Tan Son Nhat denies rumors about the time of operation of terminal T3

Anh Tú |

HCMC - On March 10, Tan Son Nhat International Airport denied rumors of spreading the T3 terminal exploited since May 5, 2025, affirming that this is not official information.

In recent days, social networks have spread information that from May 5, terminal T3 will take over procedures for domestic flights of Vietnam Airlines and Vietjet Air, while the old terminal T1 (domestic terminal) will complete procedures for domestic flights operated by Bamboo Airways, Pacific Airlines, Vietravel Airlines and Vasco.

However, the representative of Tan Son Nhat International Airport affirmed that this is not information provided by the Port, passengers need to be careful when reading this information. Currently, the units have not yet officially announced the exploitation plan at terminal T3 as well as the existing terminal after terminal T3 is put into use.

According to Vietnam Airports Corporation (ACV), the investor, the goal of completing and inaugurating Terminal T3 is set for the April 30, 2025 holiday. Currently, items such as completed architecture, roof steel structure and aircraft parking lot have reached a high construction volume.

The T3 terminal project started construction in December 2022 with a total investment of VND 10,990 billion. The project consists of four main items: passenger terminal, high-rise parking lot combined with non-airspace services, overpass system in front of the terminal and aircraft parking lot. When completed, terminal T3 will have a capacity of more than 20 million passengers/year, serving 7,000 passengers during peak hours, contributing to reducing the load on terminal T1.

Currently, airline service businesses at the airport are also actively preparing passenger service areas. Relevant units are speeding up the progress, ensuring the station is put into operation at the expected time.

Anh Tú
RELATED NEWS

Shortening the time to complete the Long Thanh airport passenger terminal

|

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.

Prime Minister inspects Tan Son Nhat Terminal T3 project for the third time

|

HCMC - On the afternoon of February 1 (the 4th day of Tet), Prime Minister Pham Minh Chinh inspected and encouraged officials and workers who are constructing Terminal T3 at Tan Son Nhat Airport.

Terminal T3 is about to be completed, reducing the load at Tan Son Nhat airport

|

HCMC - The T3 terminal project at Tan Son Nhat airport has reached about 83% of the total volume, expected to be completed on April 30, 2025, 2 months earlier than the original plan.

Mobilizing many trucks and excavators to clean up the huge amount of mud and waste after floods in Hue

|

HUE - Using many overturned excavators and trucks to urgently clean up garbage and mud after floods, returning a clean and beautiful appearance to the city.

Supervising the kitchen of primary schools, parents discovered food suspected of being spoiled

|

Hanoi Suddenly checking the kitchen of Kim Quan Primary School, parents discovered that the food was not on the menu and there were signs of not being guaranteed in quality.

Warning of Ukraine's risk of getting involved in eternal conflict

|

The former NATO Secretary General warned that Ukraine is at risk of " perennial conflict" if Europe does not increase pressure on Russia.

Hue leaders criticize management units for being slow to handle, causing relics to be flooded for a long time

|

HUE - The relic of Cham Phu Dien Tower has been flooded for many days due to heavy rain, the leaders of Hue City requested a complete handling to ensure the safety of the relic.

Malaysia continues to call up many naturalized players for the 2027 Asian Cup qualifiers

|

Head coach Peter Cklamovski has just announced a list of 27 Malaysian players preparing for the match against Nepal in the 2027 Asian Cup qualifiers.

Shortening the time to complete the Long Thanh airport passenger terminal

PHẠM ĐÔNG |

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.

Prime Minister inspects Tan Son Nhat Terminal T3 project for the third time

MINH QUÂN |

HCMC - On the afternoon of February 1 (the 4th day of Tet), Prime Minister Pham Minh Chinh inspected and encouraged officials and workers who are constructing Terminal T3 at Tan Son Nhat Airport.

Terminal T3 is about to be completed, reducing the load at Tan Son Nhat airport

MINH QUÂN |

HCMC - The T3 terminal project at Tan Son Nhat airport has reached about 83% of the total volume, expected to be completed on April 30, 2025, 2 months earlier than the original plan.