and workers who are constructing Terminal T3 at Tan Son Nhat Airport.

Terminal T3 is about to be completed, reducing the load at Tan Son Nhat airport

|

HCMC - The T3 terminal project at Tan Son Nhat airport has reached about 83% of the total volume, expected to be completed on April 30, 2025, 2 months earlier than the original plan.

Forecast of thunderstorms from tonight, cooling from tomorrow due to cold air

|

Forecast due to the impact of cold air, from the evening and night of September 9, the Northern region will have thunderstorms; the weather will turn cool from September 10.

More grave ditches discovered in Le Thi Rieng Park, 4 sets of martyrs' remains collected

|

Ho Chi Minh City - Functional forces discovered another grave ditch in area A, Le Thi Rieng Park, in the process of expanding the search and repatriation of martyrs' remains.

Representatives of kindergartens in Khanh Hoa speak out about rudimentary meals for children

|

Khanh Hoa - Representatives of a private kindergarten have sent a petition to the police, requesting clarification of the sharing of images of meals without verification.

Discovery of businesses using employees' own social insurance contributions to raise capital

|

Lam Dong - The Department of Home Affairs determined that many businesses are slow and evade social insurance contributions due to lack of capital, even using money from employees' own social insurance contributions to rotate capital.

Shortening the time to complete the Long Thanh airport passenger terminal

PHẠM ĐÔNG |

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.

Prime Minister inspects Tan Son Nhat Terminal T3 project for the third time

MINH QUÂN |

HCMC - On the afternoon of February 1 (the 4th day of Tet), Prime Minister Pham Minh Chinh inspected and encouraged officials and workers who are constructing Terminal T3 at Tan Son Nhat Airport.

Terminal T3 is about to be completed, reducing the load at Tan Son Nhat airport

MINH QUÂN |

HCMC - The T3 terminal project at Tan Son Nhat airport has reached about 83% of the total volume, expected to be completed on April 30, 2025, 2 months earlier than the original plan.