Progress of site clearance and construction of 46km of highway in Ho Chi Minh City

ĐÌNH TRỌNG |

HCMC - After nearly 1 year of construction, the HCMC - Thu Dau Mot - Chon Thanh expressway project, the section through Binh Duong, has not yet had enough construction site.

The Ho Chi Minh City - Thu Dau Mot - Chon Thanh Expressway project through the old Binh Duong province is 46km long. The land area recovered for the project is 344 hectares, affecting 1,615 households, individuals and organizations. It is expected that 252 cases will be resettled.

The site clearance project passes through 10 communes and wards, including: Tan Khanh, Tan Hiep, Vinh Tan, Binh Duong, Binh Co, Phuoc Hoa, An Long, Chanh Phu Hoa ward and Bau Bang commune.

Up to now, the units have completed the announcement of land recovery and measurement and appraisal of the drawings. Complete the approval of specific land prices and are making efforts to complete the inventory.

Doan giao nhau voi duong DT 746 chua co mat bang thi cong. Anh: Dinh Trong
The intersection with DT 746 road has no construction site yet. Photo: Dinh Trong

Notably, by the end of November 2025, the competent authority had approved the plan and disbursed compensation, support, and resettlement to over 1,000 cases with an amount of VND 3,800 billion. Individuals and organizations have handed over 153 hectares of land.

Currently, the Land Fund Development Centers are coordinating with 9 communes and wards to continue to mobilize people to agree to receive compensation and hand over the site.

Regarding the project construction, according to the Ho Chi Minh City People's Committee, the project has been started since the beginning of 2025. According to records, at the starting point intersecting with DT 746 road in Tan Hiep ward, construction has not yet been completed. This section, the project runs along Suoi Cai project for about 7km, mainly passing through the people's agricultural land. Here, the handover site is not large and not synchronous, so construction cannot be carried out yet.

Cot moc giai phong mat bang doan qua phuong Binh Duong. Anh: Dinh Trong
Land clearance milestone through Binh Duong ward. Photo: Dinh Trong

Notably, the about 10km section passing through rubber farms (in Phu Giao district, the old Binh Duong province), the handover site is quite complete. In particular, an organization has proactively handed over 80 hectares of land to build a highway.

According to records, rubber trees have been cut down to make way for the expressway construction. The contractor is constructing the roadbed at the intersection between the expressway and the Bac Tan Uyen - Phu Giao - Bau Bang dynamic road. The expressway surface and parallel roads on both sides are also under construction. Contractors are focusing on machinery and human resources to make road surfaces and pour rocks...

Phoi canh nut giao cua cao toc voi duong tao luc Bac Tan Uyen - Phu Giao - Bau Bang va duong DT 750. Anh: Dinh Trong
Perspective of the expressway's intersection with the Bac Tan Uyen - Phu Giao - Bau Bang dynamic road and DT 750 road. Photo: Dinh Trong
Hien trang cong truong thi cong ghi nhan ngay 8.12. Anh: Dinh Trong
Current status of the construction site recorded on December 8. Photo: Dinh Trong
Nha thau dang thi cong doan khoang gan 10km doan qua giao voi duong tao luc Bac Tan Uyen - Phu Giao - Bau Bang. Anh: Dinh Trong
The contractor is constructing a section of nearly 10km through the intersection with the Bac Tan Uyen - Phu Giao - Bau Bang dynamic road. Photo: Dinh Trong
Nha dau tu dang tap trung hang chuc may moc. Anh: Dinh Trong
Investors are focusing on dozens of machines. Photo: Dinh Trong
Hinh hai gan 10km cao toc dang dan lo dien. Anh: Dinh Trong
The shape of nearly 10km of the highway is gradually emerging. Photo: Dinh Trong

It is known that the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project has a total length of about 52.159km. Of which, the section passing through the old Binh Duong province is nearly 46km long with a total investment of about VND 17,400 billion. The project is designed with a scale of 4 complete lanes, a road surface width of 25.5m, and a design speed of 100 km/h. The route includes 4 interconnecting intersections, 21 expressway bridges, 5 direct overpasses and 14 underpasses for people.

ĐÌNH TRỌNG
RELATED NEWS

National Assembly deputies propose the construction of Vinh - Thanh Thuy 6-lane expressway

|

National Assembly deputies proposed to immediately invest in the Vinh - Thanh Thuy expressway project with a scale of 6 lanes in the 2026-2030 period because of the strategic significance of the route.

Revealing the complex construction intersection on the Bien Hoa - Vung Tau Expressway connecting Dong Nai to Ho Chi Minh City

|

Dong Nai - The intersection between Vo Nguyen Giap Street (Phuoc Tan Ward) and Bien Hoa - Vung Tau Expressway connecting to Ho Chi Minh City is gradually becoming clear.

Disburse about VND2,400 billion to compensate for the construction site of Ho Chi Minh City Ring Road 4 through the old Binh Duong

|

HCMC - The units have disbursed compensation of about VND 2,400 billion for site clearance to build the Ho Chi Minh City Ring Road 4 project, the section passing through the old Binh Duong area.

Quang Ninh plans to build 9 bridges connecting islands in Van Don

|

Quang Ninh - To facilitate traffic connection between islands in Van Don Special Zone, Quang Ninh province plans to build 9 bridges and 22km of road.

Japan F-35 explores damage from 7.6 Richter earthquake

|

Japan mobilized a series of aircraft, including the F-35, to explore information about the situation and damage after the 7.6 Richter earthquake on the evening of December 8.

Russia controls many key highways on the battlefield

|

On December 9, the Russian military took control of all major highways in the Kupyansk urban cluster, Ukraine.

How reservoirs in Khanh Hoa calculate floodwater and operate overflow discharge

|

Khanh Hoa - Reservoirs will calculate the amount of water in the reservoir according to meteorological bulletins and there will be a notice at least 6 hours before releasing floodwaters.

Ha Tinh's economic growth in 2025 will lead the North Central provinces

|

Ha Tinh - In 2025, Ha Tinh province's economic growth will reach 8.78%, ranking 10th out of 34 provinces and cities nationwide, ranking first in the North Central region.

National Assembly deputies propose the construction of Vinh - Thanh Thuy 6-lane expressway

PHẠM ĐÔNG |

National Assembly deputies proposed to immediately invest in the Vinh - Thanh Thuy expressway project with a scale of 6 lanes in the 2026-2030 period because of the strategic significance of the route.

Revealing the complex construction intersection on the Bien Hoa - Vung Tau Expressway connecting Dong Nai to Ho Chi Minh City

HÀ ANH CHIẾN |

Dong Nai - The intersection between Vo Nguyen Giap Street (Phuoc Tan Ward) and Bien Hoa - Vung Tau Expressway connecting to Ho Chi Minh City is gradually becoming clear.

Disburse about VND2,400 billion to compensate for the construction site of Ho Chi Minh City Ring Road 4 through the old Binh Duong

ĐÌNH TRỌNG |

HCMC - The units have disbursed compensation of about VND 2,400 billion for site clearance to build the Ho Chi Minh City Ring Road 4 project, the section passing through the old Binh Duong area.