HCMC builds 2 more bridges to relieve traffic jams in Thu Duc City

MINH QUÂN |

HCMC - The My Thuy Intersection Project (Thu Duc City) is implementing phase 3 with the construction of an overpass on Ring Road 2 and Ky Ha 3 Bridge, with a total capital of 312 billion VND.

On March 13, Mr. Luong Minh Phuc - Director of the Ho Chi Minh City Traffic Construction Investment Project Management Board (investor) said that he will hold a groundbreaking ceremony for phase 3 of the My Thuy intersection project tomorrow morning (March 14).

This phase includes the construction of an overpass on Ring Road 2 ( Vo Chi Cong Street) - the right branch with a scale of 4 lanes, and the construction of Ky Ha 3 Bridge (right branch) with the same scale of 4 lanes.

The items in phase 3 have an investment of VND 312 billion, expected to be completed in April 2026.

Phoi canh nut giao My Thuy khi hoan thanh.  Anh: Ban Giao thong TPHCM
Perspective of My Thuy intersection when completed. Photo: Ho Chi Minh City Traffic Department

The My Thuy intersection project is designed with three floors and has been implemented since 2016, with a total investment of about VND 1,826 billion for the construction project.

The project has completed some items in phases 1 and 2, and put into operation from 2019 to 2021. The completed items include: Ky Ha 3 Bridge (left branch); left underpass from Ring Road 2 to Cat Lai Port; overpass on Ring Road 2 (left branch); My Thuy 3 Bridge.

Mot so cau vuot, ham chui hoan thanh o nut giao My Thuy (TPHCM). Anh: Anh Tu
Some overpasses and underpasses have been completed at My Thuy intersection (HCMC). Photo: Anh Tu

From the end of 2023, projects such as the left overpass from Cat Lai to Phu My and Ky Ha 4 bridge will also be implemented. However, the project's progress is still facing many difficulties due to the completion of site clearance.

Hang muc cau Ky Ha 4 dang tam dung vi vuong mat bang.  Anh: Anh Tu
The Ky Ha 4 bridge project is temporarily suspended due to land clearance problems. Photo: Anh Tu

Component project 2 related to compensation, site clearance and resettlement has a total investment of 1,623 billion VND, managed by the Thu Duc City Construction Investment Project Management Board.

The project needs to clear the land on an area of 16.6 hectares, affecting 195 households. However, by the end of January 2025, Thu Duc City had only handed over 9/195 cases, affecting the overall progress.

The Ho Chi Minh City Traffic Construction Investment Project Management Board recommends that the Thu Duc City People's Committee urgently complete site clearance work, ensuring the handover of 100% of the site before April 30, 2025 for construction of the remaining items.

Du an nut giao My Thuy con vuong
My Thuy intersection project still has 186 land clearance problems. Photo: Anh Tu

According to Mr. Luong Minh Phuc, the entire My Thuy intersection project will be completed by April 30, 2026.

The completion of My Thuy intersection along with key infrastructure projects such as the expansion of Nguyen Thi Dinh, Nguyen Duy Trinh, Luong Dinh Cua streets, the Cat Lai - Phu Huu port inter-line, Ho Chi Minh City - Long Thanh - Dau Giay expressway, An Phu intersection, Tang Long bridge, Ong Nhieu bridge... are expected to contribute to reducing traffic congestion in the Cat Lai port area and the eastern gateway of Ho Chi Minh City.

Phoi canh nut giao My Thuy khi hoan thanh.  Anh: Ban Giao thong TPHCM
Perspective of My Thuy intersection when completed. Photo: Ho Chi Minh City Traffic Department

In addition, these projects also help improve the capacity of freight transport, increase the competitiveness of the Cat Lai - Phu Huu port cluster, facilitate people's travel, urban beautification and promote the urbanization of Thu Duc City.

MINH QUÂN
TIN LIÊN QUAN

HCMC will enforce 4 land plots for the construction of roads worth VND41,387 billion

|

Ho Chi Minh City - Thu Duc City plans to enforce land acquisition for 4 cases that have not yet handed over the site for the construction of the Ring Road 3 project with a total capital of more than VND 41,387 billion.

The largest intersection in Ho Chi Minh City is about to open the first underpass

|

HCMC - The underpass from the HCMC - Long Thanh Expressway to Mai Chi Tho is 760m long, with 4 lanes, part of the An Phu Intersection project (Thu Duc City) and will open to traffic before April 30.

The 14 km long elevated road connecting Ho Chi Minh City - Binh Duong is about to open

|

HCMC - The elevated road section of more than 14 km long, with 4 lanes passing through Thu Duc City, connecting with Binh Duong province (under Ho Chi Minh City Ring Road 3) will open to traffic at the end of 2025.

Starting construction of Hon La International Port Project worth nearly VND2,300 billion

|

Quang Binh - The Hon La General Port Project worth nearly VND2,300 billion has been started, which is a favorable condition for connecting goods from Laos, Thailand, and Myanmar.

80 people extinguish the fire that spread on a hill in Binh Thuan

|

Binh Thuan - About 80 people from many forces together extinguished the fire spread on the hill with lentils near Tau Mountain.

2,100 US Department of Education employees are at risk of being fired

|

President Donald Trump signed an executive decree on March 20 to begin the dissolution of the US Department of Education.

What will the Vietnam team fix before the match against Laos?

|

In the Sports Perspective program No. 207, Commentator Quang Tung pointed out the issue that the Vietnamese team needs to pay attention to before the match against Laos in the 2027 Asian Cup qualifiers.

EU has a surprising decision on confiscating Russian assets

|

The EU has unexpectedly rejected plans to seize frozen Russian assets.

HCMC will enforce 4 land plots for the construction of roads worth VND41,387 billion

MINH QUÂN |

Ho Chi Minh City - Thu Duc City plans to enforce land acquisition for 4 cases that have not yet handed over the site for the construction of the Ring Road 3 project with a total capital of more than VND 41,387 billion.

The largest intersection in Ho Chi Minh City is about to open the first underpass

MINH QUÂN |

HCMC - The underpass from the HCMC - Long Thanh Expressway to Mai Chi Tho is 760m long, with 4 lanes, part of the An Phu Intersection project (Thu Duc City) and will open to traffic before April 30.

The 14 km long elevated road connecting Ho Chi Minh City - Binh Duong is about to open

MINH QUÂN |

HCMC - The elevated road section of more than 14 km long, with 4 lanes passing through Thu Duc City, connecting with Binh Duong province (under Ho Chi Minh City Ring Road 3) will open to traffic at the end of 2025.