Panorama of the 490 billion VND road ahead of schedule in Phu Tho

Tô Công |

Phu Tho - The Road project connecting National Highway 32 to Provincial Road DT.116 connecting Tam Nong Industrial Park with Trung Ha Industrial Park has exceeded the schedule.

The Road project connecting National Highway 32 to Provincial Road 316 connecting Tam Nong Industrial Park with Trung Ha Industrial Park (phase I) - with a total investment after adjustment of more than 490 billion VND, invested by Tam Nong District People's Committee.

Toan canh tuyen duong cua du an. Anh: To Cong.
Panorama of the project's route. Photo: To Cong.

This project started in September 2022, investing in the construction of a road with a total length of 8.89km through Hung Hoa town and the communes of Van Xuan, Huong Non, Dan Quyen, Tam Nong district.

According to the design, this traffic road project has a road surface width of 11 to 18m (from 2 to 4 lanes for motor vehicles, 2 lanes for rudimentary vehicles).

Mat duong rong rai. Anh: To Cong.
The road surface is spacious with 4 lanes for motor vehicles and 2 lanes for non-motor vehicles. Photo: To Cong.

According to the reporter of Lao Dong Newspaper in late March 2025, the entire route has been paved with asphalt concrete, the drainage system, street lights, signal lights, road markings... have all been completed.

Tuyen duong rong rai, uon luon. Anh: To Cong.
The road is spacious and winding. Photo: To Cong.

It can be seen that this new route has a starting point connecting with National Highway 32 in Van Xuan commune, built through Huong Non commune and Hung Hoa town, the end point is at Provincial Road 317G in Dan Quyen commune; the route runs parallel to Ho Chi Minh road and National Highway 32.

Binh do tuyen duong. Anh: To Cong.
Route map. Photo: To Cong.

Mr. Le Huu Hoang - a resident of Van Xuan commune, Tam Nong district shared: "The new road is very spacious, helping to reduce the load on National Highway 32 through Van Xuan and Huong Non communes in some or crowded sections such as: Co Tiet intersection, Phong Chau bridge, Tam Nong High School (the section where vehicles often line up to Phong Chau pontoon bridge)...

The new route contributes to changing the face of my hometown, I hope the economy will develop further".

Diem dau tuyen duong tai xa Van Xuan. Anh: To Cong.
The starting point of the route is in Van Xuan commune. Photo: To Cong.

According to the representative of the Investor, the Tam Nong District Investment and Construction Project Management Board, phase I of the project has so far completed the construction of all work items according to the approved design, nearly 1 year ahead of schedule.

Nhung con doc kha cao duoc tao thanh. Anh: To cong.
Quite high slopes were created. Photo: To Cong.

"The unit has coordinated with the construction contractor and supervision consultants to conduct an inspection and acceptance of the entire completed volume according to the approved design documents. In the coming time, after the road is inspected by competent authorities, the acceptance work will be officially handed over and put into use" - said the representative of the project investor.

Previously, at the 6th Session, the People's Council of Phu Tho province, term XIX, passed a Resolution to adjust the project investment policy: The traffic road connecting from National Highway 32 to DT.116 connecting Tam Nong Industrial Park with Trung Ha Industrial Park.

Accordingly, the project has updated and adjusted the total investment due to adjustments and supplements to arising costs of compensation, site clearance, design adjustments, estimates and other related costs. The total investment after adjustment is 490.1 billion VND (more 40.1 billion VND).

Adjusted investment capital structure: Central budget medium-term capital for the period 2021 - 2025: 350 billion VND; Provincial budget for the period 2021 - 2025: More than 98.4 billion VND; Tam Nong district budget and other legally mobilized capital sources: More than 41.6 billion VND.

Tô Công
RELATED NEWS

Bac Ninh requests to ensure the progress of the 86,000 billion VND project

|

Bac Ninh - Bac Ninh province requires the implementation of the Ring Road 4 - Capital Region project through the area to ensure safety, quality, and on schedule.

Risk of breaking the progress of site clearance for Tuyen Quang Expressway

|

The Tuyen Quang - Ha Giang Expressway is still nearly 5.3km uncleared, while the deadline for this must be completed before March 31.

Pickup truck stuck while trying to overtake a level crossing in Hanoi

|

Hanoi - When the barrier was lowering, the pickup truck driver still drove the vehicle in, then got stuck close to the railway tracks.

Russian air defense shoots down HIMARS missiles and 568 Ukrainian UAVs in 1 day

|

Russian air defense forces shot down a US-made HIMARS missile and 568 Ukrainian fixed-wing UAVs within 24 hours.

Leaders of Bac Ninh province dialogue with trade union officials, union members, and workers

|

Bac Ninh - Provincial Party Secretary, Chairman of the Provincial People's Committee meets and dialogues with trade union officials, union members, and workers.

Trade union news: Pension payment time for May 2026

|

Trade union news bulletin on April 19: Pension payment time for May 2026; 2 majors with the highest recruitment in April 2026 in Hanoi;...

Iran completely closes the Strait of Hormuz, opens fire on ships

|

Tensions around the Strait of Hormuz continued to escalate on April 18 when Iran reversed its decision to reopen the strait and opened fire on ships trying to pass through.

1 Major General, 9 lieutenant colonels of the Army hand over positions and receive new assignments

|

1 Major General, 8 Colonels, 1 Senior Lieutenant Colonel of the Army have just been transferred, appointed, and handed over new responsibilities and tasks by the Ministry of National Defense and the Military Region.

Bac Ninh requests to ensure the progress of the 86,000 billion VND project

Vân Trường |

Bac Ninh - Bac Ninh province requires the implementation of the Ring Road 4 - Capital Region project through the area to ensure safety, quality, and on schedule.

Đôn đốc dự án nước sạch nhiều lần chậm tiến độ

TRẦN TUẤN |

Hà Tĩnh - Dự án Nhà máy nước sạch gần 230 tỉ đồng ở huyện Hương Khê nhiều lần chậm tiến độ nên UBND tỉnh Hà Tĩnh yêu cầu làm rõ nguyên nhân và trách nhiệm.

Risk of breaking the progress of site clearance for Tuyen Quang Expressway

Việt Bắc |

The Tuyen Quang - Ha Giang Expressway is still nearly 5.3km uncleared, while the deadline for this must be completed before March 31.