Construction speed of 65 billion VND river embankment project within 3 months

TRẦN TUẤN |

Ha Tinh - Construction of the Ngan Sau River embankment project through Ha Linh commune (Huong Khe district) is being accelerated within 3 months.

On November 15, present at the Ngan Sau River bank erosion repair project through village 5 and village 2, Ha Linh commune (Huong Khe district), Lao Dong Newspaper reporter recorded that the two contractors, a joint venture of Hoang Lai Company and Hoang Long Company, were concentrating maximum machinery and human resources on construction.

Many excavators, bulldozers, and trucks were mobilized to dig, fill, and tarpaulin the riverbank to carry out the Ngan Sau river embankment project, and at the same time construct the steel and structural components.

Mr. Nguyen Anh Tuan - Director of the Management Board of Construction Investment Projects of Huong Khe district - said that the project to overcome landslides on the banks of Ngan Sau river through village 5 and village 2, Ha Linh commune is one of 7 projects to overcome the consequences of natural disasters from the central reserve budget in 2023.

The project to overcome landslides on the banks of the Ngan Sau River through Village 5 and Village 2, Ha Linh Commune has a total investment of 65 billion VND. Of which, the central budget is 60 billion VND, and the counterpart capital of the investor, the People's Committee of Huong Khe District, is 5 billion VND.

After the project was approved, from February 2024, the investor carried out the procedures according to regulations, organized bidding, selected contractors and started construction from November 1, 2024.

Xe, may tap trung thi cong. Anh: Tran Tuan.
Vehicles and machines focus on construction. Photo: Tran Tuan

“The project is 1.5km long. Currently, 2 contractors are mobilizing more than 20 machines to participate in the construction, including excavators, bulldozers, rafts... along with 30 officers and workers including machine drivers... to carry out construction at a speed of 3 shifts, 4 teams to disburse public investment capital from the central budget before December 31, 2024. As for the local budget, it will be disbursed later, so the project is allowed to be completed by January 31, 2025,” Mr. Tuan shared.

The Director of the Huong Khe District Construction Investment Project Management Board added that after 15 days of construction, the project to overcome landslides on the Ngan Sau riverbank through village 5 and village 2, Ha Linh commune has completed 15% of the construction volume.

At peak, the project will increase the workforce to about 50 - 60 people on site.

According to Mr. Tuan, with such great progress pressure, during bad weather and wind, the work of processing steel and structural components must be carried out.

“Fortunately, this project has been very smooth in terms of land clearance. 100% of households donated land, only compensation for property and trees on the land was about 2 billion VND. Currently, the land clearance is 100% complete,” Mr. Tuan added.

With such a short time pressure, whether the construction quality can be guaranteed, Mr. Tuan affirmed that we must focus on ensuring progress but at the same time still put quality first. To do that, when pouring concrete, the contractor has committed to adding additives to help the concrete bond quickly and increase its strength.

Dai dien chu dau tu du an khang dinh day nhanh tien do nhung phai xem dam bao chat luong cong trinh la yeu to hang dau. Anh: Tran Tuan.
The project investor representative affirmed that the progress will be accelerated but the quality of the project must be considered the top priority. Photo: Tran Tuan

The reason why the project is in such a short and urgent construction period, according to Mr. Tuan, is because it has to fully implement investment procedures and processes according to regulations.

Recently, the People's Committee of Ha Tinh province has repeatedly issued documents urging the progress of 7 natural disaster recovery projects in the province from the central reserve budget in 2023.

“In all cases, the Chairmen of the People's Committees of the districts: Huong Khe, Vu Quang, Duc Tho, Cam Xuyen and Hong Linh town must take full responsibility for the progress and must disburse the central support capital before December 31, 2024” - according to the direction of the People's Committee of Ha Tinh province.

TRẦN TUẤN
TIN LIÊN QUAN

Giao Hoa River embankment completed, people no longer worry about landslides

|

Ben Tre - The completion of the Giao Hoa River embankment project will prevent erosion that affects more than 300 households.

Land acquisition issues, river embankment to prevent landslides in Da Nang slow progress

|

Due to site clearance problems, some emergency riverbank anti-erosion projects in Da Nang cannot be implemented on schedule.

People are upset because the residential road to Tran Hung cemetery is blocked

|

Hanoi - People in Phu Dien ward are upset because the road leading to Tran Hung cemetery is blocked, making it difficult to visit the ancestral tomb.

Hanoi proposes to pilot the removal of notarization and certification for real estate transactions

|

Hanoi is considering piloting the removal of notarization and certification of real estate donation contracts between individuals in the project.

HCMC reports after residents texted Standing Deputy Secretary of the City Party Committee Nguyen Thanh Nghi

|

HCMC - Regarding the reporter's text message to Standing Deputy Secretary of the HCMC Party Committee Nguyen Thanh Nghi, the HCMC People's Committee has just reported the handling results.

The contrasting picture behind PJICO's growth figures

|

Motor vehicle insurance brings a large source of income to PJICO, but also carries high risks because all compensation is borne by the enterprise itself.

Fire in a tourist electric vehicle parking lot in Huong Tich pagoda area, many cars burned down

|

Ha Tinh - At noon on July 8, a major fire broke out at the electric car parking lot in the Huong Tich pagoda tourist area, burning down 9 electric cars and 1 car.

Consider handling organizations and individuals if there are violations in the bidding package proposed by Son Hai Group

|

The Ministry of Finance has just sent a document reporting to the Government on the bid package previously proposed by Son Hai Group.

Giao Hoa River embankment completed, people no longer worry about landslides

Thành Nhân |

Ben Tre - The completion of the Giao Hoa River embankment project will prevent erosion that affects more than 300 households.

Land acquisition issues, river embankment to prevent landslides in Da Nang slow progress

Nguyễn Linh |

Due to site clearance problems, some emergency riverbank anti-erosion projects in Da Nang cannot be implemented on schedule.

Phú Thọ tìm nhà thầu dự án 75 tỉ đồng kè sông Hồng sạt lở

Tô Công |

Sở Nông nghiệp và Phát triển nông thôn tỉnh Phú Thọ đã công khai Kế hoạch lựa chọn nhà thầu dự án kè xử lý sạt lở bờ sông Hồng tại huyện Lâm Thao.