Progress of relocation of a series of electric poles to serve the construction of the Dong Dang - Tra Linh expressway

Tân Văn |

Cao Bang - Of the 24 110kV high-voltage power poles that had to be relocated, none had been relocated.

On April 6, informing reporters, a representative of Cao Bang Power Company (PC Cao Bang) said that the relocation of power poles is being carried out at many different voltage levels, with a large workload and high technical requirements.

According to the review, to serve the construction of the Dong Dang - Tra Linh expressway in Cao Bang province alone, it will be necessary to relocate 24 locations of the 110kV power pole.

Hang chuc cot dien cao the 110kV se phai di doi de phuc vu xay dung cao toc Dong Dang - Tra Linh. Anh: Tan Van
Dozens of 110kV high-voltage power poles will have to be relocated to serve the construction of the Dong Dang - Tra Linh Expressway. Photo: Tan Van

Initially, the enterprise has carried out some tasks that do not require power outages, such as completing the installation of 1 waiting pole location, constructing 3 locations, and digging the foundation of 7 other locations. Of the total 22 110kV poles that need to be relocated, none have been completely relocated.

PC Cao Bang has registered a power outage schedule to relocate 9/22 locations of power poles between April 10 and 20 to serve site clearance in Thach An district.

According to the business representative, there are currently 2 new column locations that need to be relocated due to the need to expand the premises, these 2 locations are being designed by the investor.

For the 35kV medium-voltage line, the unit has relocated 14/91 locations and continued to implement the construction steps.

Mot vi tri cao toc dang duoc thi cong. Anh: Tan Van
A section of the expressway is under construction. Photo: Tan Van

Of which, 9 locations have completed pillars, 10 locations are under construction and 27 locations are in the preparation stage. The company is continuing to urge construction units to complete the registration of the power outage schedule for implementation in April 2025. Also in this item, 31 more locations have arisen that need to be relocated due to site clearance adjustment.

According to research, there are two transformer stations (TBAs) that need to be relocated, Ban Dam and Hanh Phuc 1 substations, which have not yet been implemented because Ban Dam station is waiting for technical design adjustments.

Regarding the 0.4kV low-voltage line system with 176 locations that need to be relocated, the units are focusing on constructing temporary routes, ensuring that the construction progress of the expressway project is not affected.

Tuyen cao toc di qua nhieu dia hinh doi nui cung gay kho khan phan nao cho viec di doi, keo lai duong day dien. Anh: Tan Van
The expressway passing through many types of terrain also makes it somewhat difficult to relocate and pull back power lines. Photo: Tan Van

Talking with reporters, Mr. Nguyen Van Nguyen - Deputy Director of Cao Bang Power Company affirmed that the unit is closely coordinating with the project investor, organizing periodic meetings to discuss, supporting the construction unit in developing safety plans and measures, and at the same time organizing timely power outages according to construction requirements.

According to the assessment up to now, the progress of relocating the power system has not affected the overall progress of the Dong Dang - Tra Linh expressway project, while ensuring a clearance for the route to be exploited later.

Due to its specific characteristics, the expressway project spans through many mountainous areas, cutting through medium and low voltage power lines. In addition, the pulling of wires requires waiting for the power outage schedule from the local Power Company and hydropower plants, affecting the progress of relocating the power grid and constructing the highway.

Cao Bang province is proposing that the Northern Power Corporation create conditions for negotiating technical plans for the locations of pillars and routes that need to be adjusted; at the same time, requesting the Northern Power System Control Center (A1) and the Power Companies of Cao Bang and Lang Son provinces to support temporary power outage procedures to speed up relocation progress.

Tân Văn
RELATED NEWS

Cao Bang disburses public investment capital lower than the national average

|

Cao Bang - In the first quarter of 2025, the locality has only disbursed 234.409 billion VND in public investment capital, reaching 5.1% of the plan.

Urgently measuring and reclaiming land to build Ninh Thuan nuclear power

|

Ninh Thuan - The locality is implementing measurements, counting, statistics and issuing a notice of land acquisition to serve the Ninh Thuan Nuclear Power Project.

Concerns about storks affecting power grid safety

|

Ha Tinh - In the first 3 months of 2025, there were 7 incidents in Ha Tinh due to violations of the power grid safety corridor, 6 cases due to people releasing kites.

What did the Deputy Director of the Department of Performing Arts say about Jun Pham's sensitive MV?

|

Leaders of the Department of Performing Arts said that the issue of MVs containing sensitive images of Jun Pham was assigned to local units to handle according to their authority.

Dong Nai court accepts lawsuit against company with Tet bonus lower than labor agreement

|

Dong Nai - District 1 People's Court has accepted the lawsuit of the grassroots Trade Union of Tenma (HCM) Vietnam Co., Ltd., requesting the company to give Tet bonuses of at least 1 month's salary.

Politburo agrees with the policy of establishing Quang Ninh city directly under the Central Government

|

Quang Ninh - The Central Executive Committee has just issued the Politburo's Conclusion on the policy of establishing Quang Ninh city directly under the Central Government.

New regulations on civil servant positions

|

The Government assigned the Ministry of Home Affairs to advise on the promulgation of the Government's Decree regulating the position of civil servants.

Cao Bang disburses public investment capital lower than the national average

Tân Văn |

Cao Bang - In the first quarter of 2025, the locality has only disbursed 234.409 billion VND in public investment capital, reaching 5.1% of the plan.

Urgently measuring and reclaiming land to build Ninh Thuan nuclear power

Hữu Long |

Ninh Thuan - The locality is implementing measurements, counting, statistics and issuing a notice of land acquisition to serve the Ninh Thuan Nuclear Power Project.

Concerns about storks affecting power grid safety

TRẦN TUẤN |

Ha Tinh - In the first 3 months of 2025, there were 7 incidents in Ha Tinh due to violations of the power grid safety corridor, 6 cases due to people releasing kites.