Continue to lower prices for forest timber plots to remove obstacles for transportation projects

HƯNG THƠ |

Quang Tri province continues to lower the starting price of a wood lot located in an area of over 14 hectares of natural forest.

On April 3, the Ben Hai River Basin Protection Forest Management Board (Quang Tri province) said that it is coordinating with relevant units to implement procedures for auctioning forest wood.

This amount of wood is located in an area of 14.199 hectares in sub-zone 580, Vinh O commune (Vinh Linh district), managed by the Ben Hai River Basin Protection Forest Management Board. According to the approved decision of the People's Committee of Quang Tri province, the initial starting price is 1,650,250,000 VND.

Mr. Nguyen Ngoc Hung - Director of the Ben Hai River Basin Protection Forest Management Board said that after 3 unsuccessful auctions due to no customers participating, the unit proposed a price reduction and was approved by the Provincial People's Committee.

"With a new starting price of more than 1.6 billion VND, we expect customers to participate in the auction, conduct exploitation and site clearance for road construction" - Mr. Hung said.

According to Mr. Hung, the locality is currently implementing a road project connecting the East branch of Ho Chi Minh Road with the West branch. However, there are still 4.5km of site that have not been handed over due to natural forest area.

On November 24, 2023, the Prime Minister approved the conversion of this forest area to serve the project. After that, the unit organized the auction of the converted area, with a starting price of nearly 5.9 billion dong. However, the first and second auctions have no customers. By the third time, although the price dropped to VND 3.5 billion, there was no interest in, forced to continue to decrease to more than 1.6 billion.

According to the explanation, the main reason for the lack of customers is that most of the wood is in group V to group VIII, with low economic value. In addition, the forest area that needs exploitation is located along the designed road but has not been opened to traffic, so transportation is very difficult.

While the auction is at a standstill, the road project connecting the East - West branches of Ho Chi Minh Road is at risk of being behind schedule compared to the requirements.

HƯNG THƠ
RELATED NEWS

Three times auctioning forest wood to build roads but no one paid attention

|

Quang Tri - Three times auctions were held to exploit natural forest wood for road construction but still no customers participated.

Forest timber auction has no customers, review starting price

|

Quang Tri - After two auctions of natural forest areas without any customers participating, the authorities had to consider rebuilding the starting price.

Traffic project stuck because natural forest has not been cleared

|

Quang Tri - The natural forest area that the road passes through has not been cleared, causing the road project to be stuck and behind schedule.

Cars parked rampant on Tang Bat Ho street causing traffic obstruction

|

Hanoi - Traffic police will strengthen patrols and handle the situation of cars stopping and parking in violation of regulations on Tang Bat Ho street.

16th National Assembly deputies candidates meet with voters in Bac Ninh

|

Candidates for National Assembly Deputies of the 16th term meet with voters at constituency No. 3, Bac Ninh province.

Tan Van intersection, the largest on Ring Road 3 in Ho Chi Minh City, is about to open to traffic, reducing congestion in the East

|

Ho Chi Minh City - Tan Van intersection, the largest of the Ho Chi Minh City Ring Road 3 project with a total capital of more than 1,800 billion VND, is being accelerated and is expected to open to traffic on June 30.

Holiday schedule for Hung Kings Commemoration Day 2026 and occasion April 30 - May 1

|

In 2026, the holiday schedule for the Hung Kings Commemoration Day and the occasion April 30 - May 1 for workers has been determined according to the provisions of the Labor Code.

Thanh Hoa Department of Education and Training concludes the case of teachers of To Hien Thanh High School correcting scores

|

Thanh Hoa - The Department of Education and Training (GDĐT) of the province has the results of inspection and verification of the case of amending semester exam scores that occurred at To Hien Thanh High School.

Three times auctioning forest wood to build roads but no one paid attention

HƯNG THƠ |

Quang Tri - Three times auctions were held to exploit natural forest wood for road construction but still no customers participated.

Forest timber auction has no customers, review starting price

HƯNG THƠ |

Quang Tri - After two auctions of natural forest areas without any customers participating, the authorities had to consider rebuilding the starting price.

Traffic project stuck because natural forest has not been cleared

HƯNG THƠ |

Quang Tri - The natural forest area that the road passes through has not been cleared, causing the road project to be stuck and behind schedule.