Progress of Dong Da Lake renovation after 9 months of construction

Hữu Vũ |

Hanoi - After 9 months of implementation, many items of the Dong Da lake renovation project are gradually being completed.

The Dong Da Lake renovation project (also known as Hoang Cau Lake) is constructed by Vietnam Construction and Import-Export Joint Stock Corporation (VINACONEX), implemented in Dong Da district with a total investment of nearly 300 billion VND, expected to be completed in 2026.

The main goal of the project is to upgrade technical infrastructure, improve urban landscape and meet the living and entertainment needs of the people.

According to the reporter's records on April 16, at the Dong Da lake construction site, many items have clearly shown their shape.

In particular, items such as upgrading sidewalks, replacing railings, planting new trees and installing lighting systems are being urgently completed.

Cong nhan lat da nen duong dao ven ho Dong Da. Anh: Huu Vu
Workers paving the roadbed along Dong Da lake. Photo: Huu Vu

Notably, the stage and grandstand floating on the lake have been basically completed, creating a new landscape highlight for the area.

According to observations, the walking path along the lake is paved with stone, designed with soft iron railings around the lake, while the area near the water edge uses high-strength glass combined with a stainless steel frame, increasing aesthetics and modernity.

a
The floating grandstand is an important highlight of Dong Da lake. Photo: Huu Vu

Workers are currently paving the walking path around the lake. According to Dong Da District People's Committee, to serve the construction, the contractor has temporarily filled about 6,500m2 of the water surface to build a material storage yard and a floating stage.

Dong Da District People's Committee said this is a temporary construction organization measure and committed to returning the water surface to its original state after the project is completed. This temporary filling does not affect the water regulation function of the lake.

May xuc san gat mac bang nham thi cong cai tao ho Dong Da. Anh: Huu Vu
Excavators level the ground to renovate Dong Da lake. Photo: Huu Vu

Mr. Tran Van Bai, in charge of the project, informed: "The remaining items around the lake are being constructed continuously, striving to complete ahead of schedule. The area adjacent to Hoang Cau street is expected to be completed in May 2025".

Sau cai tao, ho Dong Da duoc ky vong se tro nen khang trang, sach dep voi kien truc hien dai, dong bo voi cac cong trinh hien co. Anh: Huu Vu
After renovation, Dong Da Lake is expected to become spacious, clean and beautiful with modern architecture, synchronous with existing works. Photo: Huu Vu

Dong Da District People's Committee emphasized that the renovation of the lake aims to create a space for community activities, sports, improve the quality of life and beautify the urban appearance. When completed, Dong Da Lake will be an attractive destination for people and tourists.

Toan canh cong truong cai tao ho Dong Da. Anh: Huu Vu
Overview of the Dong Da Lake renovation site. Photo: Huu Vu

The project is currently being accelerated to meet the schedule, ensure safety, quality and maintain the function of regulating water, with the expectation of bringing a green, modern living space to the capital.

Hữu Vũ
TIN LIÊN QUAN

Dong Da Lake renovation construction site on the eve of Tet

|

In the days leading up to the Lunar New Year 2025, workers at the Dong Da Lake renovation site are working hard to speed up the construction progress to ensure the project is handed over in June 2025.

Chips prove the vibrant and substantial situation of Vietnam - China cooperation

|

45 cooperation documents are a telling number, demonstrating the vibrant, substantial, diverse, and increasingly close intertwined interest of Vietnam and China.

General Phan Van Giang works with the Standing Committee of Lang Son Provincial Party Committee

|

On the afternoon of April 16, General Phan Van Giang, Member of the Politburo, Minister of Defense had a meeting with the Standing Committee of Lang Son Provincial Party Committee.

Vingroup proposes to build a 121 km long Hanoi - Quang Ninh passenger railway

|

The Hanoi - Quang Ninh passenger railway project is proposed to be invested with a length of about 121 km and a maximum design speed of 300 km/h.

Expected pilot Procuracy sued civil case in 6 provinces and cities

|

The pilot of the People's Procuracy (VKSND) sued the civil case in 6 provinces and cities to protect the civil rights of the subjects that are vulnerable groups.

Gold price is peaked over 115 million VND/tael, people in Ho Chi Minh City still buy

|

Ho Chi Minh City - On April 16, the gold market in Ho Chi Minh City continued to witness the momentum, with SJC gold price reaching more than 115 million dong/tael.

Assign the Presidential and Vice Chairman of Ho Chi Minh City People's Committee

|

Ho Chi Minh City - Chairman of Ho Chi Minh City People's Committee Nguyen Van Duoc has just signed a decision to assign work to the Chairman, Vice Chairmen of Ho Chi Minh City People's Committee for the term 2021 - 2026.

Sad news

|

Journalist Nguyen Huy Dan, born in 1928, due to his advanced age and weakness, died at 4:30 am on April 16, 2025, or 19.3 years, at 98 years old.

Dong Da Lake renovation construction site on the eve of Tet

NGỌC THÙY |

In the days leading up to the Lunar New Year 2025, workers at the Dong Da Lake renovation site are working hard to speed up the construction progress to ensure the project is handed over in June 2025.

Hà Nội yêu cầu công khai thông tin dự án cải tạo hồ Đống Đa

KHÁNH AN |

Hà Nội - UBND TP Hà Nội đề nghị quận Đống Đa công khai ngay các thông tin liên quan đến dự án cải tạo hồ Đống Đa để báo chí và người dân được biết.

UBND quận Đống Đa khẳng định không có việc lấp hồ Đống Đa

KHÁNH AN |

Hà Nội - Ngày 1.10, UBND quận Đống Đa có thông cáo báo chí về công tác triển khai thi công công trình "Cải tạo đồng bộ hạ tầng kỹ thuật, cảnh quan đô thị hồ Đống Đa".