Billion-dollar pumping station, paid for before acceptance and abandoned for more than 4 years

PHÚC ĐẠT |

The pumping station project worth 1.5 billion VND in Huong Phong commune (Hue city) has been abandoned for more than 4 years. It is worth mentioning that when the project could not be operated and had not been accepted, the investor, the People's Committee of Huong Phong commune, used the money to pay the construction unit.

4 years of abandoning a billion-dollar project

According to the people in Huong Phong commune (Hue city), a local electric pumping station has been abandoned for many years, showing no signs of operation, causing waste.

According to records at the construction site of Electric Pumping Station 15 (in Van Quat Dong village, Huong Phong commune, Hue city), Electric Pumping Station 15 has a design of 2 small attics, construction area of ​​about 27m2; inside there are 2 pumps and suction tank, discharge tank.

It is known that the 15 Van Quat Dong electric pumping station project has a total investment of 1.5 billion VND, invested by the People's Committee of Huong Phong commune, started construction on September 3, 2019 and must be completed within 120 days (ie the project will be accepted and put into operation in early January 2020).

The purpose of the project to build a pumping station is to improve the agricultural life of the people; increase production efficiency, develop the local socio-economy, improve the quality of life of rural residents, contributing to gradually achieving the New Rural standards. Contrary to the original purpose, more than 4 years have passed, this 1.5 billion VND pumping station project is still unable to operate because it is not completed, has not been able to coordinate any drop of water to serve the seasonal cultivation process of the people and has been abandoned, causing a waste of resources.

Payment but not yet acceptance of the project

According to the project documents provided by the People's Committee of Huong Phong commune, of the total investment capital of 1.5 billion VND, there are more than 881 million VND for construction and installation costs, more than 271 million VND for equipment costs, more than 148 million VND for construction investment consulting costs, 32 million VND for project management costs and more than 102 million VND for contingency costs.

The project was invested by the People's Committee of Huong Phong commune (at that time, Huong Phong commune belonged to Huong Tra town, now the commune has merged into Hue city). The unit implementing the above project is An Nhien Urban Environment and Construction Company Limited (located in Huong Van ward, Huong Tra town, Thua Thien - Hue province). The investment capital for the project is 1.19 billion VND from the central budget, the rest is from the budget of Huong Tra town, Huong Phong commune and people's contributions.

Four years ago, when the project had not yet been put into operation and accepted, the People's Committee of Huong Phong commune had paid all costs to the construction unit, contrary to regulations.

Regarding the above issue, Mr. Phan Huu Vinh - Vice Chairman of Huong Phong Commune People's Committee - said that the reason why the project could not be put into operation was because the unit that designed the electrical profile did not provide the electrical profile of the pumping station to the locality, leading to the project not being energized for operation. Meanwhile, the fact that the project had not been accepted but the investor, Huong Phong Commune People's Committee, had paid all costs to the construction unit, Mr. Vinh admitted that the above action was completely against the regulations.

Speaking with Lao Dong, Mr. Vo Le Nhat - Chairman of Hue City People's Committee - said that the city has grasped the incident and will conduct a review, request the Commune People's Committee to report and have the most appropriate handling plan.

PHÚC ĐẠT
RELATED NEWS

Hai Duong proposes to invest 120 billion VND to renovate 84 pumping stations

|

Hai Duong - The Department of Agriculture and Rural Development of Hai Duong proposed that the province invest in upgrading and renovating 84 seriously degraded pumping stations.

Pumping station operates at full capacity to prevent flooding in Hanoi

|

After storm No. 3, Yen So Pumping Station continued to mobilize human resources to carry out flood prevention work for the Hanoi area.

Transfer the case file related to the Usilk City Project to the Ministry of Public Security for consideration and investigation

|

The Government Inspectorate transferred the case file related to the Van Khe Expanded Urban Area Project (Usilk City) to the Ministry of Public Security for consideration, investigation and handling.

Commune-level civil servants who do not meet professional requirements will be sent for training

|

100% of commune-level officials and civil servants who do not meet the professional requirements of the job position will be sent to train in knowledge.

Recall of HiPP weaning jar suspected of being contaminated with rat poison, many families worried

|

The Ministry of Health urgently requested the recall of HiPP weaning jars and advised people to stop using them due to suspected rat poisoning, causing many families who used to give them to their children and grandchildren to worry.

Stocks recover thanks to Bluechip but lack liquidity

|

The stock market regained its upward momentum thanks to bluechip stocks showing signs of recovery, but liquidity decreased sharply.

Ministry of Education and Training requests review and identification of violations in the case of high school learning without graduating from secondary school in Quang Tri

|

Quang Tri - Regarding Mr. Vo Danh Thuan's high school education before graduating from secondary school, the Ministry of Education and Training affirmed that according to regulations, he must have a secondary school diploma when entering 10th grade.

7.5 magnitude earthquake off the coast of Japan, tsunami warning up to 3m high

|

A magnitude 7.5 earthquake occurred off the northeastern coast of Japan, leading to a tsunami warning of up to 3m, according to the Japan Meteorological Agency.

Hai Duong proposes to invest 120 billion VND to renovate 84 pumping stations

Công Hòa |

Hai Duong - The Department of Agriculture and Rural Development of Hai Duong proposed that the province invest in upgrading and renovating 84 seriously degraded pumping stations.

Pumping station operates at full capacity to prevent flooding in Hanoi

Nhóm PV |

After storm No. 3, Yen So Pumping Station continued to mobilize human resources to carry out flood prevention work for the Hanoi area.

Cưỡng chế thu hồi đất phục vụ Dự án Trạm bơm tiêu Yên Nghĩa

KHÁNH AN |

Sáng 18.9, quận Hà Đông (Hà Nội) tiến hành cưỡng chế thu hồi đất tại phường Quang Trung để phục vụ Dự án Trạm bơm tiêu Yên Nghĩa.