Progress and roadmap of the 2,300 billion VND hospital

ĐÌNH TRỌNG |

The 1,500-bed hospital with an investment capital of about VND2,300 billion in Binh Duong is being rushed to completion, expected to be put into operation at the end of 2025.

Recently, people in Binh Duong continue to pay attention to the construction of the 1,500-bed Binh Duong General Hospital in Dinh Hoa Ward, Thu Dau Mot City. According to people, this hospital has been under construction for a long time and needs to be urgently accelerated to complete and put into operation soon.

Regarding the above issue, according to the Binh Duong Provincial Electronic Information Portal, recently, the Binh Duong Provincial Construction Investment Project Management Board has responded to voters' petitions.

Up to now, the 1,500-bed General Hospital project is being urgently completed by the Provincial Construction Investment Project Management Board and contractors, focusing resources to complete according to the contractor's committed schedule.

For package 1, the volume of work performed to date has reached about 92.3% of the contract. The remaining work mainly consists of installing terminal equipment such as cameras, and the MEP system is still under construction.

For the arising volumes of group 5, the contractor is implementing construction, expected to be completed in the third quarter of 2025.

For package 2, the construction part has been basically completed, but the terminal equipment volume still has to wait for complete installation, synchronized with the entire system, expected to be completed in the third quarter of 2025.

Regarding the solution, the Provincial Construction Investment Project Management Board has developed a detailed plan for each work content, assigned responsibilities, and implementation time. Currently, relevant agencies and units are closely coordinating on each work content.

The Provincial Construction Investment Project Management Board actively urged contractors to speed up the import of new operating room equipment and complete construction.

Regarding the implementation plan for completion and exploitation, the Provincial Construction Investment Project Management Board said that the construction of the project is expected to be completed in the third quarter of 2025.

By the fourth quarter of 2025, the systems will be tested and operated, and the overall project will be completed. The organization will invite specialized agencies to inspect the acceptance and handover of the project for use.

2,300 billion VND hospital project is behind schedule

The project has an investment capital of about 2,300 billion VND. The project allocated capital to start building the foundation in late 2014. However, the project then stopped construction for nearly 3 years. It was not until late 2018 that construction began again and was promised to be completed around June 2020. However, after many delays, many items are still unfinished and the items cannot be connected to each other.

ĐÌNH TRỌNG
TIN LIÊN QUAN

How is the progress of the 1,500-bed hospital project after 10 years?

|

The 1,500-bed General Hospital project in Binh Duong (initial investment capital of 2,300 billion VND) was built in 2014 and is still not completed.

Verifying the case of students paying for martial arts classes to get exercise in Dak Lak

|

Dak Lak - The provincial Department of Education and Training directed Phan Dang Luu High School to verify parents' feedback about students paying for martial arts classes to achieve physical education.

The Ministry of Health proposes cash or in-kind support for families with one child, two daughters

|

The Ministry of Health proposes to give preferential maternity leave, cash or in kind support when giving birth to one child, two daughters.

Building the North-South high-speed railway, Hanoi Chairman assigns tasks to the Secretaries of communes and wards

|

The Chairman of Hanoi believes that the Party Secretaries of the communes must be the head of the commune's steering committee for site clearance to implement the North-South high-speed railway project.

Mr. Trump announces that all tariffs will be imposed on trading partners

|

Mr. Trump has announced that he will impose a Joint Stock tariff (blanket tariff) of 15-20% on most of the remaining US trading partners.

Must control livestream sales in real time

|

Developing the Law on E-commerce requires real-time control of livestream sales.

The Ministry of Education and Training manages 2 national universities from September 1

|

The two national universities will be managed by the Ministry of Education and Training from September 1, have legal status, separate accounts and use seals with the National emblem.

There will be blocks in the sky, on the ground, Submarines, and surface ships participating in the parade on the occasion of National Day

|

The parade and march on the occasion of the 80th anniversary of National Day will have pedestrian blocks, tanks, blocks in the sky, underwater, with the presence of launched launched ships and floating ships.

Dự án bệnh viện nghìn tỉ bỏ hoang trên đất vàng Hà Nội

Nhật Minh |

Hà Nội - Nằm trên địa bàn quận Cầu Giấy (Hà Nội), dự án bệnh viện quốc tế Hoa Kỳ - Hà Nội rơi vào tình trạng thi công dở dang, bỏ hoang suốt nhiều năm qua.

How is the progress of the 1,500-bed hospital project after 10 years?

ĐÌNH TRỌNG |

The 1,500-bed General Hospital project in Binh Duong (initial investment capital of 2,300 billion VND) was built in 2014 and is still not completed.

Thay nhà thầu, điều chỉnh dự án bệnh viện 1.500 giường

ĐÌNH TRỌNG |

Dự án Bệnh viện 1.500 giường kéo dài thời gian thực hiện, tỉnh Bình Dương quyết định thay nhà thầu, điều chỉnh dự án thiết bị bệnh viện.