Disbursement progress of 19,280 billion VND project through Binh Duong

ĐÌNH TRỌNG |

The Ho Chi Minh City Ring Road 3 project through Binh Duong province has an investment capital of 19,280 billion VND. Currently, units are speeding up the capital disbursement and project construction progress.

Ho Chi Minh City Ring Road 3, passing through Binh Duong province, is about 26.6km long, with a total investment of VND 19,280 billion. The project is divided into 2 component projects.

In which, component project 5 is construction and installation divided into 4 construction packages of more than 11km of roads and connecting bridges. The construction package of Binh Chuan intersection started at the end of June 2023, and by the end of September 2024, the construction had reached 122 billion VND/490 billion VND, reaching over 25% of the contract volume.

The Binh Goi bridge construction package started at the end of August 2023. Up to now, the construction has reached 269/569 billion VND, reaching 47.4% of the contract volume.

The construction package from Binh Chuan to Saigon River started in January 2024. Up to now, the construction has reached 185/1,654 billion VND, over 11% of the contract volume.

Cac tru cau vuot nut giao Binh Chuan du an duong Vanh dai 3 TPHCM qua Binh Duong. Anh: Dinh Trong
The piers of the Binh Chuan intersection overpass of the Ho Chi Minh City Ring Road 3 project through Binh Duong. Units are speeding up the disbursement and construction progress of the project. Photo: Dinh Trong

Tan Van intersection construction package started at the end of April 2024, construction progress reached 19.3% of project volume.

Mr. Nguyen Huu Tuan - Deputy Director of the Department of Transport of Binh Duong province said that the total construction packages have so far spent 1,412/3,237 billion VND (reaching 44.6%).

For component project 6, site clearance and resettlement have a total investment of 13,528 billion VND.

Binh Duong province has focused on site clearance, following the construction progress of the packages. Currently, the total area of ​​recovered land and available land is 125/129ha (reaching 97.6%).

Goi xay lap duong tu Binh Chuan den song Sai Gon. Anh: Dinh Trong
Road construction package from Binh Chuan to Saigon River. Photo: Dinh Trong

Mr. Nguyen Huu Tuan - Deputy Director of the Department of Transport of Binh Duong province, said that the compensation disbursement to date has reached 7,770/8,403 billion VND (over 92%).

15.3km is expected to be invested nearly 1 billion USD to make 4 lanes expressway

Regarding the 15.3km section of Ho Chi Minh City Ring Road 3 that overlaps with the existing My Phuoc Tan Van Road, Binh Duong Province has held many meetings to discuss the investment plan for this section. The province has also reported to the Prime Minister to seek his opinion on the investment plan.

According to records, a 15.3km section starting from a point near National Highway 1A to Binh Chuan intersection has been built with a 6-lane road. Currently, this section of road is often overloaded and congested.

Du kien lam 4 lan xe cao toc tren cao duong Vanh dai 3 TPHCM trung voi My Phuoc Tan Van. Anh: Dinh Tong
It is planned to build 4 lanes of expressway on the elevated Ring Road 3 of Ho Chi Minh City, coinciding with My Phuoc Tan Van. Photo: Dinh Tong

Binh Duong province plans to invest in phase 1 to clear land on one side of My Phuoc Tan Van road and build a 4-lane elevated highway bridge, with an investment capital of about 1 billion USD.

ĐÌNH TRỌNG
RELATED NEWS

Ho Chi Minh City will elect the new Chairman of the People's Council and Chairman of the People's Committee on March 30

|

Ho Chi Minh City will elect the Chairman of the Ho Chi Minh City People's Council, Vice Chairmen of the People's Council; Chairman of the Ho Chi Minh City People's Committee and Vice Chairmen of the People's Committee for the term 2026 - 2031 on March 30.

Kim Jong Un re-elected Chairman of North Korea

|

Mr. Kim Jong Un was re-elected Chairman of the North Korean State Council Committee in the first session of the 15th Supreme People's Assembly.

Hanoi plans to build a 2,000 billion VND theater, 9,000m2 wide

|

Hanoi - In the period 2026-2030, the city will build a theater of about 9,000 m2 on Vo Thi Sau street with an investment of about 2,000 billion VND.

Iranian nuclear power plant at risk of attack

|

US President Donald Trump declares he will eradicate the Iranian nuclear power plant unless Tehran reopens the Strait of Hormuz.

Dong Ha bypass road at risk of delay due to site clearance problems, calculating coercive measures

|

Quang Tri - The Dong Ha bypass road project is at risk of continuing to be delayed. The locality is looking for solutions and considering coercive measures to clear the site.

Quat Lam beach deserted before revival plan

|

Ninh Binh - Before the plan to develop marine tourism, the Quat Lam area is deserted, many accommodation establishments are degraded, and tourism activities are quiet.

Messi scores his 901st goal, Inter Miami dramatically wins back

|

On the morning of March 23 (Vietnam time), Lionel Messi scored from the free kick, helping Inter Miami CF defeat New York City FC 3-2 in MLS 2026.

Ho Chi Minh City faces major challenges in public investment disbursement

MINH QUÂN |

In the last months of the year, Ho Chi Minh City faced a major challenge in disbursing public investment when many key projects were behind schedule, causing the disbursement rate to only reach 20%.

Báo cáo Thủ tướng việc xây cao tốc trên cao 24.000 tỉ đồng

ĐÌNH TRỌNG |

Tỉnh Bình Dương vừa báo cáo Thủ tướng Chính phủ phương án làm cao tốc 4 làn xe trên cao đoạn 15,3km đường Vành đai 3 TPHCM.

Đẩy nhanh tiến độ hạng mục 571 tỉ đồng của dự án Vành đai 3 TPHCM qua Bình Dương

ĐÌNH TRỌNG |

Sau gần 1 năm khởi công, nút giao Bình Chuẩn (thuộc dự án Vành đai 3 TPHCM qua Bình Dương) đã thi công được khoảng trên 20% khối lượng. Những trụ, bệ đỡ cầu đầu tiên của cầu vượt đã thành hình, nền đường dẫn cũng đang được đẩy mạnh thi công.